Common Deficiencies observed in the Project Proposals received at NRRDA

Common Deficiencies observed in the Project Proposals received at NRRDA. Deficiencies in Project Selection. Errors in the preparation of Core Network. Disproportionate allocation to the Districts. Deficiency in the Preparation of CNCPL/CUPL. Inadequacy in the consultative process.

Download Presentation

Common Deficiencies observed in the Project Proposals received at NRRDA

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Common Deficiencies observed in the Project Proposals received at NRRDA

  2. Deficiencies in Project Selection Errors in the preparation of Core Network. Disproportionate allocation to the Districts. Deficiency in the Preparation of CNCPL/CUPL. Inadequacy in the consultative process. Deviations from CNCPL/ CUPL in the roads selected.

  3. Deficiencies in the Design. Inadequate investigations. Failure to check correlations in the soil properties. Inaccurate estimation of Design Parameters. Non adherence to the provisions of RRM for Pavement Component Design. In adequate Geometric Design. Failure to identify cost aberrations in the components. Inappropriate location and design of CD Works. Provisions beyond permissible as per guidelines. Deficiency in checking the Schedule of Rates, Maintenance Cost. Failure to investigate alternate designs for optimality.

  4. Deficiencies in Reporting Incompatibility of data on connectivity status. Incomplete data entry on OMMAS. Failure to clear the proposals on - line at STA Level. Incomplete data in Format “C”. Failure to give specific remarks on individual project proposal and submission of consolidated reports by STAs.