PROJECT PROGRESS REPORT As of February 24, 2014

ULTICON BUILDERS, INC. UBI Compound, Don Julian Rodriguez Ave., Ma-a, Davao City Tel . (082) 282-0280 / Fax. (082) 282-0631. PROJECT PROGRESS REPORT As of February 24, 2014

nyla
Download Presentation

PROJECT PROGRESS REPORT As of February 24, 2014

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ULTICON BUILDERS, INC.UBI Compound, Don Julian Rodriguez Ave., Ma-a, Davao CityTel. (082) 282-0280 / Fax. (082) 282-0631 PROJECT PROGRESS REPORT As of February 24, 2014 Road Upgrading (Gravel to Concrete) Based on Gravel Road Strategies, Traffic Benchmark for Upgrading to Paved Road Standard (HDM-4 Project Analysis, Intermittent Sections, Kapalong-Talaingod-Valencia, Bukidnon Road, K1589+954-K1591+425 Contract ID : 13KOOO163

  2. Original Contract Amount: P 28,296,495.72 PROJECT DESCRIPTION: • Road Upgrading from Gravel to Concrete ( W = 6.70m & T = 0.28m. ) • with 2.0m Shoulder. • Drainage & slope protection. • - Provision of traffic safety measures. PCCP LIMITS: PROJECT LIMITS: Beg. of Project : KO 1590+260 End of Project : KO 1591+590 GROSS LENGTH : 1,330.00 m. with widening NET LENGTH : 1,330.00m. • Beg. of Project : KO 1589+954 • End of Project : KO 1591+590 • GROSS LENGTH : 2,343.185 m. • GROSS LENGTH : 1,636m. W/ EXCEPTIONS Silae This Site • PROJECT PROFILE • Date Start : January 27, 2014 • Duration : 142 cal. days • Expiry Date : June 17, 2014 LOCATION MAP

  3. MANPOWER REQUIREMENTS PROJECT ENGINEER 1 SURVEYOR 1 LAB. TECH. 1 ADMIN OFFICER 1 WAREHOUSEMAN 1 EQUIPMENT CHECKER 1 HAULING CHECKER 1 DRIVERS/OPERATOR 5 SURVER AIDE 1 MECHANIC 1 TIREMAN 1 WELDER 1 FROM KAHAPONAN PLANT FOREMAN 2 BATCHING CREW 3 FLAGMAN 3 TOTAL 16

  4. CONTRACT STATUS ACCOMPLISHMENT : ACTUAL % Actual Accomplished : 5.39% % Schedule : 18.95% % Slippage : (-) 13.56% DPWH REPORT % Accomplished : 3.00% % Schedule : 2.54% % Slippage : 0.46% TIME ELAPSED : Time Elapsed : 30 CD / 142 CD % Time Elapsed : 21.12% Time Remaining : 112CD

  5. EQUIPMENT REQUIREMENTS ROAD GRADER 1 ROAD ROLLER 1 BACKHOE. 1 DUMP TRUCK 3 TRANSIT MIXER 2 TOTAL 8

  6. STATEMENT OF WORK ACCOMPLISHEDAs of February 24, 2014

  7. UPDATES ON MAJOR ITEMS Item 311 – PCCP ACCOMPLISHMENTS Contract Quantity In Length = 2,660m. @ 6.7m Width Actual Quantity In Length = 186.0m. Single Lane Balance Quantity In Length = 2,474.0m. Single Lane

  8. THE END