Project Management Tools MHA 6350 Dr. Burton
How Hillary looks upon a crook vs. how Hillary looks upon an American hero:
Tools • GANTT Charts • PERT/CPM
GANTT CHARTS • Developed by Charles Gantt in 1917. • The layout of a Gantt Chart uses information in columns on the left of a matrix to identify tasks, task managers, duration and in some cases cost. • To the right of each task in the matrix is a bar that denotes to duration of the task. • Project management software employs Gantt charts.
Project: Constructing a Home 10/5 10/10 10/15 10/20 10/25 10/30 11/4 11/9 11/14 11/19 11/24 11/29
Examples Links http://www.smartdraw.com/examples/view/index.aspx?catID=.Examples.SmartDraw.Gantt_Charts%2c_Project_Charts_%26_Timelines.Gantt_Charts http://www.ganttchart.com/
13-28 2 6 7 7 13 1 3 9 2 15 8 9 3 4 1 11 16 10 10 4 14 5 11 8 5 12 6
Program Evaluation and Review Technique(PERT)May also be referred to as: Critical Path Method (CPM) Developed in the late 50s by the Navy. Was used the Polaris program for submarined launched ballistic missiles. Originally adopted by the Department of Defense for large projects. Later was adopted by construction industry. PERT uses work groupings called activities. Activities are measured in time. Each activity is represented by an arrow.
A PERT network for constructing a home. 5 i 1 c 6 Outside plumbing e 10 Inside plumbing Plumbing inspection FINISH Start 5 2 12 9 3 9 1 2 3 4 8 10 11 a Excavating b Foundation d Framing f Wiring k Walls l Interior Finish g 5 j 2 Shingling Roof- ing h 9 Brickwork Landscaping 6 n 8 0 Exterior Finishing 7 m 9 7 Source: Lapin, 1994
A PERT network for constructing a home. 5 i 1 c 6 Outside plumbing e 10 Inside plumbing Plumbing inspection FINISH Start 5 2 12 9 3 9 1 2 3 4 8 10 11 a Excavating b Foundation d Framing f Wiring k Walls l Interior Finish g 5 j 2 Shingling Roof- ing h 9 Brickwork Dummy Activity Landscaping 6 n 8 0 Exterior Finishing 7 m 9 7 Source: Lapin, 1994
A PERT network for constructing a home. 29 11 5 TE Earliest Possible Event Time i 1 c 6 Outside plumbing e 10 Inside plumbing Plumbing inspection 0 FINISH Start 5 7 19 5 2 12 9 3 9 1 2 3 4 8 10 11 a Excavating b Foundation d Framing f Wiring k Walls l Interior Finish g 5 j 2 Shingling Roof- ing h 9 Brickwork Landscaping 6 n 8 0 Exterior Finishing 7 m 9 7 Source: Lapin, 1994
A PERT network for constructing a home. 28 29 5 i 1 c 6 Outside plumbing e 10 Inside plumbing Plumbing inspection 0 FINISH Start 5 7 19 30 26 5 2 12 9 3 9 1 2 3 4 8 10 11 a Excavating b Foundation d Framing f Wiring k Walls l Interior Finish g 5 j 2 Shingling Roof- ing h 9 Brickwork Landscaping 6 24 n 8 0 Exterior Finishing 7 m 9 7 Source: Lapin, 1994
A PERT network for constructing a home. 5 i 1 c 6 Outside plumbing e 10 Inside plumbing Plumbing inspection 0 FINISH Start 5 7 19 30 33 5 2 12 9 3 9 1 2 3 4 8 10 11 a Excavating b Foundation d Framing f Wiring k Walls l Interior Finish 42 39 g 5 j 2 Shingling Roof- ing h 9 Brickwork Landscaping 6 24 n 8 0 Exterior Finishing 7 m 31 9 7 16 24 Source: Lapin, 1994
Project: Constructing a Home FINISH TOTAL 42 days
A PERT network for constructing a home. CRITICAL PATH 29 5 TL Latest Allowable Event Times 29 i 1 c 6 Outside plumbing Plumbing inspection 0 e 10 Inside plumbing 42 5 0 30 7 19 33 42 Start 5 30 7 19 33 FINISH 5 2 12 9 3 9 1 2 3 4 8 10 11 a Excavating b Foundation d Framing f Wiring k Walls l Interior Finish g 5 h 9 Brickwork j 2 Shingling Roof- ing Backwards Pass Subtract each activity from succeeding TL Where event is beginning point for more than one activity use the smallest difference. 27 Landscaping 6 34 24 n 8 0 Exterior Finishing 7 m 31 27 9 7 24 Source: Lapin, 1994
A PERT network for constructing a home. 29 CRITICAL PATH 5 29 0 i 1 0 c 6 Plumbing inspection Outside plumbing 5 42 0 e 10 30 33 7 Inside plumbing 19 5 42 0 30 33 7 0 0 19 Start 0 0 0 FINISH 0 5 2 12 9 3 9 1 2 3 4 8 10 11 a Excavating b Foundation d Framing f Wiring k Walls l Interior Finish g 5 h 9 Brickwork j 2 Shingling Roof- ing TL 27 34 Landscaping TE 6 24 31 3 n 8 0 Event Slack Times = TL - TE 3 Exterior Finishing 7 m 27 9 7 24 Source: Lapin, 1994 3
Planning and ControlActivity Scheduling • ES=Early Start Time = TE for preceding event. • EF=Early Finishing Time = ES + t • LF=Late Finishing Time = TL for succeeding event. • LS=Late Start Time = LF - t
Limits for Scheduling Starting Times Finishing Times ES LS EF LF Preceding TE LF – t ES + t Succeeding TL Activity t
Activity Slack time = LF - EF. Finishing Time LF EF Activity Slack Time Activity