530 likes | 666 Views
Project Management for Public Health Professionals. February 2011 David Sabapathy , MD, MBA, PEng Department of Community Health Sciences 3 rd floor TRW building Faculty of Medicine University of Calgary Calgary, Alberta Canada T2N 4Z6 david.sabapathy@albertahealthservices.ca.
E N D
Project Managementfor Public Health Professionals • February 2011 • David Sabapathy, MD, MBA, PEng • Department of Community Health Sciences • 3rd floor TRW building • Faculty of Medicine • University of Calgary • Calgary, Alberta • Canada T2N 4Z6 • david.sabapathy@albertahealthservices.ca
Learning Objective • Acquire practical skills to develop a Project Management Plan to effectively and efficiently achieve a health objective Initiation Definition Planning Execution Close-Out
Course Map Idea Authority Project Charter Design Schedule Resource Plan Project Outcomes Evaluation Project Management Plan Initiation Definition Planning Execution Close-Out
Project Planning With the design complete, we know WHAT we’re doing. Now we need to decide HOW to do it Initiation Definition Planning Execution Close-Out
Specific Learning Objectives • Outline how to complete the following steps in the project life cycle • Project Planning • Use the project life cycle to address a health priority for a developing country • Project Planning • Develop a project schedule and Gantt chart • Understand the basics of developing a project budget • Develop a strategy to implement project management for a health priority in a developing country in a way that is culturally-suitable and enables uptake Initiation Definition Planning Execution Close-Out
Topics • Project Life Cycle: Stage 3 – Project Planning • Project scheduling • Gantt charts • Budgeting Initiation Definition Planning Execution Close-Out
Learning Method In-Class Case Study Activity Modules x 3 Project Management Plan Initiation Definition Planning Execution Close-Out
Scheduling Initiation Definition Planning Execution Close-Out
Scheduling Steps • Outcome of Project Definition stage Project Scope • Scheduling of Project Scope has 5 Steps • Task Sequencing - Put work packages in correct order • Work Package Estimation - Estimate time and resources • Schedule creation – Gantt chart • Task Constraints – Determine float and critical path • Resource Levelling – Re-assign and level resources Initiation Definition Planning Execution Close-Out
Step 1: Task Sequencing • All tasks obey sequence constraints • Example: Getting ready for work Initiation Definition Planning Execution Close-Out
Step 1: Task Sequencing • Define relationships between work packages • Do not be concerned with resource constraints • E.g. Even if there’s not enough FTEs to complete a work package early in the project, this should not affect the sequencing of this work package Initiation Definition Planning Execution Close-Out
Work Package Sequencing • Work Packages are the only tasks in the project that will be completed (not summary tasks). Only sequence Work Packages and do not let Resource Constraints affect sequencing. Initiation Definition Planning Execution Close-Out
Step 1: Task Sequencing Two ways to display task relationships Predecessor Table Network Diagram Initiation Definition Planning Execution Close-Out
Step 1: Task Sequencing • Concurrent tasks • 2, 3 and 5, 6 • Resource independence • Start and End milestones Start End 2 4 5 7 1 3 6 Initiation Definition Planning Execution Close-Out
MIP Case: Task Sequencing • Triple Constraint • Scope – defined by WBS • Time – 6 months • Resources • 46,000,000 TZS (50,000 USD) • 6 FTEs - 4 project team members and 8 clinic managers @ 0.5 FTE Initiation Definition Planning Execution Close-Out
MIP Case: Task Sequencing Level 0 Level 1 Level 2 Work Packages Level 3 Initiation Definition Planning Execution Close-Out
MIP Case: Task Sequencing Level 0 Measles Immunization Project - WBS 1.1 Project Management 1.1.1 Monitor progress 1.1.2 Communicate status 1.2 Strengthen Partnerships 1.2.1 Identify partners 1.2.2 Draft and sign agreement 1.3 Enhance Accessibility 1.3.1 Secure vaccine supply 1.3.1.1 Review agreements 1.3.1.2 Analyze deficiencies 1.3.1.3 Develop contracts 1.3.1.4 Sign contracts 1.3.2 Resolve cold-chain 1.3.2.1 Perform root-cause analysis 1.3.2.2 Improve process 1.3.2.3 Communicate process 1.3.2.4 Evaluate process 1.4 Provide Education 1.4.1 Survey population 1.4.1.1 Design survey 1.4.1.2 Conduct survey 1.4.2 Develop program 1.4.3 Deliver program 1.4.3.1 Recruit volunteers 1.4.3.2 Educate population 1.4.4 Evaluate program Level 1 Work Packages Level 2 Level 3 Initiation Definition Planning Execution Close-Out
MIP Case: Task Sequencing Initiation Definition Planning Execution Close-Out
MIP Case: Task Sequencing Level 0 Level 1 Level 2 Work Packages Level 3 Initiation Definition Planning Execution Close-Out
MIP Case: Task Sequencing WBS Predecessor Table Initiation Definition Planning Execution Close-Out
MIP Case: Task Sequencing Predecessor Table Network Diagram 1 6 Start End 8 3 2 4 5 7 Initiation Definition Planning Execution Close-Out
Step 2: Work Package Estimation • Recall the top-down process of Apportionment • Now time for more detailed bottom-up estimation • Each work package has 3 time and resource estimates: • Labour estimates • Equipment estimates • Material estimates Initiation Definition Planning Execution Close-Out
Step 2: Work Package Estimation • Labour estimates require 3 inputs: • Labour hours – time required for 1 FTE to complete • Staffing in FTEs* – # FTEs assigned to the work package • Wait time – necessary delay in completing work package • Equipment and material estimates important but not covered in this course • * FTE = Full-time equivalent. An FTE of 1.0 means that the person is equivalent to a full-time worker, while an FTE of 0.5 signals that the worker is only half-time. Initiation Definition Planning Execution Close-Out
