An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Steel Dynamics, Inc. Overview Gary M. Morris Manager - IT Steel Dynamics, Inc. Structural & Rail Mill November, 2006

  2. SDI FOUNDERS ‘Dick’ Teets Vice President General Manager – Structural & Rail Div Keith Busse President & CEO “Always producing a high-grade, high quality product at the lowest possible cost.” - K Busse Mark Millett Vice President General Manager – Flat Roll Division

  3. Steel Dynamics – Flat Roll Division Butler, IN.

  4. Steel Dynamics – Structural and Rail Division Columbia City, IN. Strategically located in the “Rust Belt” 450 Acres 2601 S 700 E Columbia City, IN. 46725 (866) 740-8700 Toll Free On US 30 between Columbia City and Fort Wayne Indiana

  5. APRIL 2000 pre-construction FEB. 2002 ~ 7/8 complete Steel Dynamics – Structural and Rail Division Columbia City, IN. Green-field Site $ 350 Milliontotal cost ~ $ 1 Million investment / employment position (at full staffing)

  6. Mill Process VTD Continuous Caster Semi - Finished Products EAF Scrap LMF Cooling Bed Structural Standard Reheat Furnace Hot Rolling Rail Premium Cut, Pile, & Bundle Structural Straightening Ship to Customer Rail Drill, Cut, End Straighten Inline Inspection

  7. Electric Arc Furnace(s)

  8. Electric Arc Furnace(s) Designed Capacity 1.2M tons / eaf / annum 142.5 ton/hr 50min tap-tap Spring 2003 36 – 45 avg min tap-tap Current environmental permitting allows operation of only one furnace at a time.

  9. Continuous Caster Exit of spray chamber Casting beam blanks Withdrawal Rolls Casting beam blanks

  10. Production Tracking

  11. A C Leadbetter Discharging BB2 @ 2250°F Reheat Furnance • Recuperative - Natural gas • 80’x50’ • 19’ - 47’ 6 bloom lengths • Walking Beam • 3 Zones: • Charge, Heat, Soak • Deep Charge • Heating Rate: • 356 Million Btu / hr • 300 ton/hr– hot charge • 200 ton/hr– cold charge

  12. Tandem / Combination Mill UF UR EDGER 7500 hp 7500 hp 5000 hp SMS - Schloemann

  13. Technology Control System TCS’s job is Roll Gap Adjustment • Roll gap calibration after roll change • Determination of passline after roll change • Determination of roll spring • Calculation of the position of the rolls => with the static Automatic Gage Control (AGC) before the rolling • Roll gap control (loop control) => with the dynamic Automatic Gage Control (AGC) during the rolling ( 1 sec cycle rate ) • Position control of the hydraulic cylinders (very fast loop control) in both mode, to keep the setted cylinder position of the rolls Precision: ± .05mm / .002” Precision: ± .02mm / .0008”

  14. Steel Dynamics, Inc. Question and Answer

  15. Problem Solving Communication Highly Analytical Enjoys challenges Time Management In-depth business knowledge Team oriented Programming - .NET, PowerBuilder, C#, C++, PLSQL, TSQL Strong GUI design Database design Wireless/RFID architecture Project Management Required Skills

  16. Problem Solving Communication Highly Analytical Math Time Management In-depth business knowledge Team oriented Skilled trades: pipe fitters, hydraulics, welding, electricians, mechanical MS Office Suite Project Management CNC machining Leadership Rolling Mill - Required Skills