1 / 5

Pacific Gas & Electric Company

Pacific Gas & Electric Company. MTS: Evolution of the Electric Distribution System Manho Yeung, Senior Director, System Planning and Reliability PG&E October 15, 2014. PG&E Distribution System. Service Territory 70,000 square miles with diverse topography

Download Presentation

Pacific Gas & Electric Company

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Pacific Gas & Electric Company MTS: Evolution of the Electric Distribution System Manho Yeung, Senior Director, System Planning and Reliability PG&E October 15, 2014

  2. PG&E Distribution System • Service Territory • 70,000 square miles with diverse topography • 5.5 million electric customers • 2013 peak demand about 21,000 MW • Over 50% of electric supply from non-greenhouse gas emitting facilities Distribution Grid • 3200 distribution lines • 142,000 miles of distribution lines • 1.1 million distribution line transformers • 150,000 fuses • 14,500 voltage devices • 6,900 line reclosers

  3. Integrating DER into the Distribution Grid • Distributed generation is growing exponentiallyDG Adoption • Total installed DG capacity = 1,647 MW • Total installed DG customers = 133,000 • System penetration of DG Capacity = 8% of PG&E system peak demand • 8% of distribution feeders have > 15% penetration* • 3% of distribution feeders have >30% penetration • 1% of distribution feeders have 100% penetration Roof Top Solar • Processing cycle time is 4 days from application complete to Permission to Operate (PTO) • Issued 4,000 PTO notices in August 2014 with a projected 40,000 total for 2014 • No significant distribution upgrades required to date * Penetration defined as installed generation divided by peak demand on feeder

  4. Grid of Things to Integrate DER • The grid, with its many devices, serves as a platform to enable and facilitate the integration of DERs • Protection devices to ensure safety • Devices in RED such as breakers, reclosers, and fuses coordinate with DER protection schemes • Voltage regulation to ensure service quality • Devices in GREENare voltage devices that coordinate with DER load flow • Most PGE feeders have voltage regulated by a substation Load Tap Changer and many have multiple capacitors and tap changing regulators • Conductors and transformers to transmit power • A portion of the feeder is considered “main line” where conductors are large • Tap lines are used to connect customers and further distribute electricity • Line transformers are used to step power down to secondary voltage to serve multi customers • Most of the lines are economically sized for the load that they are serving Line transformer SUB Tap line F fuse F F R F capacitor regulator booster Main line recloser breaker

  5. Need an Intelligent Gridto Integrate DERs • Programs and initiatives that make the distribution grid more intelligent, robust, reliable and affordable for our customers: • Smart Meters • SCADA (supervisory control and data acquisition) • Sensors and monitors to further improve system operations • Volt/VAR optimization to automate voltage regulation and save energy • Smart Inverters • FLISR (fault location isolation and service restoration) feeder automation • Standardizing such as larger conductor and infrastructure replacement for two way flows • Identify optimal locations and target DER (DR, EE, DG, storage) to maximize customer benefits

More Related