PROGRESS ON NGN IMPLEMENTATION -EXAMPLES

PROGRESS ON NGN IMPLEMENTATION -EXAMPLES. Prof. dr Nata š a Gospi ć , University Belgrade. Regional Workshop on Assistance to the Arab Region for the implementation of Next Generation Networks (NGN) Cairo (Egypt), 15-16 December 2009. THE AIM OF PRESENTATION.

raja-mcgee
Download Presentation

PROGRESS ON NGN IMPLEMENTATION -EXAMPLES

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PROGRESS ON NGN IMPLEMENTATION -EXAMPLES Prof. dr Nataša Gospić, University Belgrade Regional Workshop on Assistance to the Arab Region for the implementation of Next Generation Networks (NGN) Cairo (Egypt), 15-16 December 2009 ITU-D Regional Workshop, Cairo

  2. THE AIM OF PRESENTATION The presentation provides examples of progress in deploying the NGNs technologies and taking advantage of the cost savings and service opportunities in order to assist developing counties to choose their own way ITU-D Regional Workshop, Cairo

  3. Example of NGN progress ITU-D Regional Workshop, Cairo

  4. BRITISH TELECOM • “Delivering the future - BT’s 21st Century Network” • Software driven network with new, simpler portfolio of NGN services • Platform for innovation to put flexibility and choice in the hands of customers • Being deployed in UK • BT serves markets in 172 countries: maximum consistency globally ITU-D Regional Workshop, Cairo

  5. BT 21 CN • BT 21 CN • Advanced network based on intelligent systems using key technologies: • IP is key as common transport protocol for all types of communication and applications • SIP allows service provider to control the communications activity to meet a customer’s requirements • MPLS enables the efficient designation and routing of BB IP traffic flows • IP Multi-media Sub-system (IMS) to support innovative services • Also: SDH, Virtual LAN, WDM • “With the migration of its network to NGN (21 Century Network), BT expects savings in operating expenses of £1bn (about 1.5bn €) starting 2008/09. The expected investment amounts to £10bn (about 15bn €)“(KIRSCH, HIRSCHHAUSEN, 2008). ITU-D Regional Workshop, Cairo

  6. France Telecom Evolutionary Strategy Source: France Telecom ITU-D Regional Workshop, Cairo

  7. KPN, Netherlands • IMS is central to plans: once in place, will deploy fixed and mobile IP-based services, starting with simple voice services and moving to VoIP-based IP Centrex, wireless virtual PBX and messaging services • Issues: regulatory confusion • How are VoIP calls classified and charged for? Is it voice, or is it data? • Net neutrality and IP interconnect: who gets paid for what when an incumbent shares its network with 3rd party service providers? ITU-D Regional Workshop, Cairo

  8. KPN • KPN estimated that the network would require an additional €1.5 billion in capex. KPN focused on building an all-IP backbone first and then an all-IP access network on top of this. The backbone is now largely completed and the access network underway. KPN has revised its capex spend for the transformation to €0.9 billion. • “expects a reduction in operating costs of €850 million up to 2009 while the total capital expenses for the migration are estimated to be €0.9 billion. The extension of fiber to the street cabinets renders the MDFs obsolete. About 200 of the 1,391 MDF locations will remain in operation as interconnection points to the backbone (HENDRIKS, 2007, OPTA, 2006b). KPN expects an additional revenue of €1 billion from sales of the MDF real estate “ (KIRSCH, HIRSCHHAUSEN, 2008). ITU-D Regional Workshop, Cairo

  9. Approach to IMS implementation TelecomItalia KPN Orange 2009-13 Swisscom BT Telefónica 2007-10 Move to a single converged service control 2006-09 Add innovative services pushing multimedia enablement 2005-07 Expand reach of IMS breadth deploying BB VoIP Learn through niche applications Source: Operators sites ITU-D Regional Workshop, Cairo

