SunGuide TM Software Development Project Test Readiness Review (TRR) Meeting November 27, 2007

SunGuide TM Software Development Project Test Readiness Review (TRR) Meeting November 27, 2007. Agenda. Introductions. Agenda. Logistics. District 4 staff will discuss: Test area Resources available. Agenda. Current Project Status: From a Development Perspective. Solid: 511 VSL CE

Download Presentation

SunGuide TM Software Development Project Test Readiness Review (TRR) Meeting November 27, 2007

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. SunGuideTM Software Development ProjectTest Readiness Review (TRR) MeetingNovember 27, 2007

  2. Agenda SunGuide TRR Meeting

  3. Introductions SunGuide TRR Meeting

  4. Agenda SunGuide TRR Meeting

  5. Logistics • District 4 staff will discuss: • Test area • Resources available SunGuide TRR Meeting

  6. Agenda SunGuide TRR Meeting

  7. Current Project Status:From a Development Perspective • Solid: • 511 • VSL • CE • AD CCTV Driver • EV • Web Server • EM • RS • AVL/RR • IDS • ODS • RPG • What is not ready: • Some Responder Audit screens (2 of 7 are not complete) SunGuide TRR Meeting

  8. Responder Audit RequirementsSome will not be tested this week SunGuide TRR Meeting

  9. Responder Audit RequirementsSome will not be tested this week - continued SunGuide TRR Meeting

  10. Forward Looking Schedule • IV&V – TERL (FDOT/PBS&J led activity): • Dry Run: Nov 26 – Nov 30 • Actual Test: Dec 3 – Dec 7 • Installs: • Nov 26: TERL • Nov 12-26: D4 • Dec 3-7 : D5 • Dec 3-7 : D6 • Dec 10-14: D2 (may start early) • Dec 10-14 : D7 (may start early) SunGuide TRR Meeting

  11. Agenda SunGuide TRR Meeting

  12. Purpose of TRR / FAT • Purpose: • Review preparations for testing • Walk through the test procedures at a very high level and determine if anyone has any comments • Ground Rules: • Testing will not depart from the written procedures • Any requested “ad hoc” testing will occur after the formal testing process • Re-writing of requirements / scope additions will be captured for future consideration • Approvals: • FDOT/SwRI will witness each test case (on “Master SICP”) • At the conclusion, FDOT will sign SICP cover page to acknowledge all tests were executed as written/noted in the “Master SICP” SunGuide TRR Meeting

  13. Hardware Configuration • District 4 staff to describe hardware environment SunGuide TRR Meeting

  14. IC-1: Configuration Editor (CE) IC-2: Variable Speed Limit (VSL) IC-3: American Dynamics Closed Circuit Television (AD CCTV) Driver IC-4: 511 (511) IC-5: Web Server (WS) IC-6: Automatic Vehicle Location (AVL)/Road Ranger (RR) IC-7: Incident Detection Subsystem (IDS) IC-8: Event Management (EM) (includes Responder Audit) IC-9: Response Plan Generation (RPG) IC-10: Reporting Subsystem (RS) IC-11: Event Viewer (EV) IC-12: Operational Data Store (ODS) IC-13: General Subsystem Updates (GEN) Release 3.0 Integration Cases SunGuide TRR Meeting

  15. FAT 3 Limitations • Two of the Responder Audit screens have not been completed (5 are available for testing) • Comment: D5 has an install (and using operationally) the following R3.0 components: • 511 • AD CCTV Driver • VSL • Web Server • Release 3.0 core components (C2C, GUI, MAS, Data Bus, TSS) SunGuide TRR Meeting

  16. Test Case Example SunGuide TRR Meeting

  17. Questions About Test Cases? SunGuide TRR Meeting

  18. Agenda SunGuide TRR Meeting

  19. Open Discussion SunGuide TRR Meeting