An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Utility Procurement 2004

  2. Utility Procurement 2004Presenter: Albert A. Stephens, CPMDirector of Supply Chain ManagementLos Angeles Department of Water and Power

  3. Supply Chain Management with e-Commerce Solutions Provide Savings, Access Parity, Quality Products and Services For Less

  4. LADWP Quick Facts • Established in 1902 to deliver water • Electric distribution began in 1916 • Today, largest municipal utility in the nation • 2003-2004 Budget: $3.04 billion (water and electric)

  5. LADWP Quick Facts • 5 – member Board of Water and Power Commissioners • Appointed by the Mayor • Confirmed by the City Council for 5-year term

  6. LADWP Quick Facts • Workforce: 8,100 employees • Area Served: 464 square miles • Population Served: 3.8 million residents • 2025: 30% growth expected

  7. Water Service Connections: 670,000 • Water Usage: 194 billion gallons • Residential: 427,627 acre-feet (64%) • Commercial/Gov: 146,575 acre-feet (24%) • Industrial: 22,393 acre-feet (3%) • Other: 67,030 acre-feet (6%) • Pipe: 7,100 miles

  8. Electric Service Connections: 1.4 million • Total Generating Capacity: 7,000 megawatts • Los Angeles Peak Demand: 5,200 megawatts

  9. ELECTRICITY USAGE • Residential: 6,531,813 megawatt-hours (30%) • Commercial: 12,901,820 megawatt-hours (59%) • Industrial: 2,382,942 megawatt-hours (11%) • Number of Poles: 290,239 • Number of Street Lights: 250,000

  10. CUSTOMER DIVERSITY • Caucasian: 55.1% • Hispanic: 40.3% • Asian: 10.4% • African American: 7.6% • Native American: .9%

  11. Supply Chain Management and e-Procurement Goals Seems impossible? MISSION POSSIBLE

  12. Supply Chain Management and e-Procurement Goals • Increase access to the local and diverse business community • Have accurate and timely reporting for purchase, procurement, construction, and professional services contracts • Improve the efficiency of the Department’s internal buying operations • Increase accountability and control • Reduce the processing time from requisition to award through payment

  13. ACCOMPLISHMENTS

  14. Accomplishments • Business Process Improvements • Eliminated the number of outdated policies by 2/3 • Restructured Buyer Groups and Process Flow • Implemented new review and approval process for all requisitions • Utilized Technology Tools • e-commerce solutions • Transparent purchasing process • Decreased processing time • Increased diverse business contract awards • Increased accountability and control • Supply Chain/CPS Internal Accomplishments • Comprehensive internal training program • Collaborative efforts (Accounts Payable) • Supply Chain Links Newsletter • Customer Survey/Forums

  15. COST SAVINGS

  16. Cost Savings • Implemented a cost savings program that will save the Department $20 million per year by 2004 • Currently with 60% implementation, hard savings are $10.3 million to date • Reduced processing time by an average of 35% from contract requisition to award • 57% savings in processing informal bids

  17. Cost Savings for BiddingNETTMFor Period 1/2002 – 3/2004 Savings: $12,160,355 Avg. Monthly Savings: $450,384

  18. Cost Savings Source: FSO Study, November 2002

  19. Measurable Improvements *Projected figures based on contract dollars awarded through April 2003.

  20. Diverse Business Enterprise Activity *Projected figures based on contract dollars awarded through April 2003.

  21. Diverse Business Enterprise Activity *Projected figures based on contract dollars awarded through April 2003.

  22. Diverse Business Enterprise Activity *Projected figures based on contract dollars awarded through April 2003.

  23. SUPPLY CHAINMANAGEMENT

  24. The ‘three T’s’ to optimize the supply chain processes and structures:

  25. Time • Transparency • Trust Source: Dr. Richard Wilding Cranfield School of Management, UK

  26. Conceptual Overview: DWP Supply Chain Implementation Progression PURCHASING • Paper Meetings Files, Copies Turf Claims Snail Mail, Telephone, Fax, Email Reactive Development of Services . . . . . .

  27. Conceptual Overview: DWP Supply Chain Implementation Progression SUPPLY CHAIN • Internet & Intranet Document Management Work Flow System Procure Essentials Advanced E Mail, Pager, Cell Phone Proactive Client Services Static Helpdesk, File Sharing Transparency Menu Driven Systems Cost Savings Increased Supplier Access Inventory Management . . . . . .

  28. Conceptual Overview: DWP Supply Chain Implementation Progression VALUE CHAIN • Internet, Intranet, Extranet Work Enhancement Logistics, Contract Management Economic Development Market Tracking By Information Push Interactive Catalog Auto Response Help Increased $ Availability Follow-Me Communications Hyperlink File Navigation Supplier Access Parity . . . . . .

  29. Supply Chain Management and e-Procurement Goals Seems impossible? MISSION POSSIBLE

  30. Supply Chain Management with e-Commerce Solutions • Savings – Time and Dollars • Access Parity • Quality Products and Services For Less