RPC Upscope : An overview with Indian perspective. L. M. Pant Nuclear Physics Division Bhabha Atomic Research Centre. L. M. Pant India-CMS Meeting, BARC 29 th July 2010.
E N D
RPC Upscope : An overview with Indian perspective L. M. Pant Nuclear Physics Division Bhabha Atomic Research Centre L. M. Pant India-CMS Meeting, BARC 29th July 2010
The first level trigger based on the RPCs provides CMS with the most precise timing in both the barrel and endcap region Six concentric layers of chambers are used in the barrel part, while four layers have been foreseen in total for the end caps to cover a rapidity up to =2.1 L. M. Pant India-CMS Meeting, BARC 29th July 2010
barrel end-cap end-cap CMS Present end-cap RPC coverage upto 3 layers High region FRPC upgrade 2011(?) 666 cm Longitudinal section of CMS pseudorapidity, = - ln tan(/2) Is the polar angle of the particle wrt the beam axis Trigger detector RPC’s : both Barrel & End-Cap : = 0 to 2.1 Tracking detector Barrel : Drift Tubes : = 0 to 1.2 End-cap : Cathode Strip Chambers : = 0.9 to 2.1 RPCs are segmented in strips of x ~ 0.1 x (5/16)o which makes possible a pT measurement of ~ 50 GeV L. M. Pant India-CMS Meeting, BARC 29th July 2010
=0 due to insufficient funding availability, only three layers were built in the endcap which provided a limited rapidity coverage up to =1.6 =1.2 =1.6 China end-cap end-cap barrel section in 5 wheels Pakistan L. M. Pant India-CMS Meeting, BARC 29th July 2010
chambers could be constructed later on so that coverage of the full rapidity range of the original design could be achieved The key element of this proposal is to construct the 4th layer of RPCs in the endcap L. M. Pant India-CMS Meeting, BARC 29th July 2010
simulated trigger efficiency plot : Piet Verwilligen the 4th layer is in between = 1.2 and 1.6 small dips are due to an interface between different rolls in one chamber = 1.24 = 1.42 L. M. Pant India-CMS Meeting, BARC 29th July 2010
The key element of this proposal is to construct the 4th layer of RPCs in the endcap =0 =1.2 =1.6 China end-cap end-cap barrel section in 5 wheels Pakistan India & Belgium L. M. Pant India-CMS Meeting, BARC 29th July 2010
CMS has decided to split the up-scope project into two distinct phases : Phase 1 : completion of the low part ( < 1.6) Phase 2 : (earlier called as upgrade) completion of the high part (1.6 < < 2.1) L. M. Pant India-CMS Meeting, BARC 29th July 2010
Second layer of gas-gaps with gas flow pipes L. M. Pant India-CMS Meeting, BARC 29th July 2010
Bakelite gas-gaps enclosed inside the Faraday Cage April '2008 L. M. Pant India-CMS Meeting, BARC 29th July 2010
Fully assembled RPC with front end electronics, gas flow pipes, cooling pipes, HV and signal cables L. M. Pant India-CMS Meeting, BARC 29th July 2010
L. M. Pant India-CMS Meeting, BARC 29th July 2010
96 65 64 33 32 1 Not dead channels, problem with shift registers in the electronics Strip profile of cosmic events : 5K triggers RPC # 6, run No. 5135, 5K triggers at 9.4 kV L. M. Pant India-CMS Meeting, BARC 29th July 2010
presented during RPC-2010 at GSI L. M. Pant India-CMS Meeting, BARC 29th July 2010
presented during RPC-2010 at GSI L. M. Pant India-CMS Meeting, BARC 29th July 2010
Expected financial contribution for low upgrade 4.5 MCHF 18% India L. M. Pant India-CMS Meeting, BARC 29th July 2010
~1000 kCHF per sector ( end caps) ~ 800 kCHF per sector ( end caps) ~ 1.2 ~ 1.6 Cost per sector for low (RE2/2, RE2/3) L. M. Pant India-CMS Meeting, BARC 29th July 2010
L. M. Pant India-CMS Meeting, BARC 29th July 2010
RPCs to be built for low upgrade 144 + 56 extra = 200 BelgiumIndia 100 + 100 = 200 RPCs L. M. Pant India-CMS Meeting, BARC 29th July 2010
The manpower to run this facility will be provided by the respective institutes when their detectors are being tested Chamber Assembly Sites Mumbai, Chandigarh L. M. Pant India-CMS Meeting, BARC 29th July 2010
Responsibitities of each collaborating unit L. M. Pant India-CMS Meeting, BARC 29th July 2010
July’10 Aug ’10 Oct ’10 Dec ’10 Dec ’11 We are here HPL production Start up for production of gas-gaps, mechanics, electronics Assembly sites to be ready Testing, Comissioning & Complete Installation The road map HPL : 2 months are required for the production of 600 foils x (1620 x 3200 mm2) = 3110 m2 Gas-Gaps : production of 600 gas-gaps for 200 chambers would take about 12 months L. M. Pant India-CMS Meeting, BARC 29th July 2010
Summary • Ten RPCs sent to CERN are certified “Cosmic test OK” • RPC lab., at NPD-BARC is fully equipped to undertake • the assembly and testing following the QA/QCs as set by • CMS-RPC group • The Panjab University RPC lab is also equipped • with a 4-channel gas-mixing unit, • DAQ for the Cosmic Ray test, • scintillator hodoscopes, • mechanical and electrical workshops, L. M. Pant India-CMS Meeting, BARC 29th July 2010
Outlook • A/C with dehumidifiers for the RPC lab. at NPD-BARC • (civil work to start; commissioning by Dec. 2010) • Large area scintillator (18 cm x 200 cm) paddles for chamber • efficiency, cluster size and strip profile measurements • (to be ready by Nov. 2010) • VME based DAQ for 96 channels to measure all physical working • parameters for the chambers • (operational by March 2011) • Once the chambers are assembled, a complete test with a • cosmic hodoscope will be performed before the transportation • to CERN • Fabrication of a new cosmic rack (ready by Dec 2010) • the present cosmic rack to be used as a storage device • The Panjab University RPC lab. is also ready • (fully functional by Dec., 2010) L. M. Pant India-CMS Meeting, BARC 29th July 2010