TRANSPORTATION MANAGEMENT PLAN I-5 / I-805 WIDENING PROJECT California Department of Transportation Traffic Operations District Traffic Manager Branch District 11, San Diego January,2002. TMP OBJECTIVES :
E N D
TRANSPORTATION MANAGEMENT PLAN I-5 / I-805 WIDENING PROJECT California Department of Transportation Traffic Operations District Traffic Manager Branch District 11, San Diego January,2002
TMP OBJECTIVES : • To provide a working window which the Contractor can complete meaningful work. • To reduce congestion and improve safety at the I-5/I-805 Merge. • To maintain freeway access for local communities. • Increase capacity and provide for future improvements along I-5 corridor.
TMP STRATEGIES OVERVIEW • Public Information • Motorist Information • Incident Management • Construction Strategies • Demand Management • Alternative Route Strategies
MOTORISTS INFORMATION • Use (3) fixed Changeable Message Signs (CMS) at the following locations. • On northbound Route 5. 1-2 miles south of the • off-ramp to eastbound SR-52. • On southbound Route 5. 1-2 miles north of the • off-ramp to eastbound SR-78. • On northbound Route 805. 1-2 miles south of the • off-ramp to eastbound SR-52. • Use (8) Portable Changeable Message Signs (PCMS) (part of the contract).
The following new FSP hours are recommended • 5:30 AM to 11:30 AM on Weekdays • Additional two AM hours are recommended • 2:00 PM to 8:00 PM on Weekdays • Additional two PM hours are recommended • 2:00 PM to 6:00 PM on Saturday • Additional of four hours are recommended • 2:00 PM to 6:00 PM on Sunday • Additional of four hours are recommended
Public Information $608,000 Motorist Information $835,000.00 Incident Management $2,767,000 Construction Strategies $0.0 Demand Management $400,000.00 Alternative Route Strategies $10,000.00 Mailing List Database Fixed Changeable Message Signs Construction Enhanced Enforcement Program Lane Closure Charts Park & Ride Lots Stripe and Open “Northbound Truck Lane” Open House Portable Changeable Message Signs Incentive & Disincentive Clause Ramp Metering Freeway Service Patrol (FSP) Bulletins and Ads. Accelerate Construction of Vista Sorrento Parkway Ground Mounted Signs News Releases Traffic Management Team (TMT) Total Facility Closure HOV Lanes/Ramps Radio Ads. Highway Advisory Radio Web Camera Ferry Service Advertise Park &Ride Ride Share Incentives Delay Clause Caltrans Highway Information Network Print Advertisement TMPElementsand costs
Total Costs* • Total TMP Budget = approx. $4.6 M • Total Project Budget = approx $170 M • TMP Costs = 2.7% of Total Project Costs * Note: This slide was not part of the original Caltrans presentation. It is based on information received from the Senior Resident Engineer in June 2006.