1 / 34

Ch 10

Job Design & Work Measurement. Ch 10. Heizer and Render Principles of Operations Management, 8e PowerPoint slides by Jeff Heyl. Rusty Wallace’s NASCAR Racing Team. NASCAR racing became very popular in the 1990s with huge sponsorship and prize money

rashida
Download Presentation

Ch 10

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Job Design & Work Measurement Ch 10 Heizerand Render Principles of Operations Management, 8e PowerPoint slides by Jeff Heyl

  2. Rusty Wallace’s NASCAR Racing Team • NASCAR racing became very popular in the 1990s with huge sponsorship and prize money • High performance pit crews are a key element of a successful race team • Pit crew members can earn $100,000 per year – for changing tires! © 2011 Pearson Education, Inc. publishing as Prentice Hall

  3. Rusty Wallace’s NASCAR Racing Team • Each position has very specific work standards • Pit crews are highly organized and go though rigorous physical training • Pit stops are videotaped to look for improvements © 2011 Pearson Education, Inc. publishing as Prentice Hall

  4. Human Resource Strategy The objective of a human resource strategy is to manage labor and design jobs so people are effectively and efficiently utilized People should be effectively utilized within the constraints of other operations management decisions People should have a reasonable quality of work life in an atmosphere of mutual commitment and trust

  5. Process strategy • Technology • Machinery and equipment used • Safety • Product strategy • Skills needed • Talents needed • Materials used • Safety Procedure What • Schedules • Time of day • Time of year (seasonal) • Stability of schedules • Individual differences • Strength and fatigue • Information processing and response HUMAN RESOURCE STRATEGY When Who • Location strategy • Climate • Temperature • Noise • Light • Air quality • Layout strategy • Fixed position • Process • Assembly line • Work cell • Product How Where Constraints on Human Resource Strategy Figure 10.1

  6. Labor Planning Employment Stability Policies • Follow demand exactly • Matches direct labor costs to production • Incurs costs in hiring and termination, unemployment insurance, and premium wages • Labor is treated as a variable cost • Hold employment constant • Maintains trained workforce • Minimizes hiring, termination, and unemployment costs • Employees may be underutilized during slack periods • Labor is treated as a fixed cost

  7. Work Schedules • Standard work schedule • Five eight-hour days • Flex-time • Allows employees, within limits, to determine their own schedules • Flexible work week • Fewer but longer days • Part-time • Fewer, possibly irregular, hours

  8. Job Classification and Work Rules • Specify who can do what • Specify when they can do it • Specify under what conditions they can do it • Often result of union contracts • Restricts flexibility in assignments and consequently efficiency of production

  9. Job Design • Specifying the tasks that constitute a job for an individual or a group • Job specialization • Job expansion • Psychological components • Self-directed teams • Motivation and incentive systems

  10. Labor Specialization • The division of labor into unique tasks • First suggested by Adam Smith in 1776 • Development of dexterity • Less loss of time • Development of specialized tools • Later Charles Babbage (1832) added another consideration • Wages exactly fit the required skill required

  11. Job Expansion • Adding more variety to jobs • Intended to reduce boredom associated with labor specialization • Job enlargement • Job rotation • Job enrichment • Employee empowerment

  12. Enriched job Planning (Participate in a cross-function quality improvement team) Enlarged job Task #3 (Lock printed circuit board into fixture for next operation) Present job (Manually insert and solder six resistors) Task #2 (Adhere labels to printed circuit board) Control (Test circuits after assembly) Job Enlargement Figure 10.2

  13. Psychological Components of Job Design • Human resource strategy requires consideration of the psychological components of job design • Hawthorne Studies • They studied light levels, but discovered productivity improvement was independent from lighting levels • Introduced psychology into the workplace • The workplace social system and distinct roles played by individuals may be more important than physical factors • Individual differences may be dominant in job expectation and contribution

  14. Core Job Characteristics Jobs should include the following characteristics Skill variety Job identity Job significance Autonomy Feedback

  15. Self-directed teams Empowerment Self-direction Enrichment Enlargement Specialization Job expansion Job Design Continuum Figure 10.3 © 2011 Pearson Education, Inc. publishing as Prentice Hall

  16. Self-Directed Teams • Group of empowered individuals working together to reach a common goal • May be organized for long-term or short-term objectives • Effective because • Provide employee empowerment • Ensure core job characteristics • Meet individual psychological needs

  17. Self-Directed Teams To maximize effectiveness, managers should • Ensure those who have legitimate contributions are on the team • Provide management support • Ensure the necessary training • Endorse clear objectives and goals • Financial and non-financial rewards • Supervisors must release control

  18. Benefits of Teams and Expanded Job Designs • Improved quality of work life • Improved job satisfaction • Increased motivation • Allows employees to accept more responsibility • Improved productivity and quality • Reduced turnover and absenteeism

