1 / 22

Project Management Tools

Project Management Tools. MHA 6350 Dr. Burton. How Hillary looks upon a crook vs. how Hillary looks upon an American hero: . Tools. GANTT Charts PERT/CPM. GANTT CHARTS. Developed by Charles Gantt in 1917.

pia
Download Presentation

Project Management Tools

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Project Management Tools MHA 6350 Dr. Burton

  2. How Hillary looks upon a crook vs. how Hillary looks upon an American hero:

  3. Tools • GANTT Charts • PERT/CPM

  4. GANTT CHARTS • Developed by Charles Gantt in 1917. • The layout of a Gantt Chart uses information in columns on the left of a matrix to identify tasks, task managers, duration and in some cases cost. • To the right of each task in the matrix is a bar that denotes to duration of the task. • Project management software employs Gantt charts.

  5. Project: Constructing a Home

  6. Project: Constructing a Home

  7. Project: Constructing a Home 10/5 10/10 10/15 10/20 10/25 10/30 11/4 11/9 11/14 11/19 11/24 11/29

  8. Examples Links http://www.smartdraw.com/examples/view/index.aspx?catID=.Examples.SmartDraw.Gantt_Charts%2c_Project_Charts_%26_Timelines.Gantt_Charts http://www.ganttchart.com/

  9. 13-28 2 6 7 7 13 1 3 9 2 15 8 9 3 4 1 11 16 10 10 4 14 5 11 8 5 12 6

  10. Program Evaluation and Review Technique(PERT)May also be referred to as: Critical Path Method (CPM) Developed in the late 50s by the Navy. Was used the Polaris program for submarined launched ballistic missiles. Originally adopted by the Department of Defense for large projects. Later was adopted by construction industry. PERT uses work groupings called activities. Activities are measured in time. Each activity is represented by an arrow.

  11. Project: Constructing a Home

  12. A PERT network for constructing a home. 5 i 1 c 6 Outside plumbing e 10 Inside plumbing Plumbing inspection FINISH Start 5 2 12 9 3 9 1 2 3 4 8 10 11 a Excavating b Foundation d Framing f Wiring k Walls l Interior Finish g 5 j 2 Shingling Roof- ing h 9 Brickwork Landscaping 6 n 8 0 Exterior Finishing 7 m 9 7 Source: Lapin, 1994

  13. A PERT network for constructing a home. 5 i 1 c 6 Outside plumbing e 10 Inside plumbing Plumbing inspection FINISH Start 5 2 12 9 3 9 1 2 3 4 8 10 11 a Excavating b Foundation d Framing f Wiring k Walls l Interior Finish g 5 j 2 Shingling Roof- ing h 9 Brickwork Dummy Activity Landscaping 6 n 8 0 Exterior Finishing 7 m 9 7 Source: Lapin, 1994

  14. A PERT network for constructing a home. 29 11 5 TE Earliest Possible Event Time i 1 c 6 Outside plumbing e 10 Inside plumbing Plumbing inspection 0 FINISH Start 5 7 19 5 2 12 9 3 9 1 2 3 4 8 10 11 a Excavating b Foundation d Framing f Wiring k Walls l Interior Finish g 5 j 2 Shingling Roof- ing h 9 Brickwork Landscaping 6 n 8 0 Exterior Finishing 7 m 9 7 Source: Lapin, 1994

  15. A PERT network for constructing a home. 28 29 5 i 1 c 6 Outside plumbing e 10 Inside plumbing Plumbing inspection 0 FINISH Start 5 7 19 30 26 5 2 12 9 3 9 1 2 3 4 8 10 11 a Excavating b Foundation d Framing f Wiring k Walls l Interior Finish g 5 j 2 Shingling Roof- ing h 9 Brickwork Landscaping 6 24 n 8 0 Exterior Finishing 7 m 9 7 Source: Lapin, 1994

  16. A PERT network for constructing a home. 5 i 1 c 6 Outside plumbing e 10 Inside plumbing Plumbing inspection 0 FINISH Start 5 7 19 30 33 5 2 12 9 3 9 1 2 3 4 8 10 11 a Excavating b Foundation d Framing f Wiring k Walls l Interior Finish 42 39 g 5 j 2 Shingling Roof- ing h 9 Brickwork Landscaping 6 24 n 8 0 Exterior Finishing 7 m 31 9 7 16 24 Source: Lapin, 1994

  17. Project: Constructing a Home FINISH TOTAL 42 days

  18. A PERT network for constructing a home. CRITICAL PATH 29 5 TL Latest Allowable Event Times 29 i 1 c 6 Outside plumbing Plumbing inspection 0 e 10 Inside plumbing 42 5 0 30 7 19 33 42 Start 5 30 7 19 33 FINISH 5 2 12 9 3 9 1 2 3 4 8 10 11 a Excavating b Foundation d Framing f Wiring k Walls l Interior Finish g 5 h 9 Brickwork j 2 Shingling Roof- ing Backwards Pass Subtract each activity from succeeding TL Where event is beginning point for more than one activity use the smallest difference. 27 Landscaping 6 34 24 n 8 0 Exterior Finishing 7 m 31 27 9 7 24 Source: Lapin, 1994

  19. A PERT network for constructing a home. 29 CRITICAL PATH 5 29 0 i 1 0 c 6 Plumbing inspection Outside plumbing 5 42 0 e 10 30 33 7 Inside plumbing 19 5 42 0 30 33 7 0 0 19 Start 0 0 0 FINISH 0 5 2 12 9 3 9 1 2 3 4 8 10 11 a Excavating b Foundation d Framing f Wiring k Walls l Interior Finish g 5 h 9 Brickwork j 2 Shingling Roof- ing TL 27 34 Landscaping TE 6 24 31 3 n 8 0 Event Slack Times = TL - TE 3 Exterior Finishing 7 m 27 9 7 24 Source: Lapin, 1994 3

  20. Planning and ControlActivity Scheduling • ES=Early Start Time = TE for preceding event. • EF=Early Finishing Time = ES + t • LF=Late Finishing Time = TL for succeeding event. • LS=Late Start Time = LF - t

  21. Limits for Scheduling Starting Times Finishing Times ES LS EF LF Preceding TE LF – t ES + t Succeeding TL Activity t

  22. Activity Slack time = LF - EF. Finishing Time LF EF Activity Slack Time Activity

More Related