300 likes | 454 Views
FHWA VERTICAL CONSTRUCTION SCAN. Jerry R. Blanding, J.D., Innovative Contracting Engineer, Federal Highway Administration. AASHTO Highway Subcommittee on Construction: 2005 Summer Meeting. PRESENTATION OUTLINE. Study Objectives Methodology Findings Recommendations. STUDY OBJECTIVES.
E N D
FHWA VERTICAL CONSTRUCTION SCAN Jerry R. Blanding, J.D., Innovative Contracting Engineer, Federal Highway Administration. AASHTO Highway Subcommittee on Construction: 2005 Summer Meeting
PRESENTATION OUTLINE • Study Objectives • Methodology • Findings • Recommendations
STUDY OBJECTIVES FHWA asked CERF to: • Conduct study and scan tours to identify technologies and processes employed in the vertical building construction industry that will enhance construction and life-cycle performance for highways and bridges. • The premise is that sectors can learn from other sectors.
METHODOLOGY • STEERING COMMITTEE • DISCUSSION FRAMEWORK DOCUMENT • INTEREST PROFILES • MEETINGS IN THREE METRO AREAS • New York City, NY • Chicago, IL • Los Angeles, CA • COMMUNICATION & COLLABORATION • Conference Calls • E-mail • eRoom • FINAL REPORT • OPTIONAL WORKSHOP TO DISCUSS IMPLEMENTATION
SCAN TEAM • FHWA • Ian Friedland, P.E., Team Leader - Office of Infrastructure • Jerry Blanding, J.D. - Innovative Contracting Engineer • Gary L. Brown, P.E. - Eastern Federal Lands Highway Division • Bob Kogler- Turner-Fairbank Highway Research Center
SCAN TEAM • FHWA (Continued) • Dr. Cheryl Allen Richter, P.E. -Highways for LIFE Program • Charles J. Churilla, P.E. - -Highways for LIFE Program • Dan Sanayi, P.E. - Office of Asset Management
SCAN TEAM • STATE HIGHWAY DEPARTMENTS • Don Arkle, P.E., Alabama DOT • Steve DeWitt, P.E., North Carolina DOT • David Hohmann, P.E., Texas DOT • M.G. Patel, Pennsylvania DOT • NACE • Alan Forsberg, P.E. • AASHTO • Cameron Kergaye, P.E.
SCAN TEAM • OTHERS • Jon Magnusson, P.E., Magnusson Klemencic • John Dick, PCI • CERF STAFF • Michael Goode, P.E., P.M.P., Project Manager • Dr. Amar Chaker
NEW YORK CITY • HOSTED BY WEIDLINGER ASSOCIATES, INC. • LOCAL LEADER: DAVID PALMER, ARUP • PRESENTATIONS • Jim Lammie, Parsons Brinckerhof • Jeremy Isenberg, Weidlinger Associates • Jon Magnusson, Magnuson-Klemencic • Charles DeBenedittis, Tishman-Speyer
Dave Palmer, ARUP • James Dall, New York Dormitory Authority • David Scott, ARUP • Nancy Hamilton, ARUP • LUNCH SPEAKER: Frank Lombardi, Port Authority of New York and New Jersey
FIELD TRIP • Jamaica Station Air Train – John Reed, Bechtel • Kennedy Airport Terminal 4 – Nancy Hamilton, ARUP • NY Times Building Mock-up – Glen Hughes, New York Times
CHICAGO • HOSTED BY SOM • LOCAL LEADER: WILLIAM BAKER, SOM • PRESENTATIONS • Bill Moody – The John Buck Company • Harry Walder – Walsh Construction • Ross Wimer – SOM • John Zils – SOM
Alice Hoffman, Hoffman Management Consultants • Mark Simonides, Turner • Joe Burns, Thornton Tomasetti • Joe Dolinar, Lohan Caprile Goettsch • John Padoven, Bentley Systems, • Kristine Fallon, Kristine Fallon Associates, Inc • LUNCH SPEAKER: Dr. Henri Petroski
FIELD TRIP • Soldier Field (Joe Burns, Thornton- Tomasetti) • 1 S. Dearborn (HKSE)
LOS ANGELES • HOSTED BY DMJM-HARRIS (AECOM) • LOCAL LEADER: Ed MCSPEDON, HNTB • PRESENTATIONS • Robert Parkridge, Seismic Structural Design Associates • Owen Hata, Nabih Youssef Associates • William Cook, URS • Matt McDole, E-470 Public Highway Authority
Ed McSpedon, HNTB • Gerry Seelman, DMJM-HARRIS (AECOM) • Dr. Frankie Banerjee • Tim Buresh and Jim Connell, Los Angeles Unified School District • LUNCH SPEAKER: Gil Garcetti
FIELD TRIPS • Frank Gehry Partners Studio • Los Angeles Cathedral • Caltrans District 7 Headquarters • Walt Disney Concert Hall
PREVIEW OF FINDINGS • “NUGGETS” IN 15 AREAS • Use Technology More Effectively (web-based project management, 3D, 4D) • Early Contractor Involvement • Risk • Ownership of Process – Roles and Responsibilities • Aesthetics • Marketing and Communications • Project Management
PREVIEW OF FINDINGS (Continued) • Process Flexibility – Value Engineering • Busting Barriers • Streamlining • Building Business Model – Financing • Procurement • Scope Definition – Quality • Lifecycle Considerations • Insurance Impact
STAY TUNED! • FINAL REPORT SUBMITTED JUNE 20, 2005 • AN OPTIONAL WORKSHOP TO DISCUSS IMPLEMENTATION IS BEING CONSIDERED