1 / 34

Kevin A. Sponsler

Kevin A. Sponsler. Project: 250 West Street, Columbus, Ohio. Presentation Outline. Building Overview Typical Floor System Analysis Lateral System Analysis Cost and Schedule (Current vs. Redesign) Office Space Lighting System Design. Project Team. Developer: Nationwide Reality Investors

Download Presentation

Kevin A. Sponsler

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Kevin A. Sponsler Project: 250 West Street, Columbus, Ohio

  2. Presentation Outline • Building Overview • Typical Floor System Analysis • Lateral System Analysis • Cost and Schedule (Current vs. Redesign) • Office Space Lighting System Design

  3. Project Team • Developer: Nationwide Reality Investors • Architect: Acock Associates Architects • Structural: Jezerinac Geers & Associates • Civil: Evans, Mechwart, Hambleton & Tilton • MEP: Prater Engineering Associates • Landscape: Myers-Schmalenberger/MSI • General Contractor: Messer Construction

  4. Building Use • 7-Story Building With Basement • Approximately 200’ x 100’ • 143,000 Square Feet • Multi-Use Building • Parking • Storage • Retail Space • Office Space

  5. Site Location

  6. Architectural Aspects • Brick Columns With Limestone Accents • Large Glass Panels • Metal Panels • 7th Story Balcony/Terrace

  7. Structural System • ASD Designed • Floor System • Composite Beams/Deck • Lateral System • Braced Frames • Foundation • Concrete Spread Footings

  8. Mechanical Systems • Variable Air Volume System • 4 Air Handling Units / Cooling Tower • VAV Boxes on Each Floor • Restrooms Fed by Constant Air with Exhaust • CO Sensors, Exhaust System in Parking Area

  9. Lighting Systems • Lobby • Low Voltage Recessed Cans • Wall Sconces • Garage • Metal Halide • Exterior • Metal Halide Cylinders on Columns • Remaining Lighting Not In Initial Contract

  10. Electrical Systems • Shared With Adjacent Building • 277/480 Volt, 3 Phase System • Each Floor Supplied with 277/480 V, 3 Phase • Powers Lighting/Other Equipment • Stepped Down at Each Floor to 120/208 Volt • Powers Receptacles

  11. Current Floor System

  12. Floor System Options • Composite Beams/Deck Framed N-S Direction • Composite Beams/Deck Framed E-W Direction (Current System) • Non-Composite System Framed E-W Direction

  13. Preliminary System Comparisons • Preliminary Design in RAM • Results

  14. Building Corner Framing

  15. Corner Connection Options Field Welded Flanges Moment End Plate Flange Plates Beam Cantilevered Over Column

  16. Corner Framing Comparison • Costs ($)

  17. Final Floor Design

  18. Floor System Comparison

  19. Floor System Conclusion • New System vs. Current System (1 Floor) • 9.0 Less Tons of Steel • 2,419 More Shear Studs • Costs $8,800 Less • Depth of System Reduced 3”

  20. Current Lateral System • 4 Braced Frames • Located in Central Core of Building • 2 North-South Direction • 2 East-West Direction • Combination of: • Diagonal Braces • Inverted V-Type Braces

  21. Earthquake Loads (R=3 vs. R=5) • Ordinary Concentrically Braced Frame • R=5 • Brace Strength = .8ФcPn • Inverted V-Type Bracing Strength = 1.5 x Required • Slenderness Restrictions • Connection Restrictions • System Not Specifically Designed for Seismic • R=3 • No Other Restrictions

  22. Story Forces

  23. Difference in Brace Sizes • Frame on Line D From 4.4-5.1

  24. Lateral Load Conclusion • Members • Extra Restrictions on Design Using R=5 • Some Member Sizes Reduced Using R=5 • 2 Tons Less Steel • Costs • $ 2,700 less with R=5 • Little Effect on Other Systems

  25. Current Design Cost & Schedule

  26. New Design Cost & Schedule

  27. Cost Conclusion • Redesign Saves Over $50,000 • Seismic Design Criteria Has Little Effect on Structural Costs (This Building)

  28. Lighting Criteria • First Floor Open Plan Office • Tasks • Reading Copied Tasks – Ditto Copies • Handwritten Tasks With #2 Pencil • Keyboard Reading • Target Illumination • 75 fc

  29. Fixture Selection • Recessed Parabolic • 2’ x 4’ Fixture • 4” Louver • Manufacturer: Lumax Industries Inc. • 4PG33224-CO4L18 • Lamps: Sylvania • FO32/835XPS/ECO • Ballast: Sylvania • QTP 3x32T8/277 ISN-A

  30. Office Layout / Reflectance

  31. Lighting Design

  32. Lighting Design

  33. Conclusion • Floor System • Maintained Strength • Reduced Cost - $8,800/floor • Reduced Depth • Lateral System • Maintained Strength • Reduced Material Costs • Overall – Reduced Cost by $50,000

  34. Questions

More Related