1 / 8

Motivation for the new Linac4-to-PSB Half-Injection-Sector Test

Motivation for the new Linac4-to-PSB Half-Injection-Sector Test. B. Mikulec. Introduction (1). Follow-up of BCC from 18 October 2012 Preliminary conclusions from that BCC:

rianna
Download Presentation

Motivation for the new Linac4-to-PSB Half-Injection-Sector Test

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Motivation for the new Linac4-to-PSB Half-Injection-Sector Test B. Mikulec

  2. Introduction (1) • Follow-up of BCC from 18 October 2012 • Preliminary conclusions from that BCC: • Simple stripping foil test at start of L4T feasible, but half-sector test in L4Z problematic (losses due to implementation within final L4Z layout) • Installation in L4T line (after hor. bending) to be studied  see presentation Veliko BCC 22 April 2013 Ref: L4-T-EP-0002 rev 1.0

  3. Introduction (2) • Extremely compact and complex section, combining equipment from TE/ABT, EN/STI, BE/BI, TE/EPC, TE/VSC, TE/MPE. • Main motivations for sector test have been laid out in EDMS 1224575. Courtesy of L. Zuccalli BCC 22 April 2013

  4. What can be tested elsewhere • Integration issues, repair and intervention scenarios (incl. stripping foil exchange) with mechanical test stand • Stripping foil lifetime, stripping foil control and instrumentation including optimisation of screen and camera system, stripping foil efficiency and emittance growth with different foil types/thicknesses with stripping foil installation at start of L4T BCC 22 April 2013

  5. What could be tested in addition (1) • BSW3+4 • Powering and control of half of the chicane magnets • Current stability and interlocking • Stripping foil • More precise stripping efficiency measurement of H0 and H- • Interlocking of foil position • H0/H- dump • Aperture check • Temperature cross-check with simulated values  refine cooling requirements • Analysis of SiC material after removal (micro-cracks etc.; novel material!) • Interlocking (temperature and pressure drop – define operational thresholds) BCC 22 April 2013

  6. What could be tested in addition (2) • Special BLMs • Diamond BLMs (?) to measure secondaries close to H0/H- dump; evaluate operational conditions for foil degradation measurement and fast losses • H0/H- current monitor: new development! • General operational check incl. for example secondary emission suppression • Sensitivity check for H0 and H-; comparison to theory • Aperture check • Influence on measurement if beam passes besides the monitor (simulate circulating beam)? • Interlocking – essential for dump protection • Interlock system test for part of PSB injection (BIS + SIS) • Specific applications BCC 22 April 2013

  7. To be sorted out… • Planning • In parallel with Linac4 commissioning • Provide in time equipment, controls, applications • Location of control equipment, transformer etc. • Cabling • Support structures, special beam pipe connections… • Temporary downstream installation of dump (LBE/LBS line dump?) – could it be reused for L4T commissioning? • Water cooling of dump(s) BCC 22 April 2013

  8. Conclusions • Half-injection-section test would be extremely beneficial • From technical point of view for each sub-system • For risk reduction • For reduction of commissioning time for Linac4-to-PSB connection • It seems feasible to provide the required equipment for start of 2016 (Linac4 reliability run), but infrastructure availability to be checked • Test should happen first part of 2016 to be able to react to potential lessons learnt… • Installation should not perturb too much Linac4 commissioning BCC 22 April 2013

More Related