1 / 15

Managing Fixed Price Development Programs

Learn about critical areas to address when changing contract type on development contracts, including requirements definition, risk reduction, metrics, contract incentives, and post-award contract management.

ocarlson
Download Presentation

Managing Fixed Price Development Programs

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Managing Fixed Price Development Programs Presented by John Pritchard Professor of Contract Management Defense systems Management College

  2. Agenda • Trend Change • Critical Areas to Address when changing Contract Type on Development Contracts • Requirements Definition • Risk Reduction • Requirements Baselines • Metrics • Contract Incentives • Post Award Contract Management

  3. Critical Areas to Address in Development efforts • Requirements Definition • Realistic Requirements • Risk Reduction • Baselines • Design to Cost/CAIV • Metrics • Budgeting

  4. Requirements DefinitionRealistic Requirements • Realistic Requirements • Requirement process is even more critical in a Fixed Price environment • Unrealistic requirements can doom a program • All funds spent by the contractor reduce profit and/or come out of corporate funds • Trade off between “hard core” requirements and “nice to have” requirements • Must have realistic delivery schedules

  5. Requirements DefinitionRisk Reduction • Risk reduction involving tradeoff studies (early on) to weed out unrealistic requirements: • Producability • Supportability • Beyond the “state of the art” items • Beyond production capabilities of industry

  6. Requirements DefinitionBaselines • Baselines to which all parties have agreed! • User • Developer • Supporter • Changes should be kept to a minimum and rarely occur after tradeoff studies have addressed the impacts • Configuration Control Boards play a very critical role

  7. Contract Incentives • Positive or Negative Incentives or both? • Increase of Decrease Profit based on degrees of Success (or lack there of) • Objective or Subjective Incentives? • Avoid to many incentives Remember: You get what you incentivize, not what you intended to incentivize

  8. Incentivize Higher Quality • Increased Fee • Extended Contract Length • Follow-on Contracts Awarded • Accelerated Progress Payments (cash flow) • Shared Savings • Warranties • Performance Based Payments • Others?

  9. Post Award Contract Management • Effectively managing development contracts are highly dependent on limiting the amount of contract changes • Contract Cost Incentives may make contractors less willing to accept non official or just helpful advice as any change may, and probably will, affect profit • Baselines become more entrenched • Discipline by both sides is necessary any changes should be clearly stated, evaluated , priced and incorporated into the contract

  10. Post Award Contract Management • Acquisition Program Transition Workshop is advisable after award to: • Create an environment of teamwork, collaboration, communication and trust • Conducted jointly with government/contractor teams • High energy effort over a couple of days • Align Government and contract startup activities • Focus on improved program execution and communication

  11. Post Award Contract Management • Risk Assessment/Reduction should still be a primary consideration • Philosophy must be applied to ECPs or restructures • Keep careful watch on the contracts incurrence of cost and the availability of funding, especially on any incremental funding • Contractor is only obligated to work as long as the Government provides the incremental funding

  12. Post Award Contract ManagementMinimize Change Activity • As Dr. Carter stated “We on the Government side are assuming the risk of being able to articulate what it is exactly that we want and, then, not changing that notion.” • As children we were told to keep our hands to ourselves • As program mangers in fixed-price development, we should keep our hands off the contract. • Changes can be “profit in escrow” • If changes are needed, you will either need to find money and/or be prepared to back off requirements (i.e. adjust the baseline)

  13. Post Award Contract ManagementManaging Requirements Changes • Configuration Control Boards are crucial: • Establish an effective CCB Team • Establish a firm CCB process that all understand • Don’t allow requirements creep • No changes without either identifying the funds or reduction in the baseline to pay for the change

  14. Post Award Contract ManagementClaims • Under an FP arrangement - Contractors may be more willing to submit claims • Claims must be submitted within 6 years after the accrual of the claim • Contracting officer will review the claim and make a “Final Decision” • If contractors are not pleased with the final decision(s), under the Contract Disputes Act, they can appeal the decision via two routes • Administrative – Armed Services Board of Contract Appeals • Judicial – Federal Claims Court

More Related