FBI HEADQUARTERS. Renovation of the J. Edgar Hoover Building Washington, D.C. 2004-2008. Project Profile. 12 Story Building Constructed in 1972 1.2 Million SF of Federal Office Space Offices, High Security Floor (SCIF), FBI Tour, Dining, Secure Entrance. ARCHITECT.
E N D
FBI HEADQUARTERS Renovation of the J. Edgar Hoover Building Washington, D.C. 2004-2008
Project Profile 12 Story Building Constructed in 1972 1.2 Million SF of Federal Office Space Offices, High Security Floor (SCIF), FBI Tour, Dining, Secure Entrance
ARCHITECT Architectural /Interior Design Firm Government/Commercial Office Bldgs. / Interiors Called on firm for 8 Years Consulting Architect / Key Player on Team KCCT Architects
History with Architect McKissack & McKissack McKissack & McKissack Offices (24,000 sf) Mayor’s Office / Washington, D.C Department of the Treasury / Main Briefing and Conference Room KCCT State Dept HQ Renovation FBI HQ Renovation
Challenges (2004) Design Phase Established Bldg. Standard Justify Glasswool over Mineral Fiber (Cost / Aesthetics / Acoustic Performance) Specification: Advantage E/15 2x2
Challenges (2004) Bidding Phase Armstrong contractor applies pressure to GC regarding availability of Ecophon Made in the U.S. Policy brought to forefront Availability key concern for GC (10 wks to complete Floors 3 and 10)
Challenges (2004) Bidding Phase 90,000 SF Advantage E/15 2x2 available in warehouse (120,000 SF total /10 Wks) LML / PSD Meet w/ Wm. H. Walston / Kamco Delivery to Secure Facility (Distributor) Contract Award to CC / Wm. H. Walston & Company
Challenges (2005) Design Phase / 11th Fl. SCIF Secure Floor Requires Foil-Backed Ceiling to Aid in Scrambling Electronic Signals (90,000 SF / Phases I-IV) Ecophon Asks for Design Criteria None Available from Client LML / PSD Discuss Resources for Production Advantage E w/Foil Back to be applied in Canada Sample Panels Mfg’d / Excellent Quality Material named “Advantage Security”
Challenges (2005) Bidding / Phases I & II Specification: Advantage Security E/15 2x2 P&P (AWI contractor) Awarded Project Material required in 6 wks /Ecophon delivered in 4 wks. Phase I (20,000 SF) Delivered 5/05 Phase II (38,000 SF) Delivered 8/05 Reception Area w/Focus Wing Cloud
Challenges (2006) Bidding / Phases III & IV 9/12/06 P&P (AWI contractor) awaiting notice to proceed Quote Advantage Security E/15 2x2 52,000 SF Material to install late 4th qtr. Cost increases/scheduling (delete distribution) 10/25/06 Material ships to Canada for foil back Awaiting written order from P&P 10/28/06 Order released from P&P 12/20/06 Material arrives in US
Future Phases FBI / Director’s Office and Conf Room (3,000 SF Focus DG 2x2) FBI / Tour (55,000 SF Advantage E/15 2x2) Remaining Office Space (1,000,000 SF Advantage E/15 2x2)
Teamwork Communication