An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. TCC2/TDC2 LS1 Consolidation Plans EATM 09/10/2012 http://cern.ch/tcc2tdc2WG On behalf of the TDC2/TCC2 WG team

  2. Our plan for LS1 • Electricity • LV cabinet replacement • Groundloop upgrade • Renew Lights above XTAX and Targets • Implementsafetylighting • Re-route cabling in TDC2 and exchange cableswith PVC • Secondarybeamlines • Shielding modification • Survey of all beamlines • XTAX table second repair and upgrade • Collimators and targets • Monitor replacement • Mobile shieldingmotor exchange • TCSCexchange • Safety system upgrade according to safety file • Cooling and Ventilation • Controls Upgrade • Exchange of valves on Demin.& Chilledwater circuits • Chilled water pipe replacement (BA80/TCC2) • Vacuum • Damaged vacuum chambers & bellows replacement • Exchange and add ion pumps • Beam line protection system if no design change • Beam monitors • Magnets • Cooling flexibles replacement • Coolingpanoplyremovalfromcritical areas • Magnet support upgrade • Civil Engineering • Make roof and floor water tight as much as possible • Getrid of PVC tubes (drain network) • Corrective and preventive maintenance of drain network

  3. Planning: assomptions & contraints • Assumptions • T0: beam off: Feb 11th 2013. • Tf : restart of NA physics targeted for beginning of November 2014. • Constraints • RP requests 6 months cool down before short stay in TDC2/TCC2 (work preparation) and another 6 months cool down before longer intervention (work execution). • Dusty or tough activities (CE, new cable trays, water circuits) prior to new equipment installation. • Some co-activities are impossible (hot work, crane dependent, space consuming). • Hot work should be carried out at the very end of the access period. • Some groups (EN-CV and EN-EL) can start studies as of March 2014. Real work in the areas only after July 14. • Tf : 1 week contingency and 2 weeks for starting-up before restart of NA physics.

  4. Planning: option 1 • Postpone NA physics restart by another 3 months

  5. Planning: option 2 • Give priority to NA physics Proton and ion run

  6. Cablingrequests • New Radmon system • Heatingcollars for TE-VSC • New ion pumps • Targets ? • Makeyour DIC requests as soonas possible