Wind Turbine Project Design Review. December 11, 2009. BGI. Introduction. Wind Turbine Project. Jared Freyer (Project Leader, Webmaster) Senior, Mechanical Engineering Fahad Ahmad (Recruitment Officer) Sophomore, Mechanical Engineering Anthony Christie Freshman, Engineering
E N D
Wind Turbine ProjectDesign Review December 11, 2009 BGI
Introduction Wind Turbine Project • Jared Freyer (Project Leader, Webmaster) • Senior, Mechanical Engineering • Fahad Ahmad (Recruitment Officer) • Sophomore, Mechanical Engineering • Anthony Christie • Freshman, Engineering • Yuanhua Cheng • Freshman, Engineering 2 BGI
Project History Wind Turbine Project • Created by Purdue BGI Club • Developed to create a wind turbine feasibility study prarieroots.files.wordpress.com 3 BGI
University Need Wind Turbine Project • Promote the sustainability and need for wind power in Indiana • Using the wind turbine as a living laboratory • Possibilities • Design new/efficient turbine blades • Design new/efficient turbine engines • Study wind/weather on Purdue’s campus • Provide power to the intramural field lights and feed power back into the Purdue power grid 4 BGI
Goals of the Project Wind Turbine Project • Get approval from Capitol Projects Council to allow a wind turbine to be constructed • Fundraise money to construct a wind turbine on campus • Make an educational component to go with the wind turbine 5 BGI
Past Work (Spring 2009) Wind Turbine Project • Did Initial Planning • Researched Optimal Location for Turbine • Researched Optimal Class of Turbine 6 BGI
Location Requirements Wind Turbine Project • Height • Height of turbine and crane for installation restricted to 756 ft above sea level • Due to FAR Part 77 • Structure may not be more than 150 ft above airport elevation • Purdue Airport sits at 606 ft above sea level • Electrical Tie-ins • Duke Energy lines west of McCormick Rd • Purdue power lines east of McCormick Rd • Wind Quality • Determine where the most consistent wind power can be found • Generally related to topography of region 7 BGI
8 BGI
Site of Interest Wind Turbine Project • Planned installation near the intramural fields • Site is close to the northwest substation • In close proximity to Purdue power lines • Higher elevation than surrounding area • Highly visible to Purdue students • Proximity to campus would allow for easier educational access 9 BGI
10 BGI
Turbine Site Grid Interconnect 11 BGI
12 BGI
13 BGI
Turbine Selection Wind Turbine Project • Large Wind (≥ 1 MW) • Due to siting restrictions large turbines will not be possible • Medium Wind (50 kW to 500 kW) • More feasible with height restrictions • Less efficient than large wind • Small Wind (1.5 kW to 50 kW) • Much less efficient than larger sizes • Less attention demanded 14 BGI
Current Work (Fall 2009) Wind Turbine Project • Finalized Decision on Turbine Selection • Calculated Local Average Wind Speeds • Presented Proposal to ALDP • Submitted CPC-1 Paperwork 15 BGI
Turbine Selection Wind Turbine Project 16 BGI
Redriven 20 kW Wind Turbine Project • Power output • 20 kW rated power output @ 25 mph • 240 V /60 hz / 1 Phase • Features • 79 ft tall tower • 20 ft long blades • 61 dB at a distance of 25 feet • Self-erecting • Electric Yaw Controller • Dynamic Brake System www.energyeducation.tx.gov www.redriven.ca 17 BGI
Redriven 20 kW Wind Turbine Project www.redriven.ca 18 BGI
Average Wind Speeds for West Lafayette Wind Turbine Project Average Wind Speeds: Low Bound: 5.88 m/s High Bound: 7.39 m/s 19 BGI
Average Power from ReDriven 20kW Wind Turbine Project Average Power: Low Bound: 4.65 kW High Bound: 8.19 kW 20 BGI
21 BGI
22 BGI
Turbine: 99 ft (30 m) tall 650 ft (198 m) above sea level Bell Tower: 160 ft (49 m) tall 620 ft (189 m) above sea level 23 BGI
Project Expenses Wind Turbine Project • Total CO2 Offset Per Year • 52.5 tons/year (DOE/EPA) • Equivalent to 157,500 miles/year for 30 MPG car 24 BGI
CPC Process Wind Turbine Project • Capitol Projects Council • Components • CPC-1 and CPC-2 • CPC-1 Program Benchmarks • Relevance to University Strategic Plan • Educational Aspect • Alternatives Considered • Personnel (Construction and Maintenance) • Cost Estimate and Location • ALDP Recommendation 25 BGI
University Strategic Plan Wind Turbine Project • New Synergies (2008 – 2014) • Strategies common to all goals • Promote sustainability conscience • Exemplify Purdue as living laboratory • Strategies specific to each goal • Engage students in experimental learning through hands on experiences • Civic engagement through campus design projects 26 BGI
Time Table (Fall Semester) 27 BGI
Future Plans Wind Turbine Project • Analyze safety precautions • Start Fund Raising • Private Funding vs. Actual Fund Raising • Requirements for CPC-2 • Maintain Communication with Contracting Company • Educational Component • Develop Website and Monitor Data 28 BGI
Educational Component Wind Turbine Project • Website • Real time data • Energy production totals • History of project/construction • Research • Potential for blade design and testing • Data monitoring www.redriven.ca 29 BGI