1 / 20

U.S. Department of Energy Project Management: Communicating Progress – Celebrating Success

U.S. Department of Energy Project Management: Communicating Progress – Celebrating Success. Paul Bosco, PE, PMP, CFM, LEED-AP Director, Office of Procurement and Assistance Management Director, Office of Engineering and Construction Management. Outline of Presentation.

patch
Download Presentation

U.S. Department of Energy Project Management: Communicating Progress – Celebrating Success

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. U.S. Department of EnergyProject Management:Communicating Progress – Celebrating Success Paul Bosco, PE, PMP, CFM, LEED-AP Director, Office of Procurement and Assistance Management Director, Office of Engineering and Construction Management

  2. Outline of Presentation • GAO High-Risk List – Some Background • Project Success – Are We There Yet? • Project Metrics – How Are We Doing? • Documenting and Tracking Performance • Project Management Enhancements • Challenges Ahead • Questions/Comments

  3. Contract and Project Management Goal • Improve contract and project management and alignment to support accomplishment of DOE mission and strategic goals • Success Metric: • Complete projects within 10% of the original cost baseline • Secondary Goal: • Removal from GAO’s High-Risk List

  4. Project Success • Project Success: (For “Capital Asset Projects”) • Project completed within the ORIGINAL approved scope baseline, and within 10% of the ORIGINAL approved cost baseline at project completion (CD-4), unless otherwise impacted by a directed change. • Portfolio Success: • 90% of all projects meet project success criteria, based on a three-year rolling timeline.

  5. How are we Doing?Based on 3-Year Rolling Timeline

  6. How are we Doing?Pre- vs. Post-RCA (Demarcation Date: October 1, 2007) (26 / 35) (21 / 28) (43 / 44) (64 / 72) (32 / 41) (30 / 38)

  7. Documenting Project Success CD-2 Commitment CD-4 Auditable Scope Accomplished Key Performance Parameters Met Total Project Cost Completion Date (Month/Year) Signed by Acquisition Executive • Scope • Minimum Key Performance Parameters • Total Project Cost • CD-4 Date (Month/Year) • Signed by Acquisition Executive Templates Online & OECM Review Draft Memos

  8. Tracking Project PerformanceAgainst Current Project Performance Baseline Overall Project Assessment = EVMS Indicators + Assessment Factors • EVMS Indicators: • CPi • SPi • TCPi • EACs • Variances • Trends • % Complete • Assessment Factors: • Data validity • MR & Contingency • Reports • Reviews • Communication • Other information Project is expected to meet its performance baseline (PB) Project is potentially at risk of not meeting element of the PB = + Project is highly at risk of requiring a change to the PB • Yellow is not bad – provides early warning • DOE is not fixated on “getting to green,” only achieving • project success – meeting our commitments • Assessment is not solely ratio based – Trends are important

  9. Significant PM Enhancements • Established front-end planning maturity objectives • Clarified project size and structure; program versus project management … “chunking” • Transformed commitment to funding, budgeting; stabilized funding • Enhanced management and oversight • Peer reviews for projects >$100M • PARS II central repository for project data – data accuracy and consistency • ICRs/ICEs for projects >$100M DOE O 413.3B Highlights

  10. Great Progress, But…Challenges Remain – Loom Ahead GAO Meeting of March 5, 2012 • Two Impending GAO Reports (1) Non-Major System Projects; (2) EM Recovery Act • Preliminary Findings • SCOPE – SCOPE – SCOPE: “Low Confidence” • Schedule (CD-4) Completions: Too Generic – Fiscal Year (“Budget”) End Dates, i.e., FY11 • Significant Cost Under-Runs • PARS-II: Only as Good as the Data Quality

  11. Major Challenge (Dollars in Trillions) Estimate Actual

  12. Major Challenge National Deficit ($Billions)

  13. Portfolio Management – Project Prioritization FY13 Budget Capital Asset Project Backlog “Chunked” Projects Budget ± 20% Budget Target Small Projects Committed Funding Profiles Operations Non-Discretionary (e.g., payroll, utilities, etc.) (Notional Data [$1B Budget])

  14. PMI’s “Pulse of the Profession”* Focus Areas of 2012: (In priority order) • Renewed Focus on Talent Management • Need for Good Project Portfolio Management • Change Management & Risk Management – Even More Important • Agile Project Management • Focus on Benefits Realization *PMI President and CEO: Mark Langley, March 2012

  15. What’s Next? Play to Your Strengths – Disciplined Implementation • DOE has improved in project and contract management – our stats provide validation • Our successes must be credible and documented • Project management framework is in place http://energy.gov/management/office-management/operational-management/project-management • Immediate challenge: consistent implementation • Future Challenge: Program/Portfolio Management Credible project success is the key!

  16. Questions / Comments

More Related