ERCOT DC-Tie Emergency Operation Report

Detailed analysis of ERCOT DC-Ties emergency operations, including current operations, schedules, and emergency assistance. This report covers ongoing transmission outages, supply shortages, voltage deficiencies, and more.

Download Presentation

ERCOT DC-Tie Emergency Operation Report

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 2007 South DC-Tie Emergency OperationTPTFNovember 27, 2007Updated for February 4, 2008 TPTF

  2. Agenda • Current Operations of the DC-Ties • Summary of the Schedules flows in the last 12 Months

  3. ERCOT DC-Ties • ERCOT-CFE Operational DC-Ties • Eagle Pass (DC_S, 36 MW) • Laredo Variable Frequency Transformer (DC_L, 100 MW) • Sharyland Railroad (DC_R, 150MW) • ERCOT-SPP Operational DC-Ties • North DC_Tie (DC_N, 220 MW) • East DC_Tie (DC_E 600 MW) DC_N 220 MW DC_E 600 MW DC_S 36 MW DC_L 100 MW DC_R 150 MW

  4. ERCOT DC-Ties -- Operations • ERCOT/SPP DC-Ties • Open for commercial transactions and operation • ERCOT/CFE DC-Ties • Interim agreement in place with CFE. Addresses emergency assistance through the DC-Tie and BLT • Transmission Outages, Supply shortages, voltage deficiencies and other • Currently only utilized under emergency conditions • Transmission Emergency Condition • EECP

  5. ERCOT received DC-Tie flows 32 times through the South DC-Ties from October 2006 to August 2007. Each DC-Tie flow corresponds with a declaration of an Emergency Condition. South DC Tie Requests 5

  6. Eagle Pass DC-Tie Emergency Assistance Schedules 25 Times due to Transmission Emergency Conditions • October 06 (6 days) – Planned outage on Uvalde to Asphalt Mines and Forced outage on Asherton to North Laredo • November 06 (5 days) – Planned outage on Uvalde to Asphalt Mines • December 06 (2 days) – Planned outage on Uvalde to Asphalt Mines • January 07 (5 days) – Del Rio Area experienced a blackout during the planned outage on Brackettville to Hamilton and a consequent forced outage due to an unexpected cold front. • February 07 (7 days) Planned outage on Brackettville – Asphalt Mines 2 Times due to EECP on June 18th, 2007 & August 1st, 2007

  7. Laredo VFT Emergency Assistance Schedules 3 Times due to Transmission Emergency Conditions July 07 (3 days) Planned outage of an RMR unit in the Laredo area 2 Times due to EECP on June 18th, 2007 & August 1st, 2007 Railroad DC-Tie Schedules No emergency schedules in the Tie 7

  8. Del Rio Area Planned Outage on Uvalde to Asphalt Mines Oct 25 – Dec 3, 2006 Del Rio Area Planned Outage on Brackettville – Hamilton Jan 30 – Feb 2 & Feb 19 – April 19 Planned Outage on Brackettville – Asphalt Mines Feb 14 - 19 Forced Outage on Asherton – North Laredo Oct 31, 2006