E N D
1. Tempting Templates Project Status Report # 2
2. 4/01/2003 Tempting Templates - Status Report #2 2 Agenda Review Project Objectives
Milestone status & Earned Value Tracking
Summary of Results
Details of Task Activity
Plan Changes
Updated Gantt Chart
3. 4/01/2003 Tempting Templates - Status Report #2 3 Project Objectives Search for project management templates from the Internet and/or literature.
Provide an organized list of templates grouped by web site, process group, and knowledge area.
Provide a qualitative evaluation of web sites.
Provide recommendations for the list of templates to be included in an appendix of the 3rd edition of the textbook.
4. 4/01/2003 Tempting Templates - Status Report #2 4 Milestones
5. 4/01/2003 Tempting Templates - Status Report #2 5 Earned Value Analysis(chart on next page) Saved project baseline at beginning of project.
Assumed $30/hour labor rate for all team members.
Earned value chart shows us as late/over-budget. Real story not that bad.
Have achieved milestones on schedule.
We underestimated time commitment
We have used all project buffer.
Expect to achieve the remaining deliverables on schedule.
6. 4/01/2003 Tempting Templates - Status Report #2 6