After discussions in early 2006 LHCCWG launched Develop detailed commissioning plan for Stage I Target: 43 on 43 with 4 10 10 per bunch at * of 2m Leave 75ns and 25ns aspects for later Phase by phase Web based doc to start with Document later Report to LTC Activities 2006
E N D
After discussions in early 2006 LHCCWG launched Develop detailed commissioning plan for Stage I Target: 43 on 43 with 4 1010 per bunch at * of 2m Leave 75ns and 25ns aspects for later Phase by phase Web based doc to start with Document later Report to LTC Activities 2006 Kicked off March 8th Meet ~ every 2 weeks 18 meetings to date Topics ~ followed chronology of startup Dealt with a number of other issues LHC Commissioning Working Group 2006 R.Bailey, LHCCWG, December 2006
LHCCWG – topics treated R.Bailey, LHCCWG, December 2006
LHCCWG – topics treated R.Bailey, LHCCWG, December 2006
LHCCWG – topics treated R.Bailey, LHCCWG, December 2006
LHCCWG – topics treated • Generated a lot of follow up, some done, some not • Plenty of open actions, some important, some less so R.Bailey, LHCCWG, December 2006
2007 • January already pretty full • Lab opens January 8 • Post Mortem workshop January 16 17 • ATC ABOC review January 22 23 24 • LHC Machine-Experiments workshops January 25, 26 • Aims for beam uncertain • Hardware commissioning problems (Dipole short, Triplet quads) • 450GeV run ? • Sector test (from point 8 to dump) ? • Steve plans to reposition LTC as LHC commissioning body • Meet every week • Role of LHCCWG may need modification • Our availability for commissioning is at ~50% (cf ~20% in 2006) R.Bailey, LHCCWG, December 2006
So what should we (the core team) do in 2007? R.Bailey, LHCCWG, December 2006