Field-BIM: RFID-Enabled Production Management on Skanska’s New Meadowlands Stadium. David Campbell, VP, Skanska Andy Dickey, Product Manager, Tekla Josh Kanner, VP, Founder, Vela Systems. Introductions (Josh?) Skanska (David) Project Overview Pain Points Tools & Selection
E N D
Field-BIM: RFID-Enabled Production Management on Skanska’s New Meadowlands Stadium David Campbell, VP, Skanska Andy Dickey, Product Manager, Tekla Josh Kanner, VP, Founder, Vela Systems
Introductions (Josh?) Skanska (David) Project Overview Pain Points Tools & Selection Vela Systems/Tekla (Josh/Andy) Approach & Key Features Live Demonstration Skanska (David) Benefits Q & A Agenda (draft)
Location: East Rutherford, NJ Site Development Costs: $189MM Building Costs: $809MM Total Construction Cost: $998MM Date of construction contract: January 23, 2007 Estimated date of completion: April 10, 2010 Area: 1.9 million-square-foot Seating: 82,500 spectators, including 200+ luxury suites. Project Overview
Delivery pressure due to sports schedule Lack of large laydown yard means tight production coordination necessary Can’t store pre-cast onsite Pick from truck and place into structure Need to coordinate production schedule across entire supply chain Project Pain Points
Mobile Field Software – Vela Systems Strong platform of field software modules includes Materials Tracking with RFID ‘built in’ Works disconnected on Tablet PC Proven implementation and integrations track record Building Information Model – Tekla Structures Key capabilities for structural elements in design and production Powerful support for extended attributes and rules Tools and Selection
1 Manufactured 2 Ready to ship 3 Received on Site RFID Tag RFID Tag RFID Tag TabletPC with RFID Reader Internet RFID Tag 4 Erected VelaSystems Servers (Vela Hosting Facility) 3D Model Meadowlands RFID Process Flow
“Key Fob” style tag Attached on wire loop to top of piece Both tag and piece have full piece number written on them Each tag has its own unique ID number Actual RFID tags in use Tag
Estimated financial benefit: Gain of 10 days on project schedule @ $100,000/day benefit = $1.0MM savings Real-time supply-side visibility into the status of pre-cast concrete components; Creating real-time communication and collaboration between key stakeholders and suppliers; Increasing accuracy by eliminating the cumbersome, error-prone paper-based process; From: Skanska-Vela-Tekla, AIA Technology in Architectural Practice Award Application, 1/31/08 Benefits
Focus: Mobile field applications for Tablet-PCs for construction (owners, contractors, architects, engineers, consultants) Core application modules – field activities – “field notebook” File Synchronization – “tube of drawings” + communication Company is combination of construction and technology expertise Enterprise software folks: Saved Motorola $600MM Construction folks: Managed $1B in costs Over 300 jobs deployed on 3 continents Proven integrations with Tekla™ Prolog™ and Primavera™ Vela Systems Overview