250 likes | 369 Views
Delay and project profitability. Sigurður Guðni Sigurðsson September 2007. Delay and project profitability . Presumptions. Total time = Production time + Time of utilization Total time is constant Period of production 1 year, duration of operations 5 years Affect on producer/developer
E N D
Delay and project profitability. Sigurður Guðni Sigurðsson September 2007
Delay and project profitability. Presumptions Total time = Production time + Time of utilization Total time is constant • Period of production 1 year, duration of operations 5 years • Affect on producer/developer • Affect on buyer • Period of production 3 years, duration of operations 10 years • Affect on producer/developer • Affect on buyer • Lump sum payment vs. distributed payment
Reason of delay. Contract variation. • The owners (buyer) determination that makes delay and extra cost on his accountability. • Force Majeure. Neither seller or buyer have any control of the cause. The seller can delay the project of such reasons. • Delay based on sellers action. The seller is responsible and pays for it with penalty.
Short project . Sellers presumptions Fixed contract price– Payment on delivery. • Cost estimate Kr. 1.000.000 • Contribution margin 30% • Contract price Kr. 1.428.571 • Duration of production 12 months • Penalty 5 % per month • Maximum penalty 15% • Fixed cost per year 7,5% • Cost of capital 8% • Inflation 4%
Short project Buyers presumptions • Investment – no delay Kr. 1.428.571 • Operation cost per year Kr. 1.000.000 • Markup 70% • Lifetime 5 years • Financial cost 6 % • Fixed cost per year Kr. 75.000 • Inflation 4% • Return on capital 20%
Internal Rate of Return based on income distribution and delay.
Long project period. Sellers presumptions Fixed contract price – Payment on delivery. • Cost estimate Kr. 1.000.000 • Contribution margin 34,1% • Contract price Kr. 1.517.451 • Duration of production 3 years • Penalty 2,5 % per month • Maximum penalty 15% • Fixed cost (36 months) Kr. 75.000 • Financial cost 8% • Inflation 4%
Long project. Buyers presumptions • Investment – no delay Kr. 1.517.451 • Operation cost per year Kr. 1.000.000 • Markup 50% • Lifetime 10 years • Financial cost 8 % • Fixed cost per year Kr. 75.000 • Inflation 4% • Return on capital 20%
Distributed payment . Long project Two payment series • Four payments: Payment order Month. Percentage Dawn payment 0 10,0% Payment # 2 12 25,0% Payment # 3 24 25,0% Final payment 36 40,0% • Four payments - 85% of earned value at each time
Conclusions I • Time and cost in projects have strong connection. • Delay harm both seller and buyer. • The buyers protection by using penalties protect him only if income is low in the delay period or the delay is short. • It is of common interest that the production period is successful. • The length of the production period and lifetime of the product does not influence the results strongly. • Sensitivity for changes in presumptions increase with longer delay.
Conclusions II • The distribution of the income affects the delay impact. More impact as the delivery is later in the product life-cycle. • It is of great interest to study further interaction between distributed payment and profitability of projects. • The impact of distributed payments are often higher than penalty. • Distributed payment is of high value for the seller. • Distributed payment cost the buyer more as the delay increase.