180 likes | 274 Views
W-band Module Production and Other Fermilab Contributions. Modest Fermilab involvement in QUIET-I Hardware Calibration Tools 3 trips to CIT/JPL to study modules Shifts in Chile Hosted a QUIET Collaboration Meeting at Fermilab in June 09 Access to QUIET-I Data.
E N D
W-band Module Production and Other Fermilab Contributions Modest Fermilab involvement in QUIET-I Hardware Calibration Tools 3 trips to CIT/JPL to study modules Shifts in Chile Hosted a QUIET Collaboration Meeting at Fermilab in June 09 Access to QUIET-I Data Proposed Significant Partnership in QUIET-II to the Fermilab PAC in November 2009 Pier Oddone, Fermilab Director DOE Field Work Proposal In Preparation
Module bias optimization using Grid Before receiver LN2 After KICP Lab in Chicago Wire grid
Commissioning Detector using Rotating Sparse Wire Grid Polarizer
The Science Team CMB Theory: S. Dodelson, A. Stebbins RF Technology: D. McGinnis Detector Fabrication: F. DeJongh, H. Nguyen The Technical and Engineering Team Tooling Fabrication: J. Korienek, C. Lindenmeyer, Mechanical Assembly and Cryogenics: D. Butler, B. Gonzales, T. Hawke, W. Newby, J. Wilson System Controls: S. Hansen, J. Montes, J. Zimmerman Electrical Engineering and Testing: D. Kubik Significant Experience Silicon Tracking Detectors for HEP Fermi-Glast Satellite Veto Shield Dark Energy Survey Camera
Our Proposed Involvement in QUIET Phase II Technical Challenges Assembly of ~1500 W-band Polarization Analyzer Modules ~ 2 year production run Collaborative effort with Caltech and JPL Precision Placement of 106 components Components as small as 200 m x 200 m Very delicate HEMT components Precision control of silver epoxy die bonding Over 200 wirebonds per module Harsh Cryogenic and Vacuum Environment
Meeting the Production Goals Utilize 4 Coordinate Measurement Machines to Perform Automated Assembly Upgrade Machines with powerful Labview and Vision System Software Strong interests from ATLAS and CMS in using automated assembly tools at Fermilab for the LHC silicon detector upgrades A natural synergy between QUIET and Fermilab/HEP Work to be performed at the Fermilab Sidet Facility
Differences between Phase I and Phase II Assembly and Testing Phase I Phase II Module Housing Machining at JPL Module Housing Machining by Vendor using new technique Die Bonding by NxGen New Die Bonding Technique developed at Fermilab Manual Conductor Bonding at JPL Automatic Conductor Bonding at Fermilab - Quality Assurance of Conductor Bonding Mechanical Strength - Quality Assurance of Epoxy Bonding Mechanical Strength Comprehensive Testing of Module Power Draw and RF response - at 20K and Room T Comprehensive Testing of Power Draw at Room T Comprehensive Testing of RF Response at Room T Comprehensive Thermal Cycling of Modules to 20K Sample Testing of Power Draw at 20K Sample Testing of RF Response at 20K Goal: Guarantee quality components and robust procedures in order to reduce need for comprehensive testing.
Micro Assembly Tools New Tools for Die Bonding Automated Wirebonding Machines at Sidet Facility Will perform R&D of bonding mechanical strength in vacuum and cryogenic environment: R&D to Guarantee High Assembly Yield Reduces Need for Extensive Cryogenic Production Testing.
Quality Assurance is Critical “Instron” Measurement of Die Bonding Adhesion of Epotek H20F Silver Epoxy Epoxy Lap Shear Strength Measurements and Thermal Cycling down to 28 Kelvin Expected breaking point Manufacturer’s data on cold-temp degradation does not exist. Epotek is interested in our thermal-cycling result !
Quality Assurance is Critical Al-Au Wirebond Strength Measurements and Thermal Cycling to 28 Kelvin
Module Assembly and Receiver Integration Schedule 2012 2010 2011 2013 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Tooling Development Module Housing and Non-InP Parts Fabrication Fabrication and Delivery of InP Parts from CIT/JPL Assembly and Testing of 3rd 500 Modules Assembly and Testing of 2nd 500 Modules Assembly and Testing of 1st 500 Modules Integration of 1st Receiver and deployment Integration of 2nd Receiver and deployment Responsibility CIT/JPL Integration of 3rd Receiver and deployment Fermilab Chicago-Fermilab KEK/Princeton
Major Subsystem Costs W-Band Module Production and Testing: Caltech, JPL, Fermilab Component Delivery Date NSF Cost DOE Cost DOE Contingency. Module Housing/Parts 12-2010 466K - - Tooling Materials 12-2010 - 138K 28K Tooling Fabrication and Controls Programming 12-2010 - 104K 31K Production Labor 12-2010 to 3-2013 - 238K 59K Testing Labor “ - 594K 148K Total 466K 1074K 266K W-band Receiver Integration: Chicago, Fermilab Component Delivery Date NSF Cost DOE Cost DOE Contingency Materials 12-2010 to 4-2012 - 51K 10K Technician Labor “ - 80K 20K Engineering Labor “ - 94K 24K Total - 225K 54K
Summary Project Construction Tasks Delivery of 1500 W-band modules in ~2 year production run Integration and commissioning of 1 Receiver at Fermilab Calibration tools and window engineering analysis Request to Fermilab/DOE: Project Cost = $ 1.75M (includes contingency) Operations Cost = $ 224K Technical and Engineering Labor (no Scientist Labor) Production tooling material costs Contribution to Chile site operations cost Funds for Travel to Chile for Shifts and Installation All overheads have been included