DISTRIBUTION RECOVERY STREAM Water System Schematic

DISTRIBUTION RECOVERY STREAM Water System Schematic. Flow started here between 1700hrs and 2100hrs, 28 th July Initial flow of 80Ml/d building to 120Ml/d over following 12 hours. Trunk Main. District Metered Area (DMA) (110). (87km). Main (1883km). Treatment works. Valve. River.

Download Presentation

DISTRIBUTION RECOVERY STREAM Water System Schematic

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. DISTRIBUTION RECOVERY STREAMWater System Schematic • Flow started here between 1700hrs and 2100hrs, 28th July • Initial flow of 80Ml/d building to 120Ml/d over following 12 hours Trunk Main District Metered Area (DMA) (110) (87km) Main (1883km) Treatment works Valve River Service Reservoir (15) Approx 1300 Properties DMA Valve Meter DMA DMA Distribution Recovery Plan Update 09:00 29th July 2007

  2. Estimated Recharge Timetable All timings are estimated. All timings are liable to vary due to the unique nature of a 2,000km pipeline. Distribution Recovery Plan Update 09:00 29th July 2007

  3. Issues influencing timing • Demand levels – filling loft tanks, taps left running, washing backlog, flood washdown, etc • Operational issues in recharging – airlocks • Mechanical failure of distribution assets – valves, pressure control valves, booster pumps • Not been run for a while, may have flood damage • Leakage • system has been discharged • floods will have caused ground movement • Mythe production – mechanical / electrical / process failure Distribution Recovery Plan Update 09:00 29th July 2007