1 / 16

General Key Point Indicators China EMU Project Week 8 全面关键项点指标 中国动车组项目 第六周

General Key Point Indicators China EMU Project Week 8 全面关键项点指标 中国动车组项目 第六周. Frédéric SANCHEZ 孙福德 Deputy Project Manager EMU China 中国动车组项目副经理. February 13th, 08 2008 年2月13日. EMU CRH5 – Fleet failure record CRH5 动车组 - 列车故障记录.

pier
Download Presentation

General Key Point Indicators China EMU Project Week 8 全面关键项点指标 中国动车组项目 第六周

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. General Key Point Indicators China EMU ProjectWeek 8全面关键项点指标中国动车组项目第六周 Frédéric SANCHEZ 孙福德 Deputy Project Manager EMU China中国动车组项目副经理 February 13th, 08 2008年2月13日

  2. EMU CRH5 – Fleet failure recordCRH5 动车组 - 列车故障记录 • Alstom failures has been recorded by Alstom CW Team and are consolidated by RAMS Team 故障已由Alstom 调试质保人员记录,并由 RAMS 团队统一合并 • CRC failures are recorded with incomplete information and some of them are not consolidated by Alstom CRC故障的记录信息不完整,其中部分未经Alstom 团队确认 • The total of the failures is the view of MOR 合计故障呈报给铁道部 过去八周列车故障记录-逐列 KPI Project EMU China - 14/02/2008 - P 2

  3. EMU CRH5 – Fleet failure record CRH5 动车组 - 列车故障记录 • Some of the failures of this week are not closed yet. The figure of this present week could be slightly superior next week.本周故障中有一些尚未关闭。目前这一周的该项数字可能略微高于下周。 每运行10,000公里的故障数量 -所有列车 每10000公里的故障数量/ 周 公里总数/ 周 每10000公里故障/ 周 整个趋势推导 KPI Project EMU China - 14/02/2008 - P 3

  4. EMU CRH5 – Fleet failure record CRH5 动车组 - 列车故障记录 每10,000公里运行的故障数量 (001和004) 每10,000公里运行的故障数量 (010和011) KPI Project EMU China - 14/02/2008 - P 4

  5. EMU CRH5 – Fleet failure recordCRH5 动车组 - 列车故障记录 每10,000公里运行的故障数量 (012和013) 每10,000公里运行的故障数量 (016和017) KPI Project EMU China - 14/02/2008 - P 5

  6. EMU CRH5 – Fleet failure record CRH5 动车组 - 列车故障记录 每10,000公里运行的故障数量 (019和020) 每10,000公里运行的故障数量 (014和015) KPI Project EMU China - 14/02/2008 - P 6

  7. EMU CRH5 – Fleet failure record CRH5 动车组 - 列车故障记录 每10,000公里运行的故障数量 (018和021) KPI Project EMU China - 14/02/2008 - P 7

  8. EMU CRH5 – Fleet failure record CRH5 动车组 - 列车故障记录 每10,000公里运行的故障数量 (022和023) 每10,000公里运行的故障数量 (024和025) KPI Project EMU China - 14/02/2008 - P 8

  9. EMU CRH5 – Fleet failure record CRH5 动车组 - 列车故障记录 每10,000公里运行的故障数量 (026和027) 每10,000公里运行的故障数量 (028和029) KPI Project EMU China - 14/02/2008 - P 9

  10. EMU CRH5 – Fleet failure recordCRH5 动车组 - 列车故障记录 每10,000公里运行故障/ 周 车体 每10,000公里运行故障/ 周 转向架 每10,000公里运行故障/ 周 电气设备 每10,000公里运行故障/ 周 制动和气动系统 KPI Project EMU China - 14/02/2008 - P 10

  11. EMU CRH5 – Fleet failure recordCRH5 动车组 - 列车故障记录 每10,000公里运行故障/ 周 牵引子系统 每10,000公里运行故障/ 周 TCMS 每10,000公里运行故障/ 周 辅助子系统 每10,000公里运行故障/ 周 门系统 KPI Project EMU China - 14/02/2008 - P 11

  12. EMU CRH5 – Fleet failure recordCRH5 动车组 - 列车故障记录 每10,000公里运行故障/ 周 空调系统 每10,000公里运行故障/ 周 旅客信息系统 每10,000公里运行故障/ 周 内装 每10,000公里运行故障/ 周 给水和卫生系统 KPI Project EMU China - 14/02/2008 - P 12

  13. EMU CRH5 – Fleet failure recordCRH5 动车组 - 列车故障记录 每10,000公里运行故障/ 周 配餐设备 每10,000公里运行故障/ 周 安全设备 KPI Project EMU China - 14/02/2008 - P 13

  14. EMU CRH5 – Fleet failure record per weekCRH5 动车组 - 每周列车故障记录 TOP failure of the week: 本周几大: • Carbody 车体 • Traction and Auxiliairy 牵引及辅助 • Door System 门系统 • Interiors 内装 • Water and Waste System 给水和卫生系统 第六周故障 -按每列车子系统划分 电气设备 牵引子系统 辅助子系统 配餐设备 安全设备 KPI Project EMU China - 14/02/2008 - P 14 车体 转向架 制动和气动系统 门系统 空调系统 内装 给水卫生系统

  15. EMU CRH5 – Fleet MileageCRH5 动车组 - 列车里程Total Kilometres per Week 每周里程合计 • Current contractual time: No less than 15h from 2Mkm. Today the fleet ran 3.4MKm 当前合同所规定时间:距 400 万公里不少于1月。目前,列车运行了 340 万公里 • Contractual milestones estimated at Dec.(2M), Mar.(4M), Jun.(10M) and Sept.(15M) 合同规定的预计里程碑: 12月(200 万)、3月(400万)、6月(1000万)、9月(1500万) 每周累积公里数-逐列车 每周非累积公里数-逐列车 每周非累积公里数-逐列车 每周累积公里数-逐列车 KPI Project EMU China - 14/02/2008 - P 15

  16. EMU CRH5 – Fleet MileageCRH5 动车组 - 列车里程Total Kilometres per Week 每周里程合计 每周非累积公里数-逐列车 每周累积公里数-逐列车 每周非累积公里数-逐列车 每周累积公里数-逐列车 KPI Project EMU China - 14/02/2008 - P 16

More Related