An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. S&C Draft of 5/26/10 Operating Performance Update INTERNAL

  2. Production Milestones INTERNAL • June 26, 2012 • First Nickel test briquettes were sintered. • August 18, 2012 • Single largest batch of slurry sent from the Mine (18,980 t), exceeding the Financial Completion target of 674 t/h. • September 9, 2012 • First Cobalt test briquettes were sintered. • September 13, 2012 • Operating permit granted. • November 1, 2012 • 5 Autoclaves on line with dual slurry feed pumps • November 8, 2012 • First international shipment of refined nickel (40 t) • November 13, 2012 • First international shipment of refined cobalt (168 t)

  3. Production Achievements to November 30, 2012 INTERNAL Mixed Sulphides to Refinery: Ni+Co contained, t 6,900 Nickel Reduced, t 5,512 Cobalt Reduced, t 488 Amsul Produced, t 10,695 Note: The Project achieved “Commencement of Commercial Production” as described in the Finance Documents on November 26, 2012.

  4. PAL Overview • Autoclaves • PAL Autoclave Operating Hours • Operated approximately 1,788 hours in November • Ore Throughput in the PAL Autoclaves • Processed 191,085 tonnes in November • PAL Mixed SulphideProduction • Produced approximately 1,763 tonnes of mixed sulphides (ni+co contained) in November INTERNAL

  5. Refinery Overview INTERNAL • Sulphide Leaching • In November we processed1,694 tonnes of nickel and cobalt contained in mixed sulphides • Nickel Reduction • In November we reduced 1,592 tonnes of nickel powder • Cobalt Reduction • In November we reduced 164 tonnes of cobalt powder • Metals Handling • Produced 1,199 tonnes of nickel briquettes in November • Produced 100 tonnes of cobalt briquettes in November

  6. Operating Performance – PAL Ramp-Up Curve INTERNAL

  7. Operating Performance – Refinery Ramp-Up Curve INTERNAL

  8. Operating Performance – Ore Throughput INTERNAL

  9. Operating Performance – Nickel Produced INTERNAL

  10. Nickel Quality Analysis • Nickel meets LME spec for all elements except silicon. • Silicon contamination has occurred from late October and into November as Si level in Refinery solution has increased. • Refinery is currently progressing initiatives to purge silicon from the circuit. INTERNAL

  11. S&C Draft of 5/26/10 Questions? INTERNAL