PROMISE RISK TO CONTRACTORS RISK TO GOVERNMENT CASH FLOW PROGRESS PAYMENTS ADMINISTRATION

COST- REIMBURSEMENT. FIXED-PRICE. Best Effort Low High As Incurred None Max Government Max: 6/10/15 % CPFF Contracts. Shall Deliver High Low On Delivery % of Actual Min Government NO Limit. Contract Category Characteristics. PROMISE RISK TO CONTRACTORS RISK TO GOVERNMENT

ova
Download Presentation

PROMISE RISK TO CONTRACTORS RISK TO GOVERNMENT CASH FLOW PROGRESS PAYMENTS ADMINISTRATION

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. COST- REIMBURSEMENT FIXED-PRICE Best Effort Low High As Incurred None Max Government Max: 6/10/15 % CPFF Contracts Shall Deliver High Low On Delivery % of Actual Min Government NO Limit Contract Category Characteristics PROMISE RISK TO CONTRACTORS RISK TO GOVERNMENT CASH FLOW PROGRESS PAYMENTS ADMINISTRATION FEE/PROFIT

  2. Mission Support Planning Contract Types - Major Systems Continuum User Needs & Technology Opportunities TYPICAL CONTRACT TYPE CHANNEL Pre-Systems Systems Acquisition Sustainment Acquisitions B A C CPFF FFP (LOE) FPI FFP FPI FFP CPFF CPAF CPIF FOC IOC Concept Refinement Technology Development System Development & Demonstration Production and Deployment Operations & Support Concept Decision Design Readiness Review FRP Decision Review LRIP/IOT&E ILL DEFINED RQMT ... WELL ... DEFINED RQMT CE PDRR EMD PRODUCTION or DEPLOYMENT WORK STATEMENT TYPE CHANNEL

  3. Reliability of Cost Estimate and Confidence of Outcome FFP or FFP/EPA 0 - 10 % CPFF 30 % + CPIF 20 - 30 % FPIF 10 - 20 % Rules of Thumb

  4. Distribution of Cost OutcomesDoes Not Follow a Bell Shaped Curve

  5. Distribution of Cost Outcomes Does Not Follow a Bell Shaped Curve There is limited potential for under run, but infinite potential for overrun.