1 / 24

Queuing Theory Jackson Networks

Queuing Theory Jackson Networks. Network Model. Consider a simple 3 stage model where the output of 2 queues becomes the input process for a third. Station A. Station C. Station B. Network Model. Station A. Station C. Proposition 1: rate in = rate out, that is, if l A and l B

oprah
Download Presentation

Queuing Theory Jackson Networks

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Queuing Theory Jackson Networks

  2. Network Model Consider a simple 3 stage model where the output of 2 queues becomes the input process for a third Station A Station C Station B

  3. Network Model Station A Station C Proposition 1: rate in = rate out, that is, if lA and lB are the input rates for station A and B respectively, then the input rate for station C is lA+lB. Proposition 2: exponential inter-arrivals at A and B provide exponential inter-arrivals at station C. Station B

  4. Network Model Station A Station C Instructor Derivation of the minimum of 2 exponentials. Station B

  5. Jackson Network Station 1 1 2 s1 1 2 sv 1 2 sj Station j . . Station v

  6. Jackson Network • All external arrivals to each station must follow a Poisson process (exponential inter-arrivals) • All service times must be exponentially distributed • All queues must have unlimited capacity • When a job leaves a station, the probability that it will go to another station is independent of its past history and of the location of any other job • Calculate the input arrival rate to each station • Treat each station independently as an M/M/s queue

  7. Calculate Arrival Rates

  8. Example Jobs submitted to a computer center must first pass through an input processor before arriving at the central processor. 80% of jobs get passed on the central processor and 20% of jobs are rejected. Of the jobs that pass through the central processor, 60% are returned to the customer and 40% are passed to the printer. Jobs arrive at the station at a rate of 10 per minute. Calculate the arrival rate to each station.

  9. Example .6 .2 10 .8 .4 Input Central Printer

  10. Example (cont.) • For the computer center the processing times are 10 seconds for the input processor, 5 seconds for the central processor, and 70 seconds for the printer. Our task is to determine the number of parallel stations (multiple servers) to have at each station to balance workload.

  11. Example 10 8 3.2 Input Central Printer For our initial try, we will solve for s1 = 2, s2 = 1, s3 = 4

  12. 10 8 3.2 Input Central Printer

  13. If these numbers are correct, clearly Lq and Wq indicate the bottleneck is at the printer station. We may wish to add a printer if speedy return of printouts is required. Secondarily, overall processing may be increased by adding another input processor.

  14. Job Shop Example • An electronics firm has 3 different products in a job shop environment. The job shop has six different machines with multiple machines at 5 of the 6 stations. Product Order rate Flow 1 30/month ABDF 2 10/month ABEF 3 20/month ACEF Summary information is on the network below.

  15. Job Shop Example Machine D s = 3 m = 11 Machine B s = 2 m = 22 Machine C s = 1 m = 29 Machine A s = 3 m = 25 Machine E s = 2 m = 23 Machine F s = 4 m = 20

  16. Job Shop Example Machine D s = 3 m = 11 Machine B s = 2 m = 22 Machine C s = 1 m = 29 Machine A s = 3 m = 25 Machine E s = 2 m = 23 Machine F s = 4 m = 20

  17. Job Shop Example Machine D s = 3 m = 11 Machine B s = 2 m = 22 Machine C s = 1 m = 29 Machine A s = 3 m = 25 Machine E s = 2 m = 23 Machine F s = 4 m = 20

  18. Job Shop Example Machine D s = 3 m = 11 Machine B s = 2 m = 22 Machine C s = 1 m = 29 Machine A s = 3 m = 25 Machine E s = 2 m = 23 Machine F s = 4 m = 20 Lets calculate metrics for Machine B M/M/2 model with Use formulas in Fig. 16.5 p. 564 or use charts

  19. Repeat for Machines A, C, D, E, F Machine D s = 3 m = 11 Machine B s = 2 m = 22 Machine C s = 1 m = 29 Machine A s = 3 m = 25 Machine E s = 2 m = 23 Machine F s = 4 m = 20

  20. Interesting Application to Manufacturing Note that lead time is just the time in the system which for product 1 which has sequence ABDF is W = total time in system = lead time = WA + WB + WD + WF = .789 WIP = work in process = parts per month x lead time = 30(.789) = 23.67

  21. Repeat for Machines A, C, D, E, F Machine D s = 3 m = 11 Machine B s = 2 m = 22 Machine C s = 1 m = 29 Machine A s = 3 m = 25 Machine E s = 2 m = 23 Machine F s = 4 m = 20

  22. Some Recommendations If lead time is too slow (WIP too high), one possibility is to add additional machining to the bottleneck area. This occurs at stations D and B. Note that this assumes the cost of the machines is not a critical part of the decision. This may or may not need to be included in a final recommendation.

More Related