WATER MANAGEMENT AND CHALANGES IN JŪRMALA 17.03.2015 JŪRMALAS ŪDENS
STORMWATER COLLECTION OUTLINES
STORMWATER CATCHMENTS AND FLOWS: CATCHMENT AREA ESTIMATED – 2897 ha CALCULATED ANNUAL FLOW – 5 500 000 m3 (4200000 in summer) MINIMUM – 270 000 m3/month MAXIMUM – 700 000 m3/month OUTLETS – 24 (8 – Riga Gulf, 13 – Lielupe, 2 – Vecslocene, 1 – Veršupīte) Total pipeline length – 50,7 km Pumping Stations – 2 (Kauguri, Majori)
Drainage and Stormwater System ManagementFinancing and Expenses 2013 - 2015
SANITARY SEWER Vaivari, Asari, Melluži, Jaundubulti, Valteri, Krastciems
SANITARY SEWER Dubulti, Majori, Dzintari, Lielupe, Buļļciems, Priedaine
SLOKA WWTP. Flows, Loads, Outlet requirements Inlet flows are as follows: Design year 2015 Connected population 32 440 Daily average flow 9000 m3/d Design flow, qdim 500 m3/h Max flow to pre-treatment 1500 m3/h Max flow to main process 750 m3/h Inlet loads are as follows: SS 2320 kg/d 256 mg/l COD 4460 kg/d 493 mg/l BOD5 2140 kg/d 236 mg/l Total-N 480 kg/d 53 mg/l Total-P 80 kg/d 9 mg/l Required outlet concentrations SS 35 mg/l COD 125 mg/l BOD5 25 mg/l Total-N 15 mg/l Total-P 2 mg/l
Sloka, Kauguri construction works. 2013 - 2015 Construction works: • Water Supply Network – 19 407m; • Gravity Sewers – 16 541m; • Rising mains – 1 256m; • 2 pumping stations
Melluži, Valteri construction works. 2014 - 2015 Construction works: • Water Supply Network – 13,3 km; • Gravity Sewers – 11,3 km; • Rising mains – 3 km; • 2 pumping stations
Kaugurciems, Vaivari, Asari, Melluži construction works. 2014 - 2015 Construction works: • Water Supply Network – 24,1 km; • Gravity Sewers – 7,7 km; • Rising mains – 1 km; • 2 pumping stations