Accelerator Assembly & Installation Planning Gregory Fries Project Engineer, Accelerator Systems Division ASAC Review of NSLS-II October 14-15, 2010
Outline • Storage Ring Magnet/Girder Integration • Phasing of Installation • Coordination with Conventional Facilities • Storage Ring Installation • Injector Installation • Storage and Rigging • Experimental Installation • Magnetic Measurement Lab • Labor Profile • Challenges • Summary
Key Aspects of Production and Installation Accelerator Production – • We procure injector sub-systems (Linac, Booster Ring) • We build (integrate) Transfer Lines, B-RF and SR components Accelerator Installation – • Storage Ring BNL • Storage Ring RF BNL w/ vendor installing transmitter • Booster RF BNL • Transport Lines BNL • Linac Vendor w/ BNL oversight • Booster Ring Vendor using BNL technicians for all hands–on work w/ BNL oversight
Magnet/Girder Integration Building 902 1 Magnet measurement 2 Magnet inspection 3 Girder preassembly 4 Dipole measurement 5 Front-end test set-up 6 Environmental room Fully Functional and Equipped Environmental Room (DT < 0.1 C ) for 30 mm Precision Alignment Building 902
Magnet/Girder Integration Workflow In Cleanroom • 90 MP girders • 60 dipole girders
Magnet/Girder Precision Alignment Workflow • Will be learning curve • In beginning, 2nd survey will occur • Workflow flexible based on component availability • Prec. Alignment without all magnets • Final magnets installed in tunnel • Pre-assemble and store partially completed girders • 2 girders /months 2 girders / week • @ 18 months (incl. learning curve effect) • Starting March, 2011 Finish Oct, 2012
Installation and Operation Zones 1 • Key Points: • Utilities and infrastructure are segmented as shown by pentant • Temp walls constructed separating BOD segments • Installation and testing within these segments • Linac/Booster test/commission may overlap with construction activities B RF RF 2 5 L 4 3
Coordination with Conventional Facilities • Lay-down area for storage containers outside of building • Beneficial occupancy conditions for installation • Systematic hand-off of completed building zones • BNL BORE process to be used for occupancy permits • Access to space with beneficial occupancy for installation while construction continues • Interaction of installation activity with LOB construction to avoid potential interference • CFD represented in ASD installation meetings • ASD reviewing all CFD ECNs for impact
Storage Ring Systems Installation Per Pentant • Mechanical Utilities • Electrical Utilities • Magnet/Girder Assemblies • Vacuum System • Power Supplies • Beam Instrumentation • Controls Where Applicable • RF Systems • Beam Line FEs, DWs, IDs • Injection Straight
High-Level Installation Schedule • Installation is gross equipment location, connections, and component testing • Subsystem testing, integrated testing and commissioning will follow
Storage Ring Pentant 1 Installation: Week 2 22 23 24 25 26 27 Mezzanine Exp’l floor 23 25 26 27 28 24 Tunnel • Activities: • Prepare tunnel • Stage components on floor • Start cable tray on mezzanine Status: ~ 1/3 of material in building Installation starting Service Building
Storage Ring Pentant 1 Installation: Week 6 22 23 24 25 26 27 Mezzanine Exp’l floor 23 25 26 27 28 24 Tunnel • Activities: • Tray and manifolds in place in tunnel • Racks well underway • Stage cable and start pulling Status: Most material in building Installation on mezzanine Installation in tunnel Service Building
Storage Ring Pentant 1 Installation: Week 12 22 23 24 25 26 27 Mezzanine Exp’l floor 23 25 26 27 28 24 Tunnel • Activities: • Girder installation • Populating racks • Terminating cables Status: Most wiring pulled Process utilities connected Service Building
Storage Ring Pentant 1 Installation: Week 20 22 23 24 25 26 27 Mezzanine Exp’l floor 23 25 26 27 28 24 Tunnel • Activities: • Final utility connections • Equipment shakeout Status: All equipment in place System testing underway Service Building
SR RF Installation • BOD date for RF building – Mar 23, 2011 • All systems delivered directly to RF building • RF Transmitter w/ klystron installed by vendor • Remaining RF systems installed by BNL
Injector Installation Phases • Mechanical & Electrical Utilities • Booster RF • LtB Transport Line Part 1 • Through wall, up to vac valve in booster vault, needed to commission linac • Linac • Booster • LtB Transport Line Part 2 • TL complete, need to commission booster • BtS Transport line Part 1 • Up to beam dump, needed to commission booster
Injector Installation Phases Layout Phase Separation (end of injector install) BtS TL Part 1 Booster RF Booster Linac LtB TL Part 2 Phase Separation LtB TL Part 1
Transport Line Magnet/Girder Integration • Preassembly in injector service building • Magnets, Girders, Vacuum, Diagnostics • Pre-alignment • Pre-test
Injector Installation Schedule • Booster RF split into two phases: BR RF cavity & BR RF transmitter • BtS Part 2 is considered part of SR installation
Component Storage & Staging • Reviewing storage requirements for each ASD group • Finalizing number of sea containers needed at site for storage • Approx. 10-15 - 8 ft x 8 ft x 40 ft containers • Experimental floor will be used for staging • Temporary cages may be installed
Lay-down Areas for Sea Containers Lay-down Area for SR Component Storage Containers Outside Access to Experimental Floor for Unloading (column 102) Lay-down Area for Linac & Booster Containers
Rigging Summary & Status • Reviewed requirements with the riggers • Will have two dedicated 3-man rigging teams • ASD installation coordinator will be contact to riggers • Rigging requirements will continue to be detailed
Component Transport • Forklift has been ordered • 10,000 lbs. capacity • 208” max lift to reach mezzanine from experimental floor • Dolly system will be used for magnet/girder assembly transport
Installation Schedule • Installation schedule currently being reviewed with each CAM and expanded for completeness, durations and logic • Emphasis will be placed on installation schedule flexibility based on building and component availability
Experimental Installation • XFD Installation follows ASD installation by pentant • Activities Per Beamline • Pentant Hand-off from ASD • Pentant Clean-up • Hutches • Utilities • Beamline Components
Magnetic Measurement Lab • 46’ x 25’ environmental room for ID measurement • Located in building 832 • 95% Complete • BORE scheduled for Oct. 18, 2010 • Measurement equipment to start arriving in Nov. 2010 • No safety incidents during construction
Installation Labor Profiles • Installation ramps up midway through FY 11 • Peak effort is 108 FTE • ASD significant effort by term technicians and contract labor • XFD extensive use of installation labor provided by suppliers • Note that this is project labor only; does not include additional beamlines or beamline transfer
Challenges • Coordinating multiple activities/teams/access during installation • Maintaining component delivery schedules • Adapting to delivery delays • Will epoxy floor installation on experimental floor impact ASD installation schedule? • XFD installation needs might conflict with required flexibility of ASD installation schedule (hand-over delays)
Summary • Magnet/Girder integration plan well defined • Installation schedule in process of being expanded and re-evaluated • Focus on flexibility in installation schedule based on availability of building and components • Building to be available for start of ASD installation Feb ‘11 • Detailing installation logistics • Rigging and storage requirements in process • Good communication established with CFD & XFD • Required labor profile in place • Conclusion: Installation Planning is very advanced