  19. Limitations of Job Expansion Higher capital cost Individuals may prefer simple jobs Higher wages rates for greater skills Smaller labor pool Higher training costs

  20. Motivation and Incentive Systems • Bonuses - cash or stock options • Profit-sharing - profits for distribution to employees • Gain sharing - rewards for improvements • Incentive plans - typically based on production rates • Knowledge-based systems - reward for knowledge or skills

  21. 3rd Area of HR Strategy: Labor Standards • Effective manpower planning is dependent on a knowledge of the labor required • Labor standards are the amount of time required to perform a job or part of a job • Accurate labor standards help determine labor requirements, costs, and fair work • Started early in the 20th century • Important to both manufacturing and service organizations • Necessary for determining staffing requirements • Important to labor incentive systems

  22. Meaningful Standards Help Determine Labor content of items produced Staffing needs Cost and time estimates Crew size and work balance Expected production Basis of wage incentive plans Efficiency of employees

  23. Labor Standards May be set in four ways: Historical experience Time studies Predetermined time standards Work sampling

  24. Historical Experience • How the task was performed last time • Easy and inexpensive • Data available from production records or time cards • Data is not objective and may be inaccurate • Not recommended

  25. Time Studies • Involves timing a sample of a worker’s performance and using it to set a standard • Requires trained and experienced observers • Cannot be set before the work is performed • Define the task to be studied • Divide the task into precise elements • Decide how many times to measure the task • Time and record element times and rating of performance

  26. Sum of the times recorded to perform each element Number of observations Average observed time = Total normal time 1 - Allowance factor Standard time = Performance rating factor Average observed time Normal time = x Time Studies Compute average observed time Determine performance rating and normal time Add the normal times for each element to develop the total normal time for the task Compute the standard time

  27. Rest Allowances • Personal time allowance • 4% - 7% of total time for use of restroom, water fountain, etc. • Delay allowance • Based upon actual delays that occur • Fatigue allowance • Based on our knowledge of human energy expenditure

  28. 1. Constant allowance • (A) Personal allowance ……………... 5 • (B) Basic fatigue allowance ………… 4 • 2. Variable allowances: • (A) Standing allowance ……………… 2 • (B) Abnormal position • (i) Awkward (bending) ………… 2 • Very awkward (lying, stretching) …………………… 7 Rest Allowances Table 10.1

  29. Use of force or muscular energy in lifting, pulling, pushing Weight lifted (pounds) 20 …………………………………… 3 40……………………………………. 9 60……………………………………. 17 • Bad light: • Well below recommended…. 2 • Quite inadequate……………. 5 Rest Allowances Figure 10.1

  30. (E) Atmospheric conditions (heat and humidity) …………… 0-10 • Close attention: (i) Fine or exacting……………….. 2 (ii) Very fine or very exacting…… 5 • Noise level: (i) Intermittent—loud…………….. 2 (ii) Intermittent—very loud or high-pitched………………... 5 Rest Allowances Figure 10.1

  31. Mental strain: (i) Complex or wide span of attention.…………………….. 4 (ii) Very complex………………….. 8 • Tediousness: (i) Tedious…………..……………… 2 (ii) Very tedious.…………………… 5 Rest Allowances Figure 10.1 © 2011 Pearson Education, Inc. publishing as Prentice Hall

  32. Normal time = (Average observed time) x (Rating factor) = (4.0)(.85) = 3.4 minutes Normal time 1 - Allowance factor Standard time = = = 3.4 1 - .13 3.4 .87 = 3.9 minutes Time Study Example 1 Average observed time = 4.0 minutes Worker rating = 85% Allowance factor = 13%

  33. Cycle Observed (in minutes) Performance Job Element 1 2 3 4 5 Rating Compose and type letter 8 10 9 21* 11 120% Type envelope address 2 3 2 1 3 105% Stuff, stamp, seal, and 2 1 5* 2 1 110% sort envelopes Time Study Example 2 Allowance factor = 15% Delete unusual or nonrecurring observations (marked with *) Compute average times for each element Average time for A = (8 + 10 + 9 + 11)/4 = 9.5 minutes Average time for B = (2 + 3 + 2 + 1 + 3)/5 = 2.2 minutes Average time for C = (2 + 1 + 2 + 1)/4 = 1.5 minutes

  34. Standard time = = = 18.07 minutes Total normal time 1 - Allowance factor 15.36 1 - .15 Time Study Example 2 Compute the normal time for each element Normal time = (Average observed time) x (Rating) Normal time for A = (9.5)(1.2) = 11.4 minutes Normal time for B = (2.2)(1.05) = 2.31 minutes Normal time for C = (1.5)(1.10) = 1.65 minutes Add the normal times to find the total normal time Total normal time = 11.40 + 2.31 + 1.65 = 15.36 minutes Compute the standard time for the job

More Related