An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Future Planning for SLAC Persis S. Drell

  2. Scenarios Study 2003: Process • Started early in 2003 • Inclusive of SLAC faculty, staff and users. • Final Report early 2004 • Context • There will be a linear collider built and SLAC will be a major participant • PEP-II/BaBar program has a clear future to 2010 • Growth in particle astrophysics with initiation of KIPAC • Future of SSRL to 2015 and beyond determined by SPEAR3 and LCLS • Charge • Develop models for SLAC’s role in a future linear collider • Explore other exciting science opportunities for laboratory in LC/LCLS era • What will the lab look like a decade from now? SLAC Scenarios

  3. Process: surveyed the major themes in HEP and Particle Astrophysics & Cosmology • B day: 1036 (or 2 x 1035?) e+e- B factory • Neutrino day:accelerator/reactor/solar n oscillations, bb0n • LHC day:accelerator & detector projects for luminosity upgrade • Z/Higgs day:gg @ 30 GeV; e+e- -> Z (10M -> 3G Z/yr); e+e- -> ZH • Two beam day:gg -> Higgs “shop”; 2 beam e+e- -> Z or ZH; CLIC R&D; plasma afterburner for ZH • Cosmology day:Dark matter/energy via SNAP, LSST, Clusters • Additional Seminars with discussion: • An International Linear Collider and What it Might Mean for SLAC (Dave Burke) • Colloquium on ITER, including management (Rob Goldston) • Colloquium on ALMA, including management (Robert Brown) SLAC Scenarios

  4. Excellence SLAC Scientific Particle Astro Physics Science w/ Sync Light High Energy Frontier Flavor Physics Accelerator Physics and Detector Development The Ubiquitous Linac SLAC Scenarios

  5. Pillars of the SLAC Program • The High Energy Frontier • Flavor Physics • Science with Synchrotron Light • Particle Astrophysics and Cosmology • Criteria for Program Development • Cutting edge science opportunites • Opportunities to engage users • Scope of SLAC’s contributions must be commensurate with SLAC’s role as a national lab • Assumption • Linear Collider exits somewhere in the world SLAC Scenarios

  6. The High Energy Frontier

  7. Models for SLAC Participation in LC • Linear Collider the highest priority for high energy program at the laboratory • SLAC continues to champion x-band RF technology choice and strongly supports a US site for the facility. • SLAC is committed to the LC, independent of location and independent of technology • Scenarios committee studied • what are the component pieces of that commitment • how does the laboratory’s on-site effort change depending on downstream decisions: • technology choice • location • Conclusion: The scope of SLAC’s effort supporting LC largely independent LC location and technology SLAC Scenarios

  8. Model of SLAC LC Participation • Model exercise led to conclusion that a reasonable target for SLAC responsibility ~10% of the TPC • Conclusion site and technology independent • Details of the involvement do depend on site and technology • On-shore: US contribution 60% of TPC • 40% of TPC to Project office • SLAC responsible for ~10% of TPC • Off-shore: US contribution 25% of TPC • 5% of TPC to Project office • SLAC responsible for ~10% of TPC • SLAC & FNAL have major US portions • SLAC would like to have major responsibility for one of the two detectors • 50% contribution to 350 M$ detector • 50 physicists and main engineering group at SLAC • Some prototyping and possibly responsibility for major assemblies • SLAC should strive to be collaboration host SLAC Scenarios

  9. Models for SLAC Participation in LHC Upgrades • LHC is the high energy frontier • Complements involvement with LC • Opportunity for small but significant involvement • Machine opportunities in this phase include: • RF upgrades to shorten bunch lengths • RF crab cavities to increase crossing angle • Major detector challenge is inner tracker • Concern could divert resources from • traditional role in electron-based accelerators • linear collider SLAC Scenarios

  10. Flavor Physics

  11. Future B-Physics Program • A 2 x 1035 (~$200M) or 1036 (~$500M) B factory: • Quark flavor mixing sensitive to new physics • LHC can directly discover new physics of EWSB • determine its mass scale • B factory would supply unique and complementary flavor and CP information • Example: SUSY • LHC: measures flavor-diagonal squark masses • B-factory: sensitive to flavor-off-diagonal squark mass and CP-violating phases • If there is new physics in the quark flavor sector, such a machine should be built. • Complements LHC • This is the major variable between scenarios. • Requires accelerator R&D at luminosity frontier SLAC Scenarios

  12. Future Neutrino Program • Neutrinoless double beta decay (bb0n) • Mass potentially related to unification scale • Majorana mass may have implications for baryon asymmetry of the universe • Based on EXO technology if R&D successful • Consider other options if EXO finds showstopper • Participation of the SLAC community in long baseline neutrino oscillation experiments was considered. However, many others are working on this problem and there was not a clear SLAC role SLAC Scenarios

