Graduate Circle Housing Proposal for the Pennsylvania State University

Graduate Circle Housing Proposal for the Pennsylvania State University. BY. The Lasso Corp 100 Kunkle Lounge University Park PA 16802. Presentation Overview. Section 1- Team Introduction Section 2- Site Investigation Section 3- Estimate Overview Section 4- Schedule Review

paul2
Download Presentation

Graduate Circle Housing Proposal for the Pennsylvania State University

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Graduate Circle Housing Proposal for the Pennsylvania State University BY The Lasso Corp 100 Kunkle Lounge University Park PA 16802

  2. Presentation Overview Section 1- Team Introduction Section 2- Site Investigation Section 3- Estimate Overview Section 4- Schedule Review Section 5- Construction Plan

  3. Team Introduction

  4. Project Executive Chris Stultz Team IntroductionSite InvestigationEstimate OverviewSchedule ReviewConstruction Plan Project Manager- 3D Modeler Jonathan Nelson Schedule Superintendent Adam De Luca Estimation Superintendent Scott Earley Site Superintendent Hamad Alrahmani 100 Kunkle Lounge University Park PA 16802

  5. Site Investigation “Digging into the past to build the future.....”

  6. Proposed Site Team IntroductionSite Investigation Site Investigation & Background Building Description & GeometryValue EngineeringEstimate OverviewSchedule ReviewConstruction Plan Topography Pedestrian Access Maintenance Bldg. Vehicular Access Existing Structures Lot to be removed 100 Kunkle Lounge University Park PA 16802

  7. Team IntroductionSite InvestigationSite Investigation & BackgroundBuilding Description & GeometryValue EngineeringEstimate OverviewSchedule ReviewConstruction Plan Structural System Façade Material and Features Other Systems 100 Kunkle Lounge University Park PA 16802

  8. Plan Geometry and Sizes Team IntroductionSite InvestigationSite Investigation & BackgroundBuilding Description & GeometryValue EngineeringEstimate OverviewSchedule ReviewConstruction Plan 100 Kunkle Lounge University Park PA 16802

  9. Foundation Team IntroductionSite InvestigationSite Investigation & Background Building Description & GeometryValue EngineeringEstimate OverviewSchedule ReviewConstruction Plan Structure Exterior Interior Layout Electrical & Mechanical 100 Kunkle Lounge University Park PA 16802

  10. Estimate Overview “Putting a price on your ideas…”

  11. Staffing Plan Team IntroductionSite InvestigationEstimate OverviewStaff and General Conditions Monitor Project EstimateSchedule ReviewConstruction Plan 100 Kunkle Lounge University Park PA 16802

  12. Structural Concrete Team IntroductionSite InvestigationEstimate OverviewStaff and General Conditions Monitor Project EstimateSchedule ReviewConstruction Plan $1,264,771.72 100 Kunkle Lounge University Park PA 16802

  13. Structural Steel Team IntroductionSite InvestigationEstimate OverviewStaff and General Conditions Monitor Project EstimateSchedule ReviewConstruction Plan $1,447,307.52 Total Structure = $2,712,079.24 100 Kunkle Lounge University Park PA 16802

  14. Team IntroductionSite InvestigationEstimate OverviewStaff and General Conditions Monitor Project EstimateSchedule ReviewConstruction Plan 100 Kunkle Lounge University Park PA 16802

  15. Schedule Review “Timing is everything.....”

  16. Team IntroductionSite InvestigationEstimate OverviewSchedule ReviewCPM Schedule NarrativeCash Flow Projection & Payment ScheduleSchedule RisksConstruction Plan • Substantial Completion: • December 18, 2009 • Building Turnover: • December 21, 2009 100 Kunkle Lounge University Park PA 16802

  17. Team IntroductionSite InvestigationEstimate OverviewSchedule ReviewCPM Schedule NarrativeCash Flow Projection & Payment ScheduleSchedule RisksConstruction Plan • Phase 1- 20% • Phase 2- 30% • Phase 3- 50% • Methods Employed to Compress Schedule: • Multiple Crews • Well Defined Sequence of Trades • Minimal Lag Time between Activities • Consistent Steel Members • Prefabrication of Trusses and Other Systems 100 Kunkle Lounge University Park PA 16802

  18. Team IntroductionSite InvestigationEstimate OverviewSchedule ReviewCPM Schedule NarrativeCash Flow Projection & Payment ScheduleSchedule RisksConstruction Plan 100 Kunkle Lounge University Park PA 16802

  19. Team IntroductionSite InvestigationEstimate OverviewSchedule ReviewCPM Schedule NarrativeCash Flow Projection & Payment ScheduleSchedule RisksConstruction Plan 100 Kunkle Lounge University Park PA 16802

  20. Construction Plan “Coordinating safety and production.....”

  21. Team IntroductionSite InvestigationEstimate OverviewSchedule ReviewConstruction PlanSite Plan Phase 1 Phase 2 Phase 3 Waste Removal & Recycling Steel Sequence Plan Hazard Analysis & Safety Plan Unexcavated Earth Site Utilization Plan: Phase 1 100 Kunkle Lounge University Park PA 16802

  22. Team IntroductionSite InvestigationEstimate OverviewSchedule ReviewConstruction PlanSite PlanPhase 1Phase 2 Phase 3 Waste Removal & Recycling Steel Sequence Plan Hazard Analysis & Safety Plan Unexcavated Earth Site Utilization Plan: Phase 2 100 Kunkle Lounge University Park PA 16802

  23. Team IntroductionSite InvestigationEstimate OverviewSchedule ReviewConstruction PlanSite PlanPhase 1 Phase 2Phase 3 Waste Removal & Recycling Steel Sequence Plan Hazard Analysis & Safety Plan Site Utilization Plan: Phase 3 100 Kunkle Lounge University Park PA 16802

  24. Team IntroductionSite InvestigationEstimate OverviewSchedule ReviewConstruction Plan Site PlanWaste Removal & Recycling Steel Sequence Plan Hazard Analysis & Safety Plan Waste & Recycling Containers 100 Kunkle Lounge University Park PA 16802

  25. Building Sequencing Team IntroductionSite InvestigationEstimate OverviewSchedule ReviewConstruction Plan Site Plan Waste Removal & RecyclingSequence Plan Overall Building SequenceSteel Sequence Hazard Analysis & Safety Plan Steel and Concrete Sequence Roof and Envelope Sequence Interior Trades Sequence 100 Kunkle Lounge University Park PA 16802

  26. Steel Sequence Team IntroductionSite InvestigationEstimate OverviewSchedule ReviewConstruction Plan Site Plan Waste Removal & RecyclingSequence PlanOverall Building Sequence Steel Sequence Hazard Analysis & Safety Plan Steel Sequence: Starting Bay Steel Sequence: Progression through Building 100 Kunkle Lounge University Park PA 16802

  27. Hazard Analysis Team IntroductionSite InvestigationEstimate OverviewSchedule ReviewConstruction Plan Site Plan Waste Removal & Recycling Steel Sequence PlanHazard Analysis & Safety Plan 100 Kunkle Lounge University Park PA 16802

  28. Graduate Circle Housing Proposal for the Pennsylvania State University Questions? 100 Kunkle Lounge University Park PA 16802