1 / 24

Hydro Development - The Challenges and Response

Hydro Development - The Challenges and Response. R.V. SHAHI SECRETARY MINISTRY OF POWER GOVERNMENT OF INDIA. ICOLD Conference Montreal (Canada) June 20, 2003. Share in generation - Global scenario. 1973. 2000. 6,121 TWh. 15,379 TWh.

pillan
Download Presentation

Hydro Development - The Challenges and Response

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Hydro Development - The Challenges and Response R.V. SHAHI SECRETARY MINISTRY OF POWER GOVERNMENT OF INDIA ICOLD Conference Montreal (Canada) June 20, 2003

  2. Share in generation - Global scenario 1973 2000 6,121 TWh 15,379 TWh ** Other includes geothermal, solar, wind, combustible renewables & waste • Hydro share has reduced from 21% to 17.1% • Nuclear share increase significant from 3.3% to 16.9%

  3. Hydro Potential - Global Scenario Only 18% of hydro potential utilised in India % Potential utilized 58% 41% 31% 18% 18%

  4. Power Supply position in India

  5. Hydro development : Rationale Fuel Mix Years

  6. Thrust on hydro • Consistent shortages caused emphasis on short lead projects • Increase in thermal proportion - Abundant coal reserves / shorter project lead / lesser R&R problems • Still shorter lead of gas projects caused emphasis off the longer lead hydro projects • Nuclear also developed as reliable mode of thermal generation Contd…...

  7. Thrust on hydro Contd…... • Despite best efforts during planning stage, the hydro development constrained due to longer gestation construction period • environmental constraints • rehabilitation & resettlement problems • inadequate investigations : - geological / hydrological surprises Contd…...

  8. Thrust on hydro Contd…... • Turnaround now in hydro development • Government of India committed quantum jump in financial allocations • Varied facilitating measures undertaken # Added during last twenty years - 13,666 MW To add during five years (2002-07) - 14,393 MW Contd…...

  9. Thrust on hydro Contd…... • Hydro the preferred source • Clean power - no pollution ramifications during operation • Most cost effective option, free from inflation linked to fuel consumption • Effective tool for load management - to counter large variations between peak and off peak requirements and frequency variations • Supports and supplements socio economic development of the region - hydro potential mostly in areas which need substantial support for economic development • Integrated solution for power, drinking water and irrigation

  10. Initiatives on hydro development Policy on hydro development by Government of India : • Ensuring higher capacity addition through : • Enhanced Central Sector outlay • Advance Action plan for next ten years • Exploitation of untapped hydroelectric potential • Ranking Studies • Basin wise Action Plan • Preparation of feasibility studies and DPRs - 50,000 MW hydro initiative Contd...

  11. Contd…... • Promoting small and mini hydel projects • 25 MW and below fall under ‘non conventional’ category - qualify for benefits • Tariff dispensation • Rationalization of hydro tariff by allowing premium on sale rate during peak period • CERC has approved 5% hydro development surcharge on annual fixed charges for Central hydro stations Contd...

  12. Contd…... • Facilitating and expediting measures undertaken • Three stage clearance procedure for Central Sector/ Joint ventures • Simplified clearances further liberalized by Electricity Act, 2003 • Resolution of inter State issues on sharing of water and power • Support for land acquisition, R&R, Catchment Area Treatment • Emphasis on quality of Survey and Investigations • Renovation, Modernization & Uprating of existing stations

  13. Hydro development - the process Potential assessed(845 Schemes) 150,000 MW Ranking Studyof unharnessed 399 schemes 107,000 MW Hydro Initiative(162 schemes) 50,000 MW

  14. 50,000 MW Hydroelectric Initiative • 162 schemes identified with installed capacity of 50,560 MW located in sixteen States • Initiative launched in May 2003 • Consultants identified to undertake Feasibility Studies • Preparation of Preliminary Feasibility Reports - Dec.’03 - Sep.’04 Contd...

  15. 50,000 MW Hydroelectric …….. Contd…... • Detailed Project Reports - Jan.’04 - Jan.’06 for promising projects, depending on PFRs results • DPR preparation also through reputed International Consultants • Process of selection of Consultants for DPR of large projects through ICB • Clearances / sanctions - Sep.’04 - Jul. ‘06 • Implementation - 2007 - 2017

  16. Major Challenges and Response Environment protection • Comprehensive legislation in place with well laid out principles and guidelines • Environment Impact Assessment (EIA) studies carried out to evaluate pre and post construction scenarios • Minimum use of forest area and close monitoring to ensure efficient implementation of EMPs • Plan to create Forest Banks for compensatory afforestation Contd...

  17. Contd…... Rehabilitation and resettlement Lessons learnt from past - greater synthesis now between project developers, affected persons and authorities • A national R&R policy being contemplated • In parallel Ministry of Power has stepped up coordinated efforts with local / state authorities • Project specific monitoring mechanism put in place to ensure implementation of R&R plans Contd...

  18. Contd…... Safety of Dams • Built up considerable knowledge base from global experience • A few Institutions in the country have also geared up - hardware/ software • Experts of repute from across the countries consulted for studies and guidance Reliability of Investigations • Technological / procedural improvements in Survey & Investigations • State of Art equipment / technology • Consultation with Experts - a continuous process Contd...

  19. Contd…... Multiple agencies’ clearances The players : M/o • Power • Environment & Forest • Water Resources / Central Water Commission • Continuous process of improvement • Procedures streamlined • Speedy clearances • System of regular Inter Ministerial reviews in force Contd...

  20. Contd…... Compressing Construction cycle • Construction management • Construction lead reduced - 4 to 5 years • Clearance / approval period reduced by 18 to 24 months with Three stage clearance procedure • Construction technology • Choice of technology - mitigate the geological / hydrological surprises - faster implementation Contd...

  21. Contd…... Communication Consensus arrived through regular consultation process • Political consensus • Public awareness • Media support Contd...

  22. Opportunities in Indian hydroelectric sector Hydro Capacity addition target : 2002-07 - 14,000 MW 2007-17 - 50,000 MW • Detailed investigations and preparation of DPRs • EPC contracts for development of projects • Package contracts in other projects • Investment as equity partner / J.V. opportunities • Funding for the project

  23. Major concern, so long, of the investors - Poor financial health and creditworthiness of the Sector : Distribution Reforms, the key confidence indicator • Electricity Act, 2003 notified and A.P.D.R.P. scheme introduced by Government of India : Distribution business to become commercially viable within next 3 to 5 years • Competitive Environment, Power Trading Hydro as inexpensive power more viable

  24. Thank you Ministry of Power Website http://powermin.nic.in

More Related