  10. Shenzhen Telecom • Shenzhen NGN commercial pilot network represents the largest achievement in bringing about the evolution of PSTN from its current state, to that of NGN. In this network, the softswitch acts as the control center, the SHLR acts as the data center, and the ENIP acts as the unified service platform. The overall capacity of the entire network reaches up to 600,000 lines/300,000 trunks, with 150,000 actual subscribers accessed through AGs. Some of the reasons to be proud would include the following:  • It greatly improves network performance.  • At present, it gives birth to the largest NGN end office (33,000 lines).  • It breaks Shenzhen Telecom’s current record of PSTN end office cutover efficiency. Two end offices (42,000 lines in total) were cut over with high QoS in two consecutive days. From equipment installation to operation after cutover, it takes less than 20 days.  • It boasts the largest commercial IP Centrex group in the world. Only, RBT, UC, and Real-Time multimedia services exhibit similar vitality.  • As an intelligence platform, it provides new intelligent phone call services and other value-added services for its three million AND subscribers in the network. • THE PROJECT STARTED IN 2002 by China Telecom and finished in 2005. (Huawei Service, Multimedia library, Issue 20, 2005). ITU-D Regional Workshop, Cairo

  11. NGN DEPLOYMENT (Shenzhen Telecom) On September 18, 2004 the first NGN end office was established in Fuyong. Some 15,000 subscribers from the original TDM switch were transferred to the NGN network in a matter of minutes. Although the cutover lasted less than 10 minutes, it was a historical moment in the development of the China telecommunications network, because it marked the first time that NGN was able to replace the TDM end offices in the PSTN Three more end offices (the Boling office - 16,400 lines, Nanyou office - 26,000 lines, and Huangmugang office - 33,000 lines) were cutover within half a year. The cutover of these four offices were quick and orderly, and perhaps are best exemplified by the idea -- "from suburb to downtown"and "from small to large". By April 2005, Shenzhen Telecom successfully established a commercial NGN that accommodates more than 150,000 subscribers ITU-D Regional Workshop, Cairo

  12. Results (Shenzhen Telecom) While rebuilding the end office, the idea of NGN to separate call control from media bearer was brought into actual play. For the first time, high-capacity AGs were put into the original TDM switch room. As a result, subscribers under the original TDM switch were successfully transferred to the AGs within a matter of minutes. Furthermore, the AGs inherited all the access modes of the traditional TDM network such as; ordinary subscriber line, long-distance subscriber line, polarity reversal subscriber line, ISDN subscriber line, analog PBX trunk, digital PBX trunk, and V5 trunk. Also, the end users were shielded so that they were not aware of any changes in the core network. As for operation and maintenance, the distributed client mode was adopted in order to retain the original maintenance habit. ITU-D Regional Workshop, Cairo

  13. EFFECTS (Shenzhen Telecom) • Schenzhen Telecom • “Improved network operation quality: Operation records from the four NGN end offices of Shenzhen Telecom are convincing proof of an improved network operation quality. For instance, the 33,000-line Huangmugang office (the NGN end office with the largest capacity) serves as a good example. The operation indices from the NGN end office are much better than those of the original office, and the call completion rate showed an increase of 12%. Even with an increase in traffic, the softswitch system continued to run stably and the indices were much improved.  • Lower maintenance cost: After the original end office was converted into an NGN end office, indices like integrity, occupied space, and power consumption of the NGN equipment proved to be superior to those of the original TDM switch. After rebuilding, the occupied space was reduced by 40%, and power consumption by 63%. Hence, in a large-scale NGN, the maintenance cost will obviously be much lower. With its innate advantages in services like, IP Centrex and video services, NGN will quickly become the first choice in the rebuilding of the TDM network.”  (Huawei Service, Multimedia library, Issue 20, 2005). ITU-D Regional Workshop, Cairo

  14. CHINA NETCOM • China Netcom's Beijing Branch (Beijing Netcom) - April 2007 • First commercial IMS network in China • Includes IP-Centrex solution • IMS multimedia telephony system provides value-added services with the main focus on IP-Centrex targeting enterprise customers ITU-D Regional Workshop, Cairo

  15. Beijing Netcom: IP Centrex • Beijing Netcom: • To provide telecom-quality cost-efficient IP multimedia services addressing the needs of high-end enterprise users in Beijing area now and in the future. • Supports introduction of new multimedia services (voice, data,audio, video) to enhance user experience in Beijing area,including visitors and participants in the 2008 Olympic Games ITU-D Regional Workshop, Cairo

