Akshay Prakash Yojana… Driven by Consumer Participation

Akshay Prakash Yojana… Driven by Consumer Participation. Akshay Prakash Yojana (APY). Driven by Consumer Participation. Voluntary Program for Load curtailment. Voluntary supply regulations. Improved Quality of Supply. Demand Side Measures. Social benefits. Collective Responsibility.

red
Download Presentation

Akshay Prakash Yojana… Driven by Consumer Participation

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Akshay Prakash Yojana… Driven by Consumer Participation

  2. Akshay Prakash Yojana (APY) Driven by Consumer Participation Voluntary Program for Load curtailment Voluntary supply regulations Improved Quality of Supply Demand Side Measures Social benefits Collective Responsibility System Stability

  3. The TriggerSimple Questions by children …. Long term benefits of sparing electricity for education against short term illegal uses Social awareness of electricity being a scarce and precious resource

  4. Akshay Prakash YojanaVoluntary Supply Regulations • Villagers not to use any 3 phase load during 1800 hrs to 0500 hrs. Only lighting load to be allowed • Restrict Load during 1800 hrs to 0500 hrs. to 20% of full load • Removal of illegal / inefficient heavy consumption devices like heaters, cooking heaters etc. • Adopt use of energy saving lighting, pumps and other devices; Use of capacitors

  5. Akshay Prakash Yojana Self Monitoring • Formation of surveillance committees for monitoring electricity use (Veej Dakshata Committee – VDC) • Removal of all unauthorized connections • Gram Sabhas pass resolution to carry out above activities

  6. Akshay Prakash YojanaConsumer Benefits BENEFITS Consumer Benefits Enhanced Quality of Supply Elimination of unplanned load shedding Reduction in transformer break-downs and improvement in voltage Reduction in consumer complaints Optimum utilisation of power for social benefits like education, cottage industry etc.

  7. Akshay Prakash YojanaMAHAVITARAN Benefits BENEFITS Organization Benefits Reduction in commercial losses Better load management Reduction in transformer repairs and maintenance cost System stability Resulting in improved commercial and operational performance

  8. … “We must help ourselves and opt for Akshay Prakash Yojana. I think this is the only alternative available with us” ...“I declare a reward of Rs. 10,000 to anyone finding people misusing power in my native place. However I will ensure that the guilty party pays a penalty of Rs. 1 lakh” Devidas Pawar Vice President Shetkari Sangathana Nashik District

  9. Case Study of Kalvan: Bej Village • Highly irregular supply for past 6 years • Feeders hand tripped every 10-15 mins • LT and HT fuse faults at frequent intervals • Highly overloaded transformers and transformer failures • Heavy misuse of power • 183 households but only 2 residential connections • Use of electricity for cooking and heating water • (Hotplate-2hp and water heater-5 hp)

  10. Case Study of Kalvan: Bej Village • Mass movement in village to reduce theft and conserve power-Initiated by Shri. Devidas Pawar • Patrols by villagers to undercover theft and misuse • Adoption of metered connections by all consumers • 23 villages in Kalvan adopted Akshay Prakash Yojana • Partial coverage of Kalvan Taluka • Uninterrupted Power for 23 Hours • Facilitating education, irrigation and quality of life • Maximum Load reduction from 285A to 90A for Bej & New Bej due to theft reduction • Present evening load of 20A under APY Scheme

  11. Load Profile of Bej FeederPre and Post Akshay Prakash Yojana Hours

  12. Bej Village – Daily Units Consumed Impact Analysis: Kalvan Division Load Profile of Kalvan Division-Typical Day Pre and Post Akshay Prakash Yojana In MU

  13. Impact Analysis Load Profile of Sanganmer Division Pre and Post Akshay Prakash Yojana

  14. Impact Analysis Load Profile of Nasik Division Pre and Post Akshay Prakash Yojana

  15. Impact Analysis Load Profile of Nasik U/ Chadigaon Division Pre and Post Akshay Prakash Yojana

  16. Akshay Prakash – Kandagaon yojana

  17. Akshay Prakash – Kandagaon yojana

  18. Akshay Prakash YojanaMahaVitaran Initiatives Educate Need for better utilisation as electricity is scarce and precious ; Educate to remove pilferage and avail continuous supply Communicate Consumer awareness programs ; advertisements, workshops, video films and school visits Technical Support Assured light load in evening peak time; Load Monitoring to ensure that demand remains within 20% Recognition Recognise and Felicitate villages ; Visits by Energy Minister and MD MahaVitaran

  19. Thank you