This plan addresses deficiencies in compliance and updates the Emergency Planning Hazards Assessment (EPHA) and Business Continuity Program. It ensures accurate notification of hazardous chemicals and includes corrective action plans for all identified issues.
E N D
DOE Order 151.1c Comprehensive Emergency Management System Implementation Plan Update 1/11/2013
Background Implementation Plan was developed to address deficiencies in compliance identified by BSO • 2011 Emergency Planning Hazards Assessment (EPHA) was not defensible and therefore not approved. • Business Continuity Program was insufficient • Accurate and timely notification of Hazardous Chemicals • Corrective Action Plans were developed for all three of these issues Environment / Health / Safety / Security DIVISION
Emergency Planning Hazards Assessment A facility specific screening for facilities involved in producing, processing, handling, storing, or transporting hazardous materials that have the potential to pose a serious threat to workers, the public, or the environment. • As required by DOE Order 151.1c, LBNL is to assess hazardous materials and screen all chemicals that: • Represent National Fire Protection Association (NFPA) health hazard 3 or 4 and; • Are in quantities greater than those which can be easily and safely manipulated by one person (lab safety quantity); or • Are stored in multiple containers where the room total exceeds 5 times the lab safety quantity. • * If there is the possibility that a potential release may cause a classified Operational Emergency, then an EPHA is required. • The results of the EPHA will then determine if the release of each identified material will cause a hazard significant enough to be included as part of the Hazardous Material Program planning basis. Environment / Health / Safety / Security DIVISION
Emergency Planning Hazards Assessment Corrective Action Plan • LBNL staff reviewed and evaluated a screening methodology developed by the DOE Emergency Management Issues Special Interest Group (EMI SIG). Used the methodology to evaluate our existing EPHA (B 77). • The results of the evaluation indicate we have effectively mitigated the risk associated with our existing EPHA, but we are awaiting BSO approval of the findings. • Should result in a DOE planning status of “Base Program” rather than “OE Hazardous Materials Program”. • Lessens the requirements related to emergency planning, notifications, response capabilities, etc. Environment / Health / Safety / Security DIVISION
Hazardous Materials Awareness Corrective Action Plan • Review Purchasing Line Summary Report • Rad Protection Group require select purchase to receive “authorization”. • CMS report now generating a “sub-report” on items with potential to exceed the lab safety quantity. • Procurement has worked with Ebuy vendors to code certain products to generate an automated notification. Environment / Health / Safety / Security DIVISION
Hazardous Materials Awareness Corrective Action Plan • Automatic notification out to purchasers with dual appointment status • Spot checks incorporated into Chemical, Health & Safety program lab inspection • Still need to address blanket purchase orders • Still need to socialize and develop lab work process/policy through RMP Environment / Health / Safety / Security DIVISION