Gamma-ray Large Area Space Telescope. LAT Status Environmental Testing. GLAST Large Area Telescope: W Neil Johnson Naval Research Lab neil.johnson@nrl.navy.mil (202) 767 - 6817. LAT Status. LAT completed commissioning at SLAC May 10th. Determined effort by the Commissioner: Eric Grove
E N D
Gamma-ray Large Area Space Telescope LAT StatusEnvironmental Testing GLAST Large Area Telescope: W Neil Johnson Naval Research Lab neil.johnson@nrl.navy.mil (202) 767 - 6817
LAT Status • LAT completed commissioning at SLAC May 10th. • Determined effort by the Commissioner: Eric Grove • Excellent support leadership from • System Engineering: Pat Hascall • Electronics/ FSW: Gunther Haller • I&T OnLine: Ric Claus • OffLine: Anders Borgland • Packed up on May 11th and departed by dedicated truck (photos to follow) • Arrived NRL on Sunday, May 14th and installed in clean tent. MGSE and EGSE arrived on Tuesday, May 16th. • Up and running by Wednesday, completed post ship comprehensive performance test on Friday. • Continued calibrations and additional tests thru the weekend. • Installed new flight software and completed regression tests by Wednesday • Successfully completed Pre Environmental Review with GSFC on Thursday. • Moved to Vibration Test Lab on Friday. Vibe testing began yesterday.
Sensors ACD before installation of Micrometeoroid Shield 1 of 16 Calorimeter modules 1 of 16 Tracker modules
Data Acquisition System (-Z) EPU PDU PDU EPU HIB GASU HIB GASU HIB HIB HIB SIU SIU EPU
LAT Test Flow System Commissioning/ System Test 5/11/06 Shipment 5 days 5/16/06 You Are Here Install Radiators Offload & Set-up LAT Sine Vibe EMI/EMC Test Acoustic Test CPT 5 days 5 days 9 days 11 days 7 days 2 days PER 5/25/06 7/10/06 Remove Radiators T- Bal T- Cycle Pre TV CPT Pack and Ship Weight & CG 3 days 2 days 2 days 2 days 9/15/06 8 days 40 days PSR 9/13/06 NOTE: Durations for moving and setup have been incorporated into the total duration for the test.
Conclusion • The LAT is complete and tested. • No significant anomalies detected to date, except • Radiator heaters were damaged during assembly process and are now being replaced • No performance anomalies detected. Trending shows same instrument throughout assembly and test program. • The LAT Flight Software is essentially complete. • Missing GRB detection algorithm and event filter additions • Neither particularly relevant for ground testing. • Development will continue on the test bed at SLAC. • New OnLine operating system – LICOS – commissioned • The LAT project has successfully transferred activities (and people) to NRL and is efficiently executing its environmental test program.