iLembe District Municipality Municipal Water Infrastructure Grant Projects and Project Readiness

iLembe District Municipality Municipal Water Infrastructure Grant Projects and Project Readiness 13 TH SEPTEMBER 2013. ILEMBE DISTRICT MUNICIPALITY. L ocated 65km north of Durban O ne of the poorest Districts in KZN, yet one of the fastest growing

pepin
Download Presentation

iLembe District Municipality Municipal Water Infrastructure Grant Projects and Project Readiness

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. iLembe District Municipality Municipal Water Infrastructure Grant Projects and Project Readiness 13TH SEPTEMBER 2013

  2. ILEMBE DISTRICT MUNICIPALITY • Located 65km north of Durban • One of the poorest Districts in KZN, yet one of the fastest growing • Significant tourism and cultural attractions

  3. ILEMBE DISTRICT MUNICIPALITY: VISION 2027 • District is committed to people’s development, building unity and sense of belonging across racial and cultural boundaries, and to empowerment and job creation. • Vision 2027: to be a World Class African Destination, with Excellent Services and Quality of Life for its People

  4. ILEMBE DISTRICT MUNICIPALITY: SYSTEM CHARACTERISTICS • Total population - 680 000 • total number of connections – 32 437 • total length of mains - 2 205km • average System Input Volume – 62 Ml/day • average Billed Metered Consumption - 24 Ml/day • total number of water schemes - 111

  5. NON-REVENUE WATER MASTER PLAN EXECUTIVE SUMMARY - 2009 • Objective to move from NRW by Volume from approximately 50% to 27% by 2014 (part of President’s directive to halve water losses by 2014) • Reduce water leaks from approximately 30% to 17% of all water purchased/produced

  6. WC/WDM STRATEGY KPI’s Tasks Critical Success Factors Objectives GOAL • Analysis of various systems • Installation of flow loggers • Updating of records/plans • Regulation of water supply System Stabilising System Measurement & Stabilisation • Leak detection programme • Pressure reduction programme • Pipe replacement / refurbishment programme Reduction of pressure and leakage Priority Real Loss Reduction • systems 100% pressurised • reduce leaks to economic minimum • improve monitoring & reporting • maximise revenue from customer base Reduce NRW to 27% by Volume • Computation of Water Balance • Improvement of Billing systems • Reduction of illegal connections • Raising of community awareness • Sustained intervention & maintenance Water Conservation / Demand Management Service Delivery Efficiency Increased revenue • IDM Internal capacity • consumer restrictions • meter reading Meter all customers

  7. ILEMBE DISTRICT MUNICIPALITY: AREAS OF FOCUS • Mandini • Sundumbili • Tugela • Ntunjambili • Nkwambase • KwaShangase • KwaDukuza • Blythedale • Zinkwazi • Darnall • Zamani

  8. ILEMBE DISTRICT MUNICIPALITY: TRENDS

  9. ILEMBE DISTRICT MUNICIPALITY PERFORMANCE

  10. ILEMBE DISTRICT MUNICIPALITY: YEAR-ON-YEAR

  11. ILEMBE DISTRICT MUNICIPALITY: DISTRICT BREAKDOWN

  12. ILEMBE DISTRICT MUNICIPALITY: COMPARISONS

  13. “POOR RESULTS…?” • Billing of consumers remains a challenge • Leakage has remained steady, not worse • The wrong indicator is being used (NRW%) – this doesn't take into account improved service delivery and increased area of supply (“empty pipe syndrome”) • In spite of growth in the system (new connections and more pipes), only using 3Ml/day more • Leakage is only 5 times higher than best possible levels – better than all other Municipalities in KZN apart from Ugu)

  14. PROJECT LIST AND BUDGET ALLOCATION

  15. MWIG Funding Applications

  16. MWIG APPLICATIONS STATUS • WC/WDM District-Wide (pipe replacement) – Phase 1 approved: R49 400 000 • KwaChili/Shangase Rehabilitation – Phase 1 approved: R19 292 293 • Pump station refurbishment and upgrade – under review (R24 846 000) • Nsuze Water Supply – under review (R8 000 000)

  17. MWIG PROJECT READINESS WC/WDM District-Wide (pipe replacement): • Phase 1 targeted pipe replacement in Blythedale Beach, Stanger Manor, Stanger Heights (5,5km) • Number of beneficiaries: 6 465HH • Consultant appointed • Design and documentation in process • Contractor on site February 2014

  18. MWIG PROJECT READINESS KwaChili/Shangase Refurbishment: • Phase 1 WC/WDM in Ndwedwe to reduce demand from Hazelmere WTW by estimated 2,4 Ml/day • Number of beneficiaries: 23 470 HH • Consultant appointed • Feasibility study completed • Design and documentation in process • Intervention scheduled to commence October 2013 • Phase 1 completion June 2015

  19. MWIG PROJECT READINESS Contractor Shortlist: • Expression of Interest documents drawn up to shortlist contractors • CIDB grades 3 – 5 CE • CIDB grade 6 CE and upwards • Intention to manage risk to iLembe during implementation • Ensure delivery and adherence to time frames

  20. THANK YOU!