1 / 14

PRESENTATION 1 Quarter 2003 14 May 2003

PRESENTATION 1 Quarter 2003 14 May 2003. Profit and Loss Account 1Q03 – DSND Inc. Balance sheet 1Q03 – DSND Inc. DSND – debt per May 2003. Convertible Bond: - NOK 300 million - Duration 3 years from 1/2003 - Strike: NOK 20,00 per DSND share - Conversion: At pre-determined date

pippa
Download Presentation

PRESENTATION 1 Quarter 2003 14 May 2003

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PRESENTATION 1 Quarter 2003 14 May 2003

  2. Profit and Loss Account 1Q03 – DSND Inc.

  3. Balance sheet 1Q03 – DSND Inc.

  4. DSND – debt per May 2003 • Convertible Bond: • - NOK 300 million • - Duration 3 years from 1/2003 • - Strike: NOK 20,00 per DSND share • - Conversion: At pre-determined date • each month for the entire period • - Interest: 8% coupon • BNDES (Brazil), Two loans: • - USD 8,3 million (until 2012) • - USD 1,7 million (until 2008) • Financial lease on Buccaneer: • - USD 4,3 million (until 2005)

  5. Profit and Loss Account 1Q03 – Subsea 7

  6. Balance sheet 1Q03 – Subsea 7

  7. Backlog 1Q03 – Subsea 7 • Subsea 7 had at the end of 1Q a worldwide order book of approx USD 790 million • Geographical split of Backlog UK USD 333 million Norway USD 218 million Brazil USD 104 million GOM USD 86 million Asia Pac USD 49 million Total USD 790 million • USD 70 million new contracts awarded during April

  8. Main reasons for weak 1Q results in Subsea 7 • Seasonal variances North Sea • Extensive program for maintenance, repair and • dry-dockings • Cost overrun on a couple of projects • Slightly lower activity than forecasted in the GOM • and AsiaPac

  9. Main reasons for weak 1Q results in Subsea 7 (cont.) Overview of vessels:

  10. Subsea 7 – comments to each region • Norway • Activities performed according to plan • JV with Stolt Offshore awarded two-year extension from Statoil on construction framework contract • UK • Results affected by cost overrun on one bundle project • Serveral new contracts secured • Brazil • Overall market activities remain strong • Technical difficulties on two vessels resulting in significant periods of downtime in 1Q • Asia Pacific • Results affected by reduced profit from one project, project still profitable • GoM • Lower activity than expected during 1Q, but several new contracts awarded • West-Africa • Efforts with targeting entry the market given high priority

  11. DSND – Non Subsea 7 assets • Olympic Princess • Cable repair and maintenance • Contract to ACMA, an umbrella organization for 21 cable companies, until yearend 2003 plus options • The vessel is on lease from Olympic Shipping for the same period as its current contract • Buccaneer • Well service • The vessel Dry-docked in March • Short- and long term possibilities for the vesselactively pursued • Joides Resolution • Ocean Drilling Program to September 2003 (research project/program) • New possibilities for the vessels actively pursued • 50/50 owned with Transocean

  12. DSND – Non Subsea 7 assets • Big Orange • Well maintenance • Contract to Dowell Schlumberger to August 2009 (certain rights to cancel from 2005) • 41% owned • Supply fleet Brazil through DSND Consub • 10 owned supply-/crew vessels • 3 supply vessels on management • The fleet achieved a utilization ratio of 97% during 1q • All vessels on contracts to Petrobras • Atria, Helder and Taurus • Currently laid-up • Modfrag • Development of Combat Management System for Brazilian Navy until 2005 • Another development contract for one Corvette received in November last year

  13. 20 Largest shareholders pr. 13 May 2003

  14. Outlooks 2003 Market view • General market activity should remain strong • Oil price above USD 20 per barrel • Substantial number of offshore projects committed or in the early stages of production • Subsea activities continues to grow • Development of satellite and marginal fields • Increased tieback activities • Growth in deep-water areas Financial view • Significant improvement in results expected • for 2Q and 3Q compared with 1Q • High utilisation (89%) of vessel fleet • committed for 2Q and 3Q

More Related