Software Quality AssuranceImplementation PlanJune 15, 2004 Defense Nuclear Facilities Safety Board Chip Lagdon Director Office of Quality Assurance Programs
Overview • Recent Activities • SQA Assessment Observations • SQA Directives Status • Open 2002-1 IP Commitments • Path Forward
SQA Training • SQA Training Conducted – May 2004 • 22 attendees from NNSA, EM, & EH • ASQ Software Quality Engineer Course Content • 2nd Course later this year • 3 FAQS Competencies not Addressed • #1 Specific to DOE Nuclear Safety • #3 Specific to DOE Software Applications • #9 Specific to Safety Analysis Standards • Assist in Providing Qualification Approaches
Toolbox Codes • Issued final gap analysis reports for ALOHA, MACCS2, EPIcode, MELCOR, CFAST & GENII • Posted on SQA Knowledge Portal • Notified Users via SQA Newsletter/List Server • Letters to Code Developers • Will Develop Path Forward with PSO’s
Toolbox Codes (cont.) • Update Code Guidance Reports based on Final Gap Analysis – June 2004 • Code Guidance Reports + Toolbox Codes = SQA Instructions on using code
Overview of Code Commitments 4.2.1.2 4.2.1.3 4.2.1.4 4.2.1.5 4.2.1.1 2002-1 Implementation Plan (IP) Commitments 2002-1 IP Deliverables Identify Safety Analysis Codes Establish SQA Criteria Perform Gap Analysis of Each Code Develop Guidance Report for Each Code Survey Design Codes Safety Analysis Survey Report SQA Plan and Criteria Report Gap Analysis Reports Code Guidance Reports Design Code Survey Report • CENTRAL REGISTRY • Procedure for Central Registry • SQA Criteria upgrade • 3. Evaluate feasibility of upgrade Codes
SQA Assessment Observations • 16 SQA Assessments Completed • EH participated in 5 assessments • EH review in progress • Assessments are ongoing • SQA Program Implementation • Level of implementation varies across the complex • SQA procedures are established at some sites and under development at others • Control of authorized users of software needs improvement • Procedures for legacy software need to be more clearly defined • Multiple assessments may be needed to verify SQA program implementation at some sites
SQA Assessment Observations (cont.) • CRAD’s • Could be combined to eliminate duplication • Supplemental criteria added for some SQA assessments • SQA Documentation • Configuration management (version control) and documentation for internally developed software needs to be strengthened • COTS software documentation generally adequate. Error reporting and corrective action needs to be strengthened
SQA Directives Status • DOE O 414.1C 2nd Draft Complete • SME 1st draft comment disposition complete • Start DOE-wide review (RevCom) August 2004 • Issue DOE O 414.1C December 2004 • DOE G 414.1-4 • 1st draft in progress • Writing team meeting - Today • Start DOE-wide review October 2004
Other Activities • SQA Presentation for Subcommittee for Consequence Assessment and Protective Action (SCAPA) • 2 SQA Technical Papers Published • SQA Knowledge Portal Launched • June SQA Newsletter Published
Path Forward • Develop Central Registry Procedure • Update toolbox code guidance reports • Continue to participate and evaluate SQA Assessments results • NNSA and EM to update FRA documents • Support training and qualification of SQA personnel