1 / 25

Transmission Needs Analysis Scenario 5/7 Update

Transmission Needs Analysis Scenario 5/7 Update. December 7, 2012. Agenda. Review Scenario Characteristics Review Incremental Resources Review Base Case Upgrades Economic Analysis Key Lessons (S5/S7) LTSA Previews. Scenario Characteristics. Scenario 5: Drought

nmaine
Download Presentation

Transmission Needs Analysis Scenario 5/7 Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Transmission Needs AnalysisScenario 5/7 Update December 7, 2012

  2. Agenda • Review Scenario Characteristics • Review Incremental Resources • Review Base Case Upgrades • Economic Analysis • Key Lessons (S5/S7) • LTSA Previews

  3. Scenario Characteristics Scenario 5: Drought • Characterized by extended drought • Summer capabilities of existing water-consuming resources de-rated • New water-consuming resources sited primarily in the East • Water costs are assigned to water-intensive resources • Increased peak load Scenario 7: BAU – Hi Natural Gas • Characterized by a high natural gas price ($9.55 by 2016, $13.70 by 2022) • Resources retire in 2018 and 2022 for competitive reasons

  4. Resource Build: Scenario 5

  5. Scenario 5 Resources

  6. Base Case Thermal Reliability Upgrades – Scenario 5 (2022) • Water availability and higher LMP’s drive thermal/gas expansion units to areas East/South of Dallas and North of Houston. • New resources East and South of the Dallas Metro area caused base-case overloads • New resources North of Houston created increased congestion and overloads on the 345 kV imports North – Houston.

  7. Scenario 5: Base Case Reliability Upgrades *Note: Houston imports were upgraded in preparation of the base case, though “backed out” in reliability analysis. The upgrade of the existing North to Houston imports is likely unfeasible.

  8. Scenario 5: AC Stability Limitations *Assumes no incremental gas units are built in the LRGV

  9. Scenario 5: Most congested elements • Most Congested Elements in S5: • Twin Oak-Jack Creek, • Jack Creek-Gibbons Creek, • Gibbons Creek-Singleton, • Jewett-Singleton • (north of Houston region) • Hill Country-Skyline • (San Antonio region) • Dallas interface congestion

  10. Scenario 5: Economic Analysis

  11. Scenario 5: Key Lessons • Water availability and higher LMPs draw new resources East / Southeast of Dallas and North / Northwest of Houston • Increased peak loads increase stress on the 138kV systems in and around Houston / Dallas • Base case overloads are more prevalent on existing urban import paths • Heavy congestion North – Houston supports economic transmission expansion for expanded import capacity into Houston

  12. Scenario 7: Resource Build

  13. Scenario 7: Resources / Retirements

  14. Scenario 7: Base Case Thermal Reliability Upgrades • Large amount of wind generation at Panhandle area, load forecasted for 2022 and other incremental resources assumed in the scenario result in: • Major 345 kV line upgrades in Panhandle area to accommodate large amount of wind • generation, • Some 345 kV line upgrades around Houston area and other transmission upgrades • needed for urban areas primarily driven by load serving issue

  15. Scenario 7: AC Stability Limitations * Need for analysis in Scenario 7 because of massive build-out of wind in the Panhandle region

  16. Scenario 7: Base Case Reliability Upgrades

  17. Scenario 7: Most congested elements • Most Congested Elements in S7: • Panhandle interface limit • Singleton-Zenith and other 345 kV lines around Singleton area (north of Houston region) • Parker-Benbrook 345 kV line (west of DFW region)

  18. Scenario 7: Economic Analysis

  19. Scenario 7: Economic Analysis

  20. Scenario 7: Key Lessons • An increase in NG price favors renewable expansion • Favorable wind profiles drive interconnected wind on the CREZ system beyond full-build out design capability • Stability limitations for increasing transfers from the Panhandle to load require further study, new infrastructure • Increased congestion (due to urban retirements) supports economic transmission expansion for imports into Houston, Dallas, and San Antonio

  21. Questions?

  22. LTS Preview / Summary Data

  23. Renewable Resource Integration Retirement BAU -New Wind Drought Hi Nat Gas Environmental

  24. Upgrade Summaries

  25. Upgrade Summaries 1 – BAU 2 - Retirement 3- BAU / New Wind 5a –Drought 7 - Hi Nat Gas

More Related