300 likes | 406 Views
SMOS SODAP Status. Michele Zundo ESA/ESTEC EOP-PEP SMOS KP 0 09-Dec-2008. Presentation Summary. SODAP Scope SODAP Tasks SODAP Team SODAP Timeline SODAP Procedures SODAP Execution: SODAP Week 0 SODAP Week 1, 2 SODAP Outcome SODAP Observation Conclusion and Recommendations.
E N D
SMOS SODAP Status Michele Zundo ESA/ESTEC EOP-PEP SMOS KP 0 09-Dec-2008
Presentation Summary • SODAP Scope • SODAP Tasks • SODAP Team • SODAP Timeline • SODAP Procedures • SODAP Execution: • SODAP Week 0 • SODAP Week 1, 2 • SODAP Outcome • SODAP Observation • Conclusion and Recommendations
SODAP Scope • Switch On and Data Acquisition Phase • Lesson learnt. Insure before instrument commissioning starts the following: • Basic Instrument Health check • Verification Space to Ground Links XB • End to End functional data flow verification • Communication Scenario Verification • Opportunistic feed to processor and DPGS PLM-Health Check + SODAP-RF
SODAP Tasks For both ESAC and SVALSAT : • Check RF-links and budget • Verify XB masks and behaviour at high low elevation and identify operational constraints. • Confirm correctness timing of station and PLM XB scheduling • Exercise the different scenarios foreseen in Communication Baseline Doc • Exercise autonomous downlink and OBSW reset • Verify Data delivery to DPGS
SODAP Team(2) + Insa DPGS Operation Team at ESAC
SODAP Procedures (1) Described in: • Plan for RF activities during SMOS SODAP SO-PL-ESA-GS-6515 • SMOS SODAP-RF Procedure Issue 0 Draft 2 SO-GS-ESA-TP-6623
SODAP Procedures (2) ESAC
SODAP Procedures (3) SVALSAT
PLM-Health Check • Also known as Pre-SODAP • Implemented week 0 following switch-on • All OK. See Presentation by FOS
Preliminary outcome (6) • All 27 tests executed. • More than 50 Gbyte data acquired and analysed. • 135 XB passes have been scheduled • Functional chain OK (timing, dependency on elevation) i.e. no operational constraint identified. • Timing setting tuned at LOS • Different setting of stuffing data with good results (TBC) • SVAL XB tracking using SB for initial lock tested
Preliminary outcome (7) • ESAC links budgets and behavior at different elevation
Preliminary outcome (8) • SVALSAT RF links budgets and behavior at different elevations
Preliminary outcome (9) • SVALSAT Conclusion • The Eb/No observed is between 15 and 20 dB over all passes taken. This shows that there is a large system margin. At 15 dB Eb/No the IF input level is -40 dBm and the antenna tracking receiver SNR is about 17.5 dB. The threshold SNR for antenna autotrack is 10 dB. This means that there is a system margin of 7.5 dB.
Preliminary outcome (10) • Data continuity checked, major problems observed since data is lost on-board on MM partition 3
Observations working list(1) • Informal working list of observations to be changed to formal at subsystem level OBS/AR/NC/SPR if/as needed. • List will be cleaned up at end of SODAP • Major issues from SODAP point of view are: • Missing Packet detected (problem with on-board MM writing) (see presentation from FOS) • Duplicated/lost XB_DOWNLINK to SVALSAT • Occasional crashes of DAS acquisition • Inconsistent performance of E2E WAN transfer
Preliminary Conclusions • The System can deliver XB data to support IOCP • Both ESAC and SVAL scenario feasible
Recommendations (both Short and long term) • Initiate IOCP with NRT Communication scenario 2 orbit overlap • Address problem in acq. part of DAS to make it robust or consider alternate procurement. • Initiate implementation of OBSW modifications to cope with MM write error and partition disabling issues • Complete performance evaluation of NRT WAN link. • Decouple XB station commanding from data dissemination
Thanks • Thanks to the all Team for hard work and long hours