1 / 11

RF measurements during long MD in Week 27 Monday 4/7/2011

RF measurements during long MD in Week 27 Monday 4/7/2011. Faraday Cage : T. Argyropoulos , T . Bohl , A. Burov , H. Damerau , J. E. Muller, E. Shaposhnikova , J. Tuckmantel CCC : H. Bartosik , W. Hofle , Y. Papaphilippou , G. Rumolo , B. Salvant , D. Valuch , SPS OP.

phong
Download Presentation

RF measurements during long MD in Week 27 Monday 4/7/2011

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. RF measurements during long MD in Week 27Monday 4/7/2011 Faraday Cage: T. Argyropoulos, T. Bohl, A. Burov, H. Damerau, J. E. Muller, E. Shaposhnikova, J. Tuckmantel CCC: H. Bartosik, W. Hofle, Y. Papaphilippou, G. Rumolo, B. Salvant, D. Valuch, SPS OP SPSU-BD 14/07/2011

  2. General Purpose: Compare the longitudinal parameters of the nominal with the low γt cycle, using the 50 ns LHC beam (1-4 batches) • Voltage adjustments of the 200 MHz RF cavities in both cycles, to obtain similar conditions • Stabilize with double RF system (V800=V200/10 in both cycles) • Studies of PS  SPS transmission • Higher intensities (1.8e11 p/b injected) Super cycle with two nominal magnetic LHC cycles for nominal and low γt optics • Intensities at injection ~ 1.3e11 p/b • Transverse param.  CCC Measurment outline No controlled longitudinal emittance blow-up

  3. RF Voltage set up – both cycles Q26: Bucket Area 0.65 eVs at ramp (from high intensity MDs) Q20: Bucket Area 0.6 eVs (sufficient) How to make them comparable? Q26 Q20 τinj~4 ns τinj~4 ns τFB~2.95 ns ε ~ 0.34eVs t ~ 13.9 s t ~ 15.3 s τFB~2.57 ns ε ~ 0.37eVs τFΤ~1.58 ns ε ~ 0.44eVs τFΤ~1.55 ns ε ~ 0.54eVs

  4. RF Voltage set up – Q26 • be more close to Q20 • no changes at FB. Cycle is optimized. • keep V high at ramp because we need • it for emitt. blow -up Q26 – 0.65 eVs Q26 – 0.60 eVs τinj~4 ns τinj~4 ns t ~ 13.9 s t ~ 15.1 s τFB~2.57 ns ε ~ 0.37eVs τFB~2.55 ns ε ~ 0.36eVs τFΤ~1.45 ns ε ~ 0.47eVs τFΤ~1.55 ns ε ~ 0.54eVs Unstable later in the cycle because of larger filling factor

  5. RF Voltage set up – Q20 • to have the same mismatch at injection • as for Q20 • slightly better for stability • still unstable  need 800 MHz τinj~3.9 ns τinj~4 ns τFB~2.9 ns ε ~ 0.33eVs τFB~2.95 ns ε ~ 0.34eVs t ~ 15.8 s t ~ 15.3 s τFΤ~1.58 ns ε ~ 0.44eVs τFΤ~1.58-1.61 ns ε ~ 0.45eVs

  6. Double RF system (V800=V200/10) Q26 Q20 BSM Losses~2-6 % Stable BLM Losses~7-10 % Very unstable, more for Q26

  7. PS  SPS transmission in Q26 • Studies of PS  SPS transmission in Q26 : • single batch • nominal Intensity (~1.3e11 p/b injected) • 3 different emittances (εnom < ε1< ε2 ) • 2 different bunch lengths • by changing the voltage in the 3 80 MHz RF cavities in PS (adjusting also the rotation time) • Preliminary results show: • higher ε  better stability •  more losses • higher τ  more losses • Analysis needs to be done.

  8. Transmission/losses • SPS page 1 examples for: • Q26 - single batch – double RF – nominal εinj • Similar for Q20 Nominal intensity High intensity   ~1.63e11 p/b ~1.81e11 p/b ~1.26e11 p/b ~1.33e11 p/b ~1.6e11 p/b was achieved for 4-batches at FT • Further analysis needs to be done

  9. Comparison Q26-Q20 (4 batches, 2 RFs) • Nominal Intensity (~1.3e11 p/b injected) • Higher Intensity (~1.8e11 p/b injected)

  10. Comparison Q26-Q20 (4 batches, 2 RFs) Unstable bunches at the end of the 1st batch at Flat Top

  11. Conclusions • Nominal Intensities (~1.3e11 p/b at FT) - losses~2-6 %: • Higher Intensities (~1.6e11 p/b at FT) - Double RF - losses~10 %: • Q20 is stable • Q26 some bunches unstable at flat top • PS  SPS transmission: dependence in εL and τ. • Single RF: Q20 is more stable than Q26 (higher threshold/Energy in the cycle) • Both unstable at the end of the ramp. • Double RF (V800=V200/10 ): Q20 is stable • Q26 some bunches unstable at flat top Future plans • Analysis of the PSSPS transmission data • Changes in 200 MHz RF Voltages to have more similar conditions at ramp: • 1) Increase Q20 or/and 2) decrease Q26 • Emittance blow-up at Q26 to stabilize the beam. • Keep the voltage dips at injections (23 MV) for Q26 voltage program • in the cases of more than 1 batch injections.

More Related