  13. Science with Synchrotron Light

  14. Science with Synchrotron Light • Did not extensively review • Opportunities aggressively developed over past 5 years • SPEAR3 • LCLS • Enabling broad spectrum of science • Materials Science • Structural Biology • Environmental Science • Fempto-chemistry • Nanoscale Dynamics • ..... • Path forward well determined • Includes doubling of SSRL staff by 2010 • Plateau 2010 onward • Continued Accelerator R&D Important SLAC Scenarios

  15. Particle Astrophysics and Cosmology

  16. Particle Astrophysics and Cosmology • KIPAC  Area of growth • Expect doubling of current effort • Did not want to interfere with birth of Institute • Model on: • GLAST ISOC • Involvement with JDEM, LSST • Future major projects? • Identified level of effort • 150-200 technical personnel by 2010 SLAC Scenarios

  17. Scenarios

  18. Pillars of the Program • High Energy Frontier • Participation in LC • Participation in LHC upgrades • High Gradient Accelerator R&D • Science with Synchrotron Light • SPEAR III • LCLS • Accelerator R&D aimed at machines past LCLS.V1 • Flavor Physics • mne • Future B-factory program • High Luminosity Accelerator R&D • Particle Astrophysics and Cosmology • GLAST ISOC • Scaled to example of LSST, JDEM participation SLAC Scenarios

  19. Scenarios: Details • Scenario 1: • LC Anywhere • no B-factory upgrade past 3x1034 • Advanced accelerator R&D doubling in 10 years • Scenario 2 • LC Anywhere • 2x1035 B-factory at SLAC • Advanced accelerator R&D grows by 50% in 10 years • Scenario 3 • LC on shore • 1036 B-factory at KEK • Full Linac capability preserved • Advanced accelerator R&D doubling in 10 years • Scenario 4 • LC off shore • 1036 B-factory at SLAC • Advanced accelerator R&D grows by 50% in 10 years SLAC Scenarios

  20. Conclusions of Scenarios Study • Committee enthusiastic about rich program of science in all scenarios • Scope of the linear collider effort at SLAC independent of LC location and technology • SLAC committed to warm x-band and US site • Committee recommends SLAC consider participating in LHC luminosity upgrades • Level of advanced accelerator R&D should grow • Greatest variable in scenarios is the future of the B-factory program • Future SSRL program has well defined growth path • Particle astrophysics should at least double • SLAC Linac will continue to be an essential part of the program SLAC Scenarios

  21. Since Scenarios.... • ITRTP SLAC ILC R&D aligning to cold decision • Decision not to pursue Super-B at SLAC • FY06 budget • B-factory turns off 2008 at latest • Beginning of transfer of responsibility for LINAC to BES • BES commits to support LINAC in LCLS era • KIPAC vision developed with focus on dark energy/dark matter • JDEM & LSST focus of R&D effort SLAC Scenarios

  22. Major Budget Drivers Going Forward • BES commitment to support the linac potentially frees $96M for HEP to redirect to new initiatives • Early transfer of responsibility from HEP to BES is helpful to HEP since can take advantage of these resources in advance of the B-factory turn off • We will compete within the HEP for those resources to support and grow ILC R&D at SLAC • An additional ~$20M (people and M&S) is available with the ramp down of BaBar ($37M ramps to $15.5 in FY13) • Since much of this is in people, we have tried to craft a program that uses those talents for smaller initiatives that provide science to the community in the ‘gap’ between B-factory turn off and ILC turn on SLAC Scenarios

  23. Elements of Proposed Mid-Term Particle and Astro-Particle Program • Non-Accelerator Based • Neutrinoless double beta decay • Our technical approach: EXO • Ground based dark energy telescope • Our technical approach: LSST • Space based dark energy probe • Our technical approach: Join SNAP Collab. • Accelerator Based • ILC/ILC detector • Details from Raubenheimer/Jaros • Accelerator Research  SABER • Continued broad program • New accelerator based initiative** • Revisit recommendations of scenarios study SLAC Scenarios

  24. Program Scenarios • Built ‘bottom up’ scenarios with program growth based on planned technological development • Included ramp down of BaBar effort • Included hoped for ramp up of ILC effort • Included distribution of technical resources, physicists and M&S • These are ‘scenarios’ not ‘plans’ SLAC Scenarios

  25. FLAT FLAT Scenarios 1: 5% Growth SLAC Scenarios

  26. 6%/year SLAC Scenarios

  27. Programmatic Priorities • For the near term: • We must focus on B-factory performance and delivery of science to our largest user community • For the mid term: • We must continue in our leadership role for the ILC • Highest priority new facility for the world community • We must complete GLAST construction and develop the ISOC • Challenges here due to marriage of 2 cultures • We must work to provide additional opportunities for science to the HEP user community in ~2012 • e.g. LSST, EXO, JDEM, .... • For the long term: • The R&D in accelerator science is our hope for the future of the field • To make the next accelerator *after* the ILC technically feasible and affordable SLAC Scenarios