An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Cal/Coronagraph Integration Lewis Roberts 2/25/2010

  2. Agenda • Schedule • Tasks • Summary

  3. High Level Schedule • 1st week – Set up and integrate with Coronagraph • 2nd week – Integrate with AO system. Test system in lab • 3rd week – IFU detector is installed and tested. • 4th week – 1 Engineering night and 2 science nights.

  4. Detailed Week 1 Schedule(This is just the highlights, a more detailed schedule is available on the Twiki) • March 1 • Drive Equipment to Palomar • Start Dewar Pumping/Cooling • March 2 • Sasha Tutors Gautam/Lewis on Coronagraph operations • Install Calibration Bread Board • March 3 • Install & Align Dewar • Alignment • March 4 • March 5 • Install System on AO bench

  5. Detailed Week 2 Schedule(This is just the highlights, a more detailed schedule is available on the Twiki) • March 8 • Drive to Palomar • End-to-End Alignment • March 9 • AO Lab Tests Day 1 • March 10 • AO Lab Tests Day 2 • March 11 • AO Lab Tests Day 3 • March 12 • AO Lab Tests Day 4

  6. Detailed Week 3 Schedule(This is just the highlights, a more detailed schedule is available on the Twiki) • March 15 • Install new connectors on Cal System Dewar at JPL • March 16 • Drive to Palomar • Install Cal System Dewar into Cal System before IFU is installed. Need to confer with IFU team.

  7. Detailed Week 4 Schedule(This is just the highlights, a more detailed schedule is available on the Twiki) • March 21 • In lab testing of Coronagraph, IFU, AO and Cal System • March 22 • Install Instrument on Telescope (Morning) • Engineering Night (Night) • March 23 • Science Observations • March 24 • Science Observations

  8. StaffingWeek 1

  9. StaffingWeek 2

  10. StaffingWeek 3

  11. StaffingWeek 4

  12. Integration Tasks • This section summarizes tasks that need to be done at the telescope and involve a modification to the existing instrument.

  13. Overall Image of Calibration System

  14. Enclosure Modifications P1640 Cables emerge from the top of the enclosure here. Cryotiger Lines Cal WFS Leach Electronics Box (See next slide)

  15. Design of the Side Panel Missing Handle

  16. Interferes with AO Spit

  17. Need To redesign Vacuum gauge/valve holder

  18. Needed to have a custom part made by Brooks Automation. To bring the end of the gas lines to the edge of the enclosure to allow for access to attach the gas lines to the dewar when the instrument is mounted to the telescope. Part was ordered 2/19. Will arrive 1st week of march. Leaving about 1/8” for the panel. ~3” 10.715”

  19. Cut Rear Dewar Foot Cut Here

  20. Reverse FPM Mount Need to reverse the FPM Mount to put the long motors in the direction shown. Also need to reverse the FPM in the mount.

  21. Lyot Stop Mount Put the Lyot Stop Mount on a new baseplate, to make room for the P1640 breadboard.

  22. 1) Temporarily reroute ADC Cables around Optical Stimulus, while its installed.2) Route New Cables, will tie them in similar places to existing cables. Optical Stimulus

  23. 80/20 Beamsplitter was replaced with a 50/50 beamsplitter. For additional light during science observations, we can remove the beamsplitter.Agilis tip/tilt stage will be controlled … New Location of Quad-Cell for Coronagraph FSM

  24. Integration Tasks • Machine Enclosure to hold Cal Gold Box • Machine Enclosure/install Cal patch panel • Cut hole in enclosure for Cal cold lines • Modify Dewar stand for Cal breadboard • Reverse FPM Mount • Reroute Risley Prism cables • Route New Cables • Move Quad Cell • Relocate Lyot Stop or Swap Mirror for beamsplitter

  25. Outstanding Questions • Need to Confirm IFU integration schedule • Confirm hole pattern for Handle on Side Panel • Identify magnitude of AO Spit interference problem. • Vacuum Valve/Gauge Fixture • Control of the Quad Cell Tip/Tilt mirror