1 / 31

INTRODUCTION TO TRENCHLESS TECHNOLOGY

INTRODUCTION TO TRENCHLESS TECHNOLOGY. Traditional Methods. First suited for “gre enfield” Low tech – little change over past 50 yrs. Level of planning & implementation basic “ Non-greenfield” – surface disruptions, underground utilities. Trenchless Technologies.

prentice
Download Presentation

INTRODUCTION TO TRENCHLESS TECHNOLOGY

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. INTRODUCTION TO TRENCHLESS TECHNOLOGY

  2. Traditional Methods • First suited for “gre enfield” • Low tech – little change over past 50 yrs. • Level of planning & implementation basic • “Non-greenfield” – surface disruptions, underground utilities

  3. Trenchless Technologies • Thrust Boring & Pipe Jacking (pre-1900’s) • Auger Boring (1940) • Impact Moling (1962) • Directional Drilling (1971) • Impact Ramming (1980) • Pipe Bursting (1980’s)

  4. Definition ofTrenchless Technologies “A family of methods, materials, and equipment capable of being used for the installation of new or replacement or rehabilitation of existing underground infrastructure with minimal disruption to surface traffic, business, and other activities.”

  5. New Construction Techniques H.D.D. Pipe Bursting Micro tunneling Pipe Jacking Auger Boring

  6. Horizontal Directional Drilling • Lengths of 15 - 1800 m • Diameters of 25 - 1200 mm • Applications: • utility conduits • Pipelines • gravity sewers • force mains • horizontal remediation wells • geotechnical investigations

  7. HDD Process

  8. HDD Process

  9. Pipe Bursting • Lengths of 100 - 900 m • Diameters of 75 - 1060 mm • Applications: • replacement of force mains • replacement of gravity sewers Static Head Pneumatic Head Hydraulic Head

  10. Pipe Bursting Process(Static)

  11. Pipe Bursting Process(StaticCont.)

  12. Pipe Bursting Process(Pneumatic)

  13. Microtunneling • Lengths of 25 - 225 m • Diameters of 250 - 3050 mm • Applications: • gravity sewer installations

  14. Microtunneling Process

  15. Pipe Jacking • Lengths of up to 490 m have been achieved • Diameters of 1060 - 3050 mm • Applications: • large diameter gravity sewers and force mains

  16. Pipe Jacking Process

  17. Auger Boring • Lengths of 12 - 150 m • Diameters of 200 - 1500 mm • Applications: • relatively short crossings of pipes and conduits

  18. TWO CASE HISTORIES (一)Pipe Bursting (二)Horizontal Directional Drilling

  19. Alternatives • Parallel the existing gravity trunk sewer with a new gravity trunk sewer • Construct a series of 5 new pumping stations and pump to adjacent sewerage area

  20. Parallel Trunk Sewer • Advantages • Maintains gravity flow • Disadvantages • Construction in silty sand to clayey material 3 to 6 metres deep with high groundwater in close proximity to Millstone River, a highly sensitive Coho salmon habitat stream. • Additional right-of-way would be required • Cost Estimated at $5.1 million

  21. Pumped Option • Advantages • Minimizes environmental impacts as pump stations and forcemains for the most part would be constructed in existing right-of-ways. • Disadvantages • Added undesirable long term operational costs to the City of Nanaimo • Cost Estimated at $5.2 million

  22. Pipe Bursting Researched as a Possible Alternative • Advantages • Less environmental impact as excavation is minimized • Gravity flow maintained • No additional right-of-ways required • No long term operational and maintenance costs associated with pump stations • More cost effective than alternatives • Disadvantages • Upsize required at the upper limit of PB technology in North America; however, there had been limited success • Lengths 100m to 175m • Limited availability of contractors in North America with capability to perform upsize of this nature

  23. Demonstration Section • Ability to burst project lengths (100m to 175m) • Ability to burst pipe couplings • Ability to burst concrete encasement • Although some difficulties encountered, remaining project was subsequently awarded

  24. 650mm (26”) 750mm (30”) 350mm (14”)

More Related