OpenFlow Campus Trials at Clemson (OFCLEM) Spiral 2 Year-end Project Review. Clemson University PI: Kuang-Ching (KC) Wang, Associate Professor Co-PI: Jim Pepin, CTO Staff: Dan Schmiedt, Wayne Ficklin Students: Glenn Evans, Sajindra Pradhananga, Aaron Rosen, Bob Strecansky Date: 08/25/2010.
E N D
OpenFlow Campus Trials at Clemson (OFCLEM)Spiral 2 Year-end Project Review Clemson University PI: Kuang-Ching (KC) Wang, Associate Professor Co-PI: Jim Pepin, CTO Staff: Dan Schmiedt, Wayne FicklinStudents: Glenn Evans, Sajindra Pradhananga, Aaron Rosen, Bob Strecansky Date: 08/25/2010
Project Summary • Scope This project will deploy an OpenFlow testbed on the Clemson University campus and connect with wireless mesh access points and mobile terminals. This trial will conduct OpenFlow experimentation focused on OpenFlow enabled network operation solutions as a precursor to deployment into Clemson research and production networks. 8/25/2010
Milestone & QSR Status 8/25/2010
Accomplishments 1: Advancing GENI Spiral 2 Goals • GENI Spiral 2 goals focus on early experimentation, instrumentation & measurement, security, and meso-scale build-out. • OFCLEM has contributed to the following in Spiral 2: • Meso-scale build out • OF switches deployed at three buildings • OF vlans mapped across entire campus • L2 connectivity with BBN, GT, and Stanford (Wisconsin link next) • OF wireless APs deployed on campus street lights (pilot) • Soon to connect parking lot police video mesh network • Early experiments • Initiated three EAGER experiments on security, P2P, and network coding • Experiments focus on measurement and stress tests on GENI slices • Support three GEC9 plenary demo 8/25/2010
Accomplishments 2:Other Project Accomplishments • CIO, CTO and IT staff actively promote support for campus OpenFlow operation • Our NOC team voiced interest in learning more about OpenFlow • Further engagement with NOC will be planned for Spiral 3 • Assigned GENI experiment projects in graduate QoS network course • Undergraduate projects will be created in Spiral 3 8/25/2010
Issues • None noted. 8/25/2010
Plans • What are you plans for the remainder of Spiral 2? • Continue integration with Stanford and BBN (AM and Opt-In) • Continue validation of 1.0 network operation • Complete pilot wireless APs deployment and validation • The GPO is starting to formulate goals for Spiral 3. What are your thoughts regarding potential Spiral 3 work? • Support GENI Experimenters • Engage NOC IT staff on OpenFlow operation and management • Continue development on extensions for OF wireless mesh networks 8/25/2010