Culvert Inventory Plan. Statewide Culvert Asset Management (SCAM) Recommendations January 23, 2013. Culvert Inventory Plan. Overview Plan Components Resourcing Plan Organization Chart Project Milestones Budget Other Agency Considerations Next Steps Questions.
E N D
Culvert Inventory Plan Statewide Culvert Asset Management (SCAM) Recommendations January 23, 2013
Culvert Inventory Plan • Overview • Plan Components • Resourcing Plan • Organization Chart • Project Milestones • Budget • Other Agency Considerations • Next Steps • Questions
Overview: Goal: • Support project scoping for 2016 – 2018 STIP • Deliver inventory and condition assessment • Identify priority culverts needing repair or replacement • HMT “Priority Corridor Routes” Recommendations: • Basic Condition Application + Advanced Condition Application (BCA + ACA) • Resourcing Plan
Non-interstate: 1000 miles Completed: 600+ miles Remaining: 400 miles Interstate: 700 miles
Resource Plan • Centralized project management • Full-time project commitment • Field Crews – develop recruitment pool • Supplement with contractors/consultants where needed • IT/GIS • Project Management
Culvert Inventory Target Milestones Note: No significant field work during winter months (Nov 2013 – March 2014)
Other Agency Considerations Maintenance Involvement • Initial local knowledge • 1 employee, 1 day/section • Traffic control in Portland and like areas • Options for providing prep work (if available) • Rotational Opportunities Other ODOT staff involvement • Rotational Opportunities
Other Agency Considerations Non–Priority Corridor Culverts • Current culvert inventory efforts have been stopped but should be able to resume in Spring 2013. • Field crews must attend approved training • May require additional resources to provide support
Plan: Next Steps • Hire Project Manager • Establish Steering Committee • Report back to Leadership Teams • HMT: Quarterly?