Work Package Estimation • The estimated duration of a Work Package is the sum of the Active Time and Wait Time. • Active Time is an estimate of people’s time spent on the task. Wait Time is an estimate of the necessary delay to complete the task Initiation Definition Planning Execution Close-Out
MIP Case: Work Package Estimation PT = Project Team Member; CM = Clinic Manager, V = Volunteers Initiation Definition Planning Execution Close-Out
Step 3: Schedule Creation • Work package sequencing and durations complete • Can now create a Gantt chart • Graphical method for displaying a project schedule • WBS on vertical axis, timeline on horizontal axis Initiation Definition Planning Execution Close-Out
Gantt Chart Creation • Two elements are required to create a Gantt Chart: • Work Package Sequence • & • Work Package Duration Initiation Definition Planning Execution Close-Out
MIP Case: Schedule Creation Sequence Duration Gantt Chart Initiation Definition Planning Execution Close-Out
MIP Case: Schedule Creation Initiation Definition Planning Execution Close-Out
Step 4: Task Constraints • Every task has four dates • Early start – earliest a task can begin given the tasks preceding it • Early finish – earliest task can finish given the tasks preceding it • Late start – latest a task can start given the tasks preceding it • Late finish - latest a task can finish given the tasks preceding it • Two steps to defining dates • Early start/finish - Forward pass through network diagram • Late start/finish - Backward pass through network diagram Initiation Definition Planning Execution Close-Out
Step 4: Task Constraints • Float or “slack” • The difference between Early start/finish and Late start/finish is schedule flexibility! • Float = Early start – Late Start • Critical path = Path through all tasks with zero float • Tasks with zero float must be completed by their early finish date or the project will be delayed! Initiation Definition Planning Execution Close-Out
Critical Path • The Critical Path is the sequence of tasks that must be completed on schedule if the project is to be on schedule. Any delay in a task along the Critical Path will result in a project delay. • Attention must always be paid to the Critical Path. Initiation Definition Planning Execution Close-Out
Step 5: Resource Levelling Task duration estimates implied a certain resource allocation Examine schedule: Resources under or over-allocated at any time? Adjust schedule to have consistent, continuous use of fewest resources Initiation Definition Planning Execution Close-Out
Activity Module #3: Project Schedule Handout Activity Module #3: Project Schedule Discuss use of project management software Start activity module… Initiation Definition Planning Execution Close-Out
Resource Plan Initiation Definition Planning Execution Close-Out
Course Map Idea Authority Project Charter Design Schedule Resource Plan Project Outcomes Evaluation Project Management Plan Initiation Definition Planning Execution Close-Out
Resource Plans • Resource Plan • WHAT is required for each task (human resources, equipment, materials, finances) • WHEN its required • Useful communication tool for Project Stakeholders Initiation Definition Planning Execution Close-Out
Human Resources Human Resource plan already done during project scheduling! We determined WHAT people we need and WHEN we need them Now communicate in a Gantt chart format to stakeholders What People When Needed Initiation Definition Planning Execution Close-Out
Human Resource Plan • A Human Resource Plan is a useful communication tool that identifies when people are scheduled to work on a project task. Initiation Definition Planning Execution Close-Out
Project Budgeting • Two steps • Cost Estimation – What is the cost? • Cost Budgeting – When is the money required? • Manages project risk associated with finances Initiation Definition Planning Execution Close-Out
Cost Estimation • Iterative process • More accuracy with time • Accuracy costs money • Recall our first pass: • Apportionment Estimate Accuracy Project Life Cycle Timeline Initiation Definition Planning Execution Close-Out
Estimation • Project estimation (scope, time, resources) improves as the project life cycle unfolds. • Improved estimation requires additional cost. Initiation Definition Planning Execution Close-Out
Estimation Techniques • Analogous estimates (top-down estimates) • Our Apportionment process during the Project Definition stage • Less costly, less accurate • Needs historical reference point • Bottom-up estimates • Estimate work packages from WBS • More costly, requires expert input, more accurate • Parametric modeling • Project parameters in mathematical model (e.g. $5 per sqft * 2500 sqft) • Historical data accuracy, parameters quantifiable Initiation Definition Planning Execution Close-Out
Assumptions • All estimates involve assumptions • Document the basis for your cost estimate • Without documentation, a cost estimate is unexplainable Initiation Definition Planning Execution Close-Out
MIP Case: Cost Estimation • Bottom-up Estimation for each work package in the WBS • Check against apportionment Initiation Definition Planning Execution Close-Out
MIP Case: Cost Estimation Initiation Definition Planning Execution Close-Out
MIP Case: Cost Estimation Initiation Definition Planning Execution Close-Out
Cost Budgeting • Work package cost estimates spread over time • Enables timely recognition of cost deviations from plan • Two inputs • Work package cost estimates • Project schedule Initiation Definition Planning Execution Close-Out
MIP Case: Cost Budgeting Initiation Definition Planning Execution Close-Out