  16. KOREA Korea can serve as a good example for developing countries in whole or in part in this arena as it is in the midst of migrating to its own next generation network referred to as BcN or Broadband Convergence Network. The key drivers of deploying NGN ITU-D Regional Workshop, Cairo

  17. KOREA DEVELOPMENT (P:\STG\4StudyPeriod\SG2\200\2009\0277E.doc 09/11/2009; 26.08.2009 Source: National Information Society Agency (NIA) ITU-D Regional Workshop, Cairo

  18. KOREA ROADMAP A public-private-partnership (PPP) model has been activated in the implementation of the BcN. This basically means the private sector builds and commercializes networks and services, whereas the government arranges laws, polices and the necessary standardization conditions for new services. Source: National Information Society Agency (NIA) • The BcN Roadmap shows the different phases in the different networks that incorporate the whole BcN. • From 2004 and 2005, four consortiums were formed (made up of major telecom companies and local cable companies who all had a stake in nurturing the market) and first set up pilot projects/test beds in order to test potential applications and business models of convergence services including video phones, IPTV, VoIP, wireless sensor networking, etc. ITU-D Regional Workshop, Cairo

  19. SPAIN • Telefónica SA, Spain • “Mobile Attendant” service provides personalised, reliable, easy-to-use advanced communications experience across wireless and wireline networks • Integrates voice, video, text and data into one seamless communications environment, part of Telefónica's vision linking fixed and mobile networks together to deliver a converged communications experience ITU-D Regional Workshop, Cairo

  20. Telefónica SA, Spain • PC software manages calls running on GSM or 3G phones via a simple graphical interface to handle, e.g., simultaneous calls, transfers, multi-party conferencing • Can simultaneously run multimedia sessions from PC including presence and reachability messaging updates • Future: add a Personal Assistant with capabilities to enhance productivity for field-based and highly mobile personnel ITU-D Regional Workshop, Cairo

  21. Batelco - Bahrain • 176,000 lines migrated to NGN • Anticipated would require >5 years to implement but went considerably faster • Migration didn’t disrupt normal service • Now customers can connect to Batelco BB internet same day vs. one week • NGN delivers on promise to bring affordable BB access to all households making Bahrain among the best connected in the world ITU-D Regional Workshop, Cairo

  22. Example: Small operator from developing country-Telekom Srpske, B&H- • New servicesare based on the NGN and IMS architecture. • Strategy • parallel existance of TDM and NGN network till full migration to NGN (Year 2012.) • 75.000 PSTN users are migrated to Softswitch using MSAN platform - preserving all PSTN services (the end of the 2008). • Solutions consisting of IMS Core elements and Softswitch • NGN Techno-Economic Aspects • Investment protection • Costs reduction (capital and operational) • Carrier grade reliability • Scalability • Improved product selection • Increase usage of the existing networkinfrastructure • Speed of innovation and introduction of services ITU-D Regional Workshop, Cairo

  23. Telekom Srpske First step towards NGN ITU-D Regional Workshop, Cairo

  24. Telecom Srpske: Next Steps in migration to NGN Full migration of PSTN users from TDM to NGN using MSAN and Softswitch platform (2012.) Offering new services: Video Call, Video Conference, Unified Messaging, Presence and Instant Messaging etc. Interconnection with the international VoIP networks FMC - Fixed Mobile Convergence ITU-D Regional Workshop, Cairo

  25. CONCLUSION Every country’s situation is different with their own distinct unique market and environmental factors Costs and financial support are vital and can not be ignored Public-private partnership Local initiatives Developing countries should be encourage to take a part in international effort to develop best migration path to NGN ITU-D Regional Workshop, Cairo

  26. THANK YOU FOR YOUR ATTENTION! Prof. dr Natasa Gospic University Belgrade Tel: +381 11 3091310 Email n.gospic@sf.bg.ac.yu 15-16 December 2009 Regional Workshop on NGN Cairo, Egypt