1 / 40

Bridge over BNSF Railroad 7 km East of Windham - East

Bridge over BNSF Railroad 7 km East of Windham - East. Bridge Replacement Project Using Accelerated Bridge Construction. Project Location. Existing Bridge. 3-Span Concrete Tee Beam 123 Feet Long 28 Feet Wide. Approach L ooking Southeast. Profile L ooking Southwest. Design Parameters.

omar
Download Presentation

Bridge over BNSF Railroad 7 km East of Windham - East

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Bridge over BNSF Railroad7 km East of Windham - East Bridge Replacement Project Using Accelerated Bridge Construction

  2. Project Location

  3. Existing Bridge • 3-Span Concrete Tee Beam • 123 Feet Long • 28 Feet Wide

  4. Approach Looking Southeast

  5. Profile Looking Southwest

  6. Design Parameters • National Highway Route • 2500 vehicles per day (23% Trucks) • Major truck route between Great Falls and Billings • US Air Force Missile Route • Grain Elevator in Moccasin • BNSF Railroad Crossing • Accident cluster at bridge

  7. New Bridge Requirements • New width = 40 feet • Increased railroad lateral clearance • Increased railroad vertical clearance • Avoid existing foundations (timber piles) • Minimize grade raise to catch slopes on existing approaches – avoid sliver fills and new R\W • Minimize traffic disruptions

  8. What are our options? • New Bridge on Offset Alignment • New Bridge on same alignment using On-site Detour • New Bridge on same alignment using Phase Construction • New Bridge on same alignment using Off-site detour and ABC

  9. Could Accelerated Construction work here?? • How long can we shut down bridge site? • How quickly can we build a new bridge? • How much building can be completed before with existing bridge in place? • Is there a reasonable detour route?

  10. Possible detour route • Secondary Highways – wide shoulders / flat slopes • Similar detour length for thru-traffic • Detour through town of Hobson – school crossing • At-grade RR crossing in Hobson • Many local detours possible (County Roads)

  11. ABC Planning Efforts • Contacts with • Town of Hobson - Mayor • Hobson School • County Commissioners • Trucking Industry – grain elevator • Air Force Base • BNSF Railroad • Road User Cost Calculations • Preliminary ABC Ideas • Contract Time Estimates • Local Events

  12. – Hay Days – Utica Montana

  13. What can we accelerate? What portion of construction takes the most time? • Foundation construction – 4 days/shaft or 4 piles/day • Drilled Shaft testing – 14 days before testing / longer if problems are encountered • Forming bent caps – 3 days each • Curing bent caps – 15 days per project • Deck forming – 20 days up to 300 feet • Deck curing and sealing – 28 days Allowing for some overlap……80 days for major items

  14. Potential Solutions • Foundations • What can we do while traffic is on existing bridge? • What foundation types will work? • Forming and curing bent caps • What cast-in-place can be done while traffic is on existing bridge? • Precast end and intermediate caps? • Deck forming and curing • Full-depth precast deck panels • Partial-depth • Stay-in-place Forms

  15. Divided Work Into Stages • What could be completed before detouring traffic • What would be accelerated while traffic is on detour route • What work could be done after traffic is moved back on new bridge

  16. Work Prior to Detouring Traffic Drilled 4 shafts outside the bridge limits and behind the existing intermediate bents.

  17. Cast struts/crash wall on top of and between shafts

  18. Cast walls on top of struts

  19. Traffic on Detour Day 1 • Removed span 2 deck and beams • Removed span 3 deck

  20. Day 2 • Removed span 3 beams • Removed bent 3 and 4 • Removed span 1 deck

  21. Day 3 • Bent 4 – drove piles, formed and placed cap • Bent 3 – Set cap and placed closure • Removed span 1 beams • Removed bents 1 and 2

  22. PrecastPier Cap

  23. Day 4 • Bent 2 – Set cap • Bent 1 – drove piles

  24. Day 5 • Bent 2 – placed closure • Bent 4 –formed and placed cap

  25. Day 6 • Span 3 – Set girders and deck panels

  26. Day 7 • Sunday – no work Day 8 • Span 2 – Set girders and deck panels

  27. Day 9 • Span 1 – Set girders and half the deck panels Day 10 • Span 1 – Set remaining deck panels • Began forming closure pours

  28. Day 11 • Bents 1 & 4 – Formed and placed backwalls • Formed deck panel closure pours Day 12 • Continued forming deck panel closure pours Day 13 and 14 • Saturday and Sunday – No work Day 15 • Adjusted deck grades • Prepare for deck closure pours

  29. Day 16 and 17 • UHPC Closure Pours

  30. Day 18 and 19 • Removing form work and grinding joints • Fill low spots

  31. Day 20 and 21 • Weekend no bridge work – building approach fills Day 22 • More grinding and approach fills Day 23 • Tying barrier steel • Test run with slip form Day 24 • Approach work Day 25 • Slip formed barriers • Final grading along RR tracks

  32. Day 26 and 27 • More grading work • Approach rails Day 28 • Finished approach rails Day 29 • Opened to Traffic One day ahead of schedule (incentive/disincentive deadline)

  33. Now lets see that in fast motion

  34. Lessons Learned • Project scheduling was intensive • Design details are critical – things need to fit • Allow adequate tolerance on precast elements • UHPC is difficult to grind – reduce exposed area to minimize grinding • Have an Engineer on site during construction of critical elements – be prepared to make decisions

  35. Questions?? Project Contact: Jeff Olsen jolsen@mt.gov 406-444-7